Power Government Departments Closing in 0 days TDR #29095363

Various Jobs During Upcoming Overhauling At Ahp-Mm Area Of 215Mw Of Unit 5 At Btps.- 1 Bottom Ash Hopper 2 Bottom Ash Hopper Jet Pump Nozzle-Checking & Servicing / Replacement 3 Feed Gate, Feed Sump Checking & Servicing 4 Bottom Ash Hopper Refract

Issued by Government Departments · Bandel Thermal Power Station, Hooghly., West Bengal
Tender Value
24.59 Lakhs
Estimated cost
Bid Submission
27 Sep 2021
0 days left
EMD
42000
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Bandel Thermal Power Station, Hooghly. → West Bengal
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Various Jobs During Upcoming Overhauling At Ahp-Mm Area Of 215Mw Of Unit 5 At Btps.- 1 Bottom Ash Hopper 2 Bottom Ash Hopper Jet Pump Nozzle-Checking & Servicing / Replacement 3 Feed Gate, Feed Sump Checking & Servicing 4 Bottom Ash Hopper Refractory ( Excluding Materials ) Replacement. 5 Bottom Ash Hopper Refractory Cooling Line Maintenance ( 18 No. Orifice Plate Checking / Replacement With Valve Installation ) 6 Bottom Ash Hopper Jetting Nozzle Checking / Servicing / Replacement 7 Clinker Grinder Overhauling 8 Coarse Ash Hopper 9 Coarse Ash Hopper O / L Valve Replacement 10 Wet Tower 11 Air Separator Tank Door Fabrication With Painting 12 Throat Piece Replacement Hydro Vector 13 Tail Piece Replacement Of Hydro Vector 14 Nozzle Replacement Of Hydro Vector 15 Wet Tower 16 Dome Velve ( 100 / 150 / 200 / 300 Nb ) Checking / Servicing / Replacement 17 Plug Valve ( 80Nb ) Replacement 18 Glove Valve 150 / 200 Nb Replacement 19 Gate Valve 200Nb Of Pd Pump Replacement 20 Knife Gate Valve 300Nb Servicing 21 Material Handling Valve Servicing / Replacement 22 Dry Ash Conveying Line Valve Installation 23 Fabrication Work 24 Coarse Ash Hopper 1” / 2” Pipe Line Fabrication Job 25 Dry Conveying Pipe Line Different Area Fabrication Work1 ) Surge Hopper Checking &Need To Base Servicing2 ) Bottom Hopper Flange Checking& Gasket Replacement10 Nos 26 1 ) Surge Hopper Checking &Need To Base Servicing2 ) Bottom Hopper Flange Checking& Gasket Replacement10 Nos 27 1 ) Pd Pump T Fabrication ( 04 ) Nos2 ) Pd Pump Air Line Header ( 100Nb&65Nb ) De-Metering &Need To Base Fabrication Work With Painting3 ) Service Water Line Shade Fabrication Work. 28 Cable Tray Support Leg Fabrication Work In Front Of Bottom Hopper 29 Cac Compressor Cooling Water Line Replacement With Valve & Painting 30 Vacuum Line Champing / Support At Different Area 31 1 ) Silo Target Box Checking& Need To Base Servicing Work With Ss Liner Plate.2 ) Ahp-B Pass Bypass Line Approach For Maintenance Work. 32 Wet Tower Gratings Fabrication & Ash Water Pump House Checkerplate Fabrication Work 33 Wet Tower Shade Fabrication Work With Shade & Painting ( Shade Provided Vendor Shade Make-Tata / Sail / Jindal ) 34 Vacuum Pump House Ladder Fabrication Work With Painting For Overhauling Of Chain Pulley Block 35 Pipe & Bend 36 New Erw Pipe Installation With Flange Fabrication Work 37 300 Nb Ba Slurry Line Checking, Dismantling, Rotation Need Based Replacement Including Ash Pond Area 38 200 Nb Fly Ash Line Checking, Rotation & Need Based Replacement &De-Metering 39 200 Nb Ci Bends / Y Piece Checking And Replacement & De-Metering 40 Pad & Gasket 41 Esp Pad Change, Surge Hopper Pad Change 42 Total Fly Ash System Line ( 200 Nb ) Gasket Replacement ( Hopper To Ish, Hopper To Air Separator Tank 43 Equipment 44 Conveying Compressor Total Overhauling Job 45 Vacuum Pump Total Overhauling Job 46 Modification Work 47 Esp Fluidised Air Line Modification ( One No. Branch ) 48 Gst

BOQ

Sub. :Various jobs during upcoming Overhauling at AHP-MM area of 215MW of Unit 5 at BTPS
Sl. No. Item Description
1BOTTOM ASH HOPPER
2Bottom Ash Hopper jet pump nozzle-Checking & servicing/replacement
3Feed Gate, Feed Sump Checking & servicing
4Bottom ash hopper refractory (excluding materials) replacement.
5Bottom ash hopper refractory cooling line maintenance (18 no. orifice plate checking/replacement with valve installation)
6Bottom ash hopper JETTING NOZZLE checking/ servicing/ replacement
7Clinker Grinder overhauling
8COARSE ASH HOPPER
9Coarse Ash Hopper O/L valve Replacement
10WET TOWER
11Air separator tank door fabrication with painting
12Throat piece replacement Hydro vector
13Tail piece replacement of Hydro vector
14Nozzle replacement of Hydro vector
15WET TOWER
16DOME VELVE (100/150/200/300 NB) checking/ servicing/ replacement
17PLUG VALVE (80NB) replacement
18GLOVE VALVE 150/200 NB replacement
19GATE VALVE 200NB of PD pump replacement
20Knife gate valve 300NB servicing
21Material Handling Valve servicing/ replacement
22Dry ash conveying line valve installation
23FABRICATION WORK
24Coarse ash hopper 1”/2” pipe line fabrication job
25Dry Conveying pipe line different area Fabrication work1)Surge hopper checking &need to base servicing2)Bottom Hopper flange checking& gasket replacement10 nos
261)Surge hopper checking &need to base servicing2)Bottom Hopper flange checking& gasket replacement10 nos
271)PD pump T Fabrication (04) nos2)PD pump Air line header(100NB&65NB) de-metering &need to base fabrication work with painting3)Service water line shade fabrication work.
28Cable Tray support leg fabrication work in front of Bottom Hopper
29CAC compressor cooling water line replacement with valve & painting
30Vacuum line champing/support at different area
311)Silo Target box checking& need to base servicing work with ss liner plate.2)AHP-B Pass bypass line approach for maintenance work.
32Wet tower gratings fabrication & Ash water pump house checkerPlate fabrication work
33Wet tower shade fabrication work with shade & painting (Shade provided vendor shade make-TATA/SAIL/JINDAL)
34Vacuum pump house ladder fabrication work with painting for overhauling of chain pulley Block
35PIPE & BEND
36New ERW pipe installation with flange fabrication work
37300 NB BA Slurry line checking, Dismantling, Rotation need based replacement including Ash pond area
38200 NB Fly ash line checking, Rotation & Need based Replacement &DE-Metering
39200 NB CI Bends/Y piece Checking and replacement & DE-Metering
40PAD & GASKET
41ESP PAD change, Surge Hopper Pad change
42Total Fly ash system line (200 NB) Gasket replacement (Hopper to ISH,Hopper to air separator Tank
43EQUIPMENT
44Conveying Compressor total overhauling job
45Vacuum pump total overhauling job
46MODIFICATION WORK
47ESP Fluidised Air Line Modification (one no. branch)
48GST

AI Tender Summary

OUR REF NO 29095363
AUTHORITY Government Departments
TENDER VALUE 24.59 Lakhs
LAST DATE 27-09-2021
Authority
Authority Name West Bengal Power Development Corporation Limited
Work Description Various Jobs During Upcoming Overhauling At Ahp-Mm Area Of 215Mw Of Unit 5 At Btps.- 1 Bottom Ash Hopper 2 Bottom Ash Hopper Jet Pump Nozzle-Checking & Servicing / Replacement 3 Feed Gate, Feed Sump Checking & Servicing 4 Bottom Ash Hopper Refractory ( Excluding Materials ) Replacement. 5 Bottom Ash Hopper Refractory Cooling Line Maintenance ( 18 No. Orifice Plate Checking / Replacement With Valve Installation ) 6 Bottom Ash Hopper Jetting Nozzle Checking / Servicing / Replacement 7 Clinker Grinder Overhauling 8 Coarse Ash Hopper 9 Coarse Ash Hopper O / L Valve Replacement 10 Wet Tower 11 Air Separator Tank Door Fabrication With Painting 12 Throat Piece Replacement Hydro Vector 13 Tail Piece Replacement Of Hydro Vector 14 Nozzle Replacement Of Hydro Vector 15 Wet Tower 16 Dome Velve ( 100 / 150 / 200 / 300 Nb ) Checking / Servicing / Replacement 17 Plug Valve ( 80Nb ) Replacement 18 Glove Valve 150 / 200 Nb Replacement 19 Gate Valve 200Nb Of Pd Pump Replacement 20 Knife Gate Valve 300Nb Servicing 21 Material Handling Valve Servicing / Replacement 22 Dry Ash Conveying Line Valve Installation 23 Fabrication Work 24 Coarse Ash Hopper 1” / 2” Pipe Line Fabrication Job 25 Dry Conveying Pipe Line Different Area Fabrication Work1 ) Surge Hopper Checking &Need To Base Servicing2 ) Bottom Hopper Flange Checking& Gasket Replacement10 Nos 26 1 ) Surge Hopper Checking &Need To Base Servicing2 ) Bottom Hopper Flange Checking& Gasket Replacement10 Nos 27 1 ) Pd Pump T Fabrication ( 04 ) Nos2 ) Pd Pump Air Line Header ( 100Nb&65Nb ) De-Metering &Need To Base Fabrication Work With Painting3 ) Service Water Line Shade Fabrication Work. 28 Cable Tray Support Leg Fabrication Work In Front Of Bottom Hopper 29 Cac Compressor Cooling Water Line Replacement With Valve & Painting 30 Vacuum Line Champing / Support At Different Area 31 1 ) Silo Target Box Checking& Need To Base Servicing Work With Ss Liner Plate.2 ) Ahp-B Pass Bypass Line Approach For Maintenance Work. 32 Wet Tower Gratings Fabrication & Ash Water Pump House Checkerplate Fabrication Work 33 Wet Tower Shade Fabrication Work With Shade & Painting ( Shade Provided Vendor Shade Make-Tata / Sail / Jindal ) 34 Vacuum Pump House Ladder Fabrication Work With Painting For Overhauling Of Chain Pulley Block 35 Pipe & Bend 36 New Erw Pipe Installation With Flange Fabrication Work 37 300 Nb Ba Slurry Line Checking, Dismantling, Rotation Need Based Replacement Including Ash Pond Area 38 200 Nb Fly Ash Line Checking, Rotation & Need Based Replacement &De-Metering 39 200 Nb Ci Bends / Y Piece Checking And Replacement & De-Metering 40 Pad & Gasket 41 Esp Pad Change, Surge Hopper Pad Change 42 Total Fly Ash System Line ( 200 Nb ) Gasket Replacement ( Hopper To Ish, Hopper To Air Separator Tank 43 Equipment 44 Conveying Compressor Total Overhauling Job 45 Vacuum Pump Total Overhauling Job 46 Modification Work 47 Esp Fluidised Air Line Modification ( One No. Branch ) 48 Gst
Basic Detail
Tender No WBPDCL/BTPS/NIT/E1946/21-22
Bidding Type Tender
Location
City Bandel Thermal Power Station, Hooghly.
State West Bengal
Key Dates
Publish Date 03 Sep 2021
Submission Date 27 Sep 2021
Open Date 29 Sep 2021
Finance
Tender Value 24.59 Lakhs
Tender Fee Ref. Documents
EMD 42000
Exemption Not Available
Document List
6b676558-1a49-45d4-8b0c-fa8c61bd64c0.html
BOQ_654836.xls
Tendernotice_1.pdf

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Sep 03, 2021
11:30 IST

Tender Published

Tender notice published.

Completed
Sep 27, 2021
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
Sep 29, 2021

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
html

6b676558-1a49-45d4-8b0c-fa8c61bd64c0.html

xls

BOQ_654836.xls

pdf

Tendernotice_1.pdf