| 1 | Part-A: Foundation& Cable RunwayReinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : |
| 2 | (a) 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 3 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size). |
| 4 | Centering and shuttering including strutting, propping etc. and removal of form for : |
| 5 | (a) Lintels, beams, plinth beams, girders, bressumers and cantilevers. |
| 6 | (b) Columns, Pillars, Piers, Abutments, Posts and Struts. |
| 7 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level. |
| 8 | (a) Thermo-Mechanically Treated bars. |
| 9 | Smooth finishing of the exposed surface of R.C.C. work with 6 mm thick cement mortar 1:3 (1 Cement : 3 fine sand) |
| 10 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : |
| 11 | (a): Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 12 | Welding by gas or electric plant including transportation of plant at site etc. complete. |
| 13 | 12 mm cement plaster of mix : |
| 14 | (a): 1:6 (1 cement: 6 fine sand) |
| 15 | Finishing walls with water proofing cement paint of required shade : |
| 16 | (a): New work (Two or more coats applied @ 3.84 kg/10 sqm). |
| 17 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. |
| 18 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.. |
| 19 | (a): In cement mortar |
| 20 | Steel work welded in built up sections/ framed work including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. |
| 21 | (a) In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works. |
| 22 | PART -B ::Erection, Painting etc.Laboure charges for orienting and fixing all anchor bolts in position by usingtemplatesin true plumb & allignmentolt during concrecting of foundation beam / column as per approved drawingand direction of the Engineer-in-charge. |
| 23 | Carriage of tower materials for upto 21 MRoof Top Tower by mechanical transport from BSNL SSA Store,Kamrup Telecom District , located atDispur, Guwahatito the work site located any whereunder kamrup SSA, including sorting , numbering ,loading , unloading and stacking in countable manner atwork site etc. complete as per direction of the E - in-C. |
| 24 | Labour charge for errection of 20 M high roof top tower with existing anchor bolts including assembling, lifting, fitting and fixing in position themembers with the help of bolts, nuts, washer or as directed including antenna fixtures (approximate weight of tower shall be 4523.00 KG) keeping the verticallity of the errected tower on all sides within + 25mm (i.e. the bottom of the line joining the centre of the top of the tower and the centre of the base of the tower is within + 25mm from the centre of the base of the tower) taking all precautions against damage, accident, obtaining necessary insurance coverage against all risk etc complete as per approved drawing and direction of the E-in-C. |
| 25 | Painting15 M high roof top tower from top to bottom including bracings, landings, platforms, guard rails, runways etc with superior quality weather resistant LUXOL High-gloss or equivalent synthetic enamel paint (two or more coats) in international orange and white shade of approved brand and manufacture in equal alternate layers to give an even shade over and including a coat of Zinc Chromate yellow primer and a base coat of etching primer (BISON wash primer or equivalent)including scaffolding and taking all necessary safety precaution to protect human life. insuance coverage of labours etc complete as per direction of Engineer-in-Charge. |
| 26 | Add or deduct for painting oftowerabove/below 15 mtr height as per item No-16 of PART-B. |
| 27 | Supply hot dipped galvanised missing Tower material / members (if any) conforming to relevant IS codes as specified in BSNL Tower Manual, including welding, drilling holes, threading wherever necessary all complete as per drawing & direction of the Engineer-in-Charge.(This item shall be paid only on production of necessary certificate from the competant store authority regarding the quantity of store materials issued short along with the list thereof) |
| 28 | Supplying and fixing GI nuts & bolts (missing nuts & bolts) conforming to relevant IS codes as specified in BSNL Tower Manual of different size with required washers for errection of 40M tower.(This item shall be paid only on production of necessary certificate from the competant store authority regarding the quantity of store materials issued short along with the list thereof) |
| 29 | Part:C: Electrical worksProviding Pit Earthing with coper earth plate of size 600 x 600 x 3mm thick placed vertically in the excavated pit of size 900 x 900 x 3000mm . The plate shall be connected with 50x6 mm GI strips.The bolts,nuts washers shall be copper.The pit shall be filled with charcoal and salt upto (Item No.1 Contd)a depth of 900mm and remaining portion with black soil without stones. The masonry chamber shall be provided at ground level of size 300 x 300 x 300mm with 125 mm thick brick work with bricks of CD 50 in CM 1:4 (1cement:4 coarse sand) made on 700X700X150 mm base concrete 1:4:8 (1-cement:4-coarse sand:8-graded stone aggt. with 40mm nominal size ) with a hole in the middle to pass the GI pipe of 20 mm dia with a provision for funnel and provided withCI frame and cover (wt of cover not less than 4.5 kg/sqm) with locking arrangements. The funnel shall be fixed with wire mesh. The manhole cover shall be painted and marked with the value of earth resitance including measurement of earth resistance by earth megger etc complete as per direction of the E-in-C.The value of earth resiatance should be less than 0.50 O and nothing extra shall be paid for getting extra resiatance less than 0.50 O. |
| 30 | Providing & FixingLED avaiation lamp of single bulb system of Bajaj , Binoy or equivalent approved brand at the top of Tower with day and night automatic timer switch , MCB switch, armoured insulated copper cable from aviation lamp to MCB switch with necessary fixturesetc complete as per direction of the E-in-C. |
| 31 | Supplying & laying of 2x1.5 Sqmm armoured copper conductor Cable \"Armoured/ ISI PVC Insulated & sheathed cable\" of approved quality and brand including copper terminations/ Lugs etc. all complete as per directions of Engineer- in-charge. Sheath earthing for the armoured cable shall be done at minimum of two points on the tower as per the standards specified. |
| 32 | Supplying and making interconnection of thetower by G.I. stripes of size 50X 3 mm and the same G.I.strip shall be connected to the pit earth from the pole taking down along the wall of the building by suitable nuts & bolts etc complete as perdirection of the Engineer in Charge. (The rate is inclusive of required scaffolding ,clamps for fixing flats on vertical walls etc complete and nothing extra shall be paid ) |
| 33 | Providing and fixing copper Lightening arrester of 1500mm length, 25mm dia, hollow tube and of wall thickness not less than 1.60 mm including tinning the bottom portion of the spike for a length of not less than 150mm and connecting to the G.I. strip of size 50 x 3mm by means of clamps and 2nos 10mm dia brass bolts and nuts all complete as directed by the Engineer-in-charge. The lightening spike shall be fixed to the tower with Teflon sheet to avoid direct contact with the tower. |
| 34 | Providing and laying 2.00mm thick anti-static PVC sheet flooringof approved brandand shade on smooth finished and damp proof base using adhesive (Dunlop SR-458 or Fevicol SR-998 or equivalent )including rolling with light wooden roller making smooth etc.complete as per direction of the Engineer in Charge. |
| 35 | Providing and laying / fixing copper strip of size 30 X 0.20 mm below antistatic PVC sheet flooring ,fixing with C.P. brass screws,making continuouscontact of carbon layer of the flooring sheet with the copper strips at joints for making continuous conductivityand proper earthing of the flooring and finally connecting the copper strip to the earth point all complete as per direction of the Engineer in Charge. |