| 1 | Earth work in excavation for structures in all depths as per drawing and M.O.R.D.technical specification section 300 and 1600 including setting out, construction of shoring and bracing, removal of stumps and other deleterious materialsand disposal in all lead and lift including dressing of sides and bottom and back filling in trenches with excavated Suitable materials. All work of rock cutting by blasting shallbecarried out by taking all necessary precautionsagainstsoil erosion, damage to hill side, water pollution etc. and to protect stability ofhill side rock shall be excavated with chiseling and wedging out rock (where blasting is prohibited). All earth work in cutting/excavation including rock excavation shall be carried out true to lines grades, side slopes, width, camber super elevation and level as shown on the drawings or as directed by the Engineer-in-Chargehauling and stacking of materials useful for construction at suitable sites and safe disposal of unsuitable cut materials in specified manner, filling of unevenness blind age and finishing the road tospecifieddimensionorasdirectedbythe Enginer-in-Charge.Ifthefoundation ofthe structureisinanareawithstagnant wateror water is met with in the excavation due to spring seepage rain and other causes it shall be removed by suitable diversion, bailing out or pumping as directed and the area of the foundation or embankment shall be kept dry. Any loss to the public or private property during the course of excavation shall be the whole responsibility of the contractor which shall have to be duly compensated by him at his own cost in all cases.The rate isincluding royality, Malkana,Toll tax, sale tax, GST orother taxes imposed by the Government. |
| 2 | Providing and layingMechanically mixed and vibratedconcretefor plain / reinforced concretenominal mix 1:5:10 ( one cement is to five sand is to ten graded crushed stone aggregate 40 millimeter (forty millimeter) nominal size in or under water and curing complete for 14 (fourteen) days, in open foundationsfor all type of structures and the like drain etceteraincluding pumping or bailing out water(surface and sub soil water) dewatering for all depths and any quantum of water including removal of slush which may arise at the time of laying under water complete for all heights / depths including the cost of form work completeas per drawings and M.O.R.D. technical specification Clauses 802,803,1202 and 1203 or as directed by the Engineer-in-Charge including carriage of material within all leads, lifts and other incidentals. The rate includes octroi,royality,Malkana,Toll tax, GST or any other taxes imposed by the Government. |
| 3 | Back filling with granular material behind abutments, wing walls, return walls , retaining wallcomplete as per drawing and M.O.R.D. technical specification clause 1203 and section 1604 , as per direction of Engineer-In-Charge including hauling /carriage of materials to various location through all modes of transportation in all leads, lifts and other incidental complete in all respect. The rate isincluding royality, Malkana,Toll tax,GST orother taxes imposed by the Government. |
| 4 | Providing weep holes in brick masonry/stone masonry/plain or reinforced concrete abutment, wing wall, return wall with 100mm (one hundred millimeter) dia P.V.C. pipe extending through the full width of the structures with slope of I (v): 20(H) towards drainage face complete as per drawing and MORD technical specification clauses 709 and 1206.60 including hauling /carriage of materials to various location through all modes of transportation in all leads, lifts and other incidental complete in all respect and as per the direction of Engineer-In-Charge.The rate isincluding royality, Malkana,Toll tax,GST orother taxes imposed by the Government. |
| 5 | Providing and laying of boulder apron laid in wire crates with 4 mm (four millimetre diametre) dia GI wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm (one hundred millimetre into one hundred millimetre) mesh (woven diagonally) including 10 (ten) per cent extra for laps and joints laid with stone boulders weighing not less than 40 kg (fortykilogram) each as per drawing and technical specifications Clause 1301. injcludingleads, lifts and other incidental complete in all respectincluding hauling /carriage of materials to various location through all modes of transportation in and as per the direction of Engineer-In-Charge.The rate isincluding royality, Malkana,Toll tax,GST orother taxes imposed by the Government. |
| 6 | Compacting of original ground supporting sub-grade, loosening of the ground upto a level of 300 mm (Three hundred millimetre) below the subgrade level, watered, graded and compacted in layers to meet requirement of Tables 300.1 and 300.2 for subgrade construction as per M.O.R.D.Technical Specification Clause 303.5.2 in all leads, lifts and other incidental complete in all respectincluding hauling /carriage of materials to various location through all modes of transportation in and as per the direction of Engineer-In-Charge.The rate isincluding royality, Malkana,Toll tax,GST orother taxes imposed by the Government. |
| 7 | Providing and laying mechanically mixed and vibrated plain cement concrete in foundation and plinth as per drawingand technical specification section 800, 1200 and 1600 for nominal mix 1: 4: 8 (one cement isto four sand isto eight graded crushed/brokenstone aggregate40 mm (forty millimeters) nominal size and curing complete including pumping or bailing out water, dewatering, removal of slush as required at site which may arise at the time of laying under water complete for all heights/depthsand including the cost of form work in retaining walls, breast walls etceteraas per the direction of Engineer-in-Charge and carriage of materials, within all leads and lifts and other incidentals. The rate is including octroi, royality, Malkana, toll tax, GST or any other taxes imposed by the Government. |
| 8 | Providing and laying rubble stone fooring in cement mortar 1:3 ( one cement isto three sand) laid over cement concrete bedding complete as per drawing and techanical specification clause 1303as directed by the Engineer-in-Charge including carriage of material within all leads, lifts and other incidentals. The rate isincluding royality, Malkana,Toll tax, GST orother taxes imposed by the Government. |
| 9 | Providing weep holes in brick masonry/stone masonry/plain or reinforced concrete abutment, wing wall, return wall with 100mm (one hundred millimeter) dia P.V.C. pipe (Finolex/ Vertex0 30 cm (thirty centimetre longwith slope of I (v): 20(H) towards drainage face complete as per drawing and MORD technical specification clauses 614, 709 and 1204.3.7 including hauling /carriage of materials to various location through all modes of transportation in all leads, lifts and other incidental complete in all respect and as per the direction of Engineer-In-Charge.The rate isincluding royality, Malkana,Toll tax, GST orother taxes imposed by the Government. |