| 1 | Supply,Carraige upto site, Installation, testingand Commissioning of11/0.433KV,100 KVA 3-phase Distribution Transformers with Bimetallic Terminal Connectors Energy Level-2 |
| 2 | Supply, Carriage up to site, Erection, testing and commissioning ofSteel Tubular Pole, 9 Mtr. Long Pole(ST-410 SP33) with planting depth of 1/6 th of the height of the pole, (9 mtr. Long ) |
| 3 | Supply, Carriage up to site, Erection, testing and commissioning ofSteel Tubular Pole, 8 Mtr. Long Pole(SP15) with planting depth of 1/6 the of the height of the pole, (8 mtr. Long ) |
| 4 | Supply ,Carriage up to site, laying ,stringing, tensioning , binding of ACSR Conductor, (30mm2 ACSR Conductor) |
| 5 | Supply,Carraige upto site, and fixing ofGI Channel Iron x-arm 9\" long100x50x6mm including suitable clamps/collars (32 kg/No.) |
| 6 | Supply,Carraige upto site, and fixing ofGI Channel Iron x-arm 9\" long75x40x6mm including suitable clamps/collars (22 kg/No.) |
| 7 | Supply, Carriage up to site, and fixing of GI V-Cross & F-Top duly fabricated as per REC Standards including clamps(50x6 mm) & GI Nuts & Bolts (19 kg/No.) |
| 8 | Supply, Carriage up to site, Installation, testing and Commissioningof GI Angle iron 9\" length 50X50X6mm along with complete clamping arrangement (for Tranformer Belting) (16 KG/No.) |
| 9 | Supply, Carriage up to site, Installation, testing and Commissioning o 11 kV Disc Insulators (polymer) Complete with fitting(45KN) |
| 10 | Supply, Carriage up to site, Installation, testing and Commissioning of danger Plates |
| 11 | Supply, Carriage up to site, Installation, testing and Commissioning of 11 KV Pin Insulators (Polymer) with Pins (5KN) |
| 12 | Supply, Carriage up to site, Installation, testing and Commissioning of 11 kV G.O AB Switch , 3-phase, 3 pole 400A polymerStn. Type |
| 13 | Supply, Carriage up to site, Installation, testing and Commissioning of 11 kV Horn Gap Fuse Set 3phase 400A polymerStn. Type |
| 14 | Supply, Carriage up to site, Installation, testing and Commissioning of LT Fuse Sets (Pre-fabricated) |
| 15 | Supply, Carriage up to site, Installation, testing and Commissioning of Gapless Surge Arrestor,9 KV ,10 KA ,LA with PorcelainStn. Type |
| 16 | Supply, Carriage up to site, laying ,stringing, tensioning , binding of 1.1 KV grade, 185 sq-mm 1-corePVC Cable |
| 17 | Supply, Carriage up to site, Installation, testing and Commissioning of Sundry items like Aluminium lugs, Jumpers, Binding tapes etc. |
| 18 | Supply, Carriage up to site, Installation, testing and Commissioningof GI, LTStructure Mukhi type(with Shackles)(50x6 mm) as per RECStandard |
| 19 | Supply, Carriage up to site, and fixing of Galvanisednuts and bolts of sizes |
| 20 | SITC of Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2 Nos.), anchor plate (200x 200 x 6 mm), nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 21 | Providing, carriage, transportation, Installation etc. Earthing of substation --Excavation ofearth pit of dia650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mmx6 mmfor connection of transformer body, G.O Set & lightening arrestor Strip for neutral earthing of size 25 mmx6 mm for connection of transformer body, G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts, refilled with earth enhancement materials and earth Chamber made of brick masonry with RCC slab cover. |
| 22 | Providing, carriage, transportation, Installation etc. of Cement bottoming 1:2:4 mix as per REC standards 0.5cum/pole (Pit 600x600x1600 mm) for 9 MTR ST Pole |
| 23 | Earthing Complete by GI Rod 20mm 2.5 mtr long through GI Strip as per RECStandard. |
| 24 | Providing & Painting of Poles with one coat of Red Oxide and two coats of aluminium paint |
| 25 | Supply, Carriage up to site, Installation, of Sign Board (2X2 feet) along with required accessories like clamps, nuts and bolts etc. |