Construction Of Masonry Well. Construction Of 4 (Four) Nos Masonry Well At Sachindra/Wakhiram/Kalicharan/Sarpamar Under Chawmanu Rd Block, 2020-21.(2Nd Call).
Tender Value
Ref. Documents
Estimated cost
Bid Submission
31 Aug 2021
0 days left
EMD
16270
Bank guarantee accepted
Document Fee
1000
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Chawmanu → Tripura
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Construction Of Masonry Well. Construction Of 4 (Four) Nos Masonry Well At Sachindra/Wakhiram/Kalicharan/Sarpamar Under Chawmanu Rd Block, 2020-21.(2Nd Call).
BOQ
| Sl. No. | Item Description |
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means overareas (exceeding 30cm in depth, 1.5m in width as well as 10 sqm on plan) including disposalof excavated earth, lead upto 50m and lift upto 1.5m, disposed earth to be levelled and neatlydressed.-All kinds of soil |
| 2 | Excavation for structure. With Dewatering. Excavation for stucture as per drawing and technical specification clause 305.1 in/c setting out, dewatering,construction of shoring,shuttering & bracing,removal of stumps& other deleterious material and disposal upto lead of 50m,dressing of sides & bottom and backfilling in trenches with excavated suitable material. ordinary soil upto 3m depth.3m to 6m depth. All kinds of soil. 1) upto 3m depth. |
| 3 | 2) upto 3m to 6m depth. |
| 4 | Excavation for structure. Without Dewatering. Excavation for stucture as per drawing and technical specification clause 305.1 in/c setting out, dewatering,construction of shoring,shuttering & bracing,removal of stumps& other deleterious material and disposal upto lead of 50m,dressing of sides & bottom and backfilling in trenches with excavated suitable material. ordinary soil upto 3m depth.3m to 6m depth. ii) Ordinary rock (not requiring blasting. II) upto 3m depth. |
| 5 | Supplying and filling in plinth, under floor, foundations etc. with sand (fine) from local quarry with all lifts including spreading in horizontal layers, watering, grading to required slope, ramming, consolidating and compacting each layer by using plate compactor or by any suitable method complete |
| 6 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering --All work upto plinth level:a) 1:3:6 ( 1 Cement: 3 fine sand : 6 graded well burnt brick aggregate 20 mm nominal size) |
| 7 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases upto floor five level excluding the cost of centring, shuttering, finishing and reinforcement. b) R work in beams,lintels,bands,plain window sills,staircase and spiral staircases ex/c precast spiral staircase.1:2:4 ( 1 Cement: 2 fine sand : 4 graded well burnt bick aggregate 20 mm nominal size). |
| 8 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and skirting courses, fillets, columns, pillars, piers, abutments, posts and struts etc. upto floor five level excluding cost of centring, shuttering, finishing and reinforcement1:2:4 ( 1 Cement: 2 fine sand : 4 graded 4 graded well burnt bick aggregate 20 mm nominal size) |
| 9 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete uptofloor five level.Thermo-Mechanically Treated bars /cold twisted deformed steel bars. |
| 10 | Centering shuttering including struttings, propping etc.and removal of form work for:c) Lintels, beams, plinth beams, girders, bressumers and cantilevers with shuttering ply |
| 11 | b) Columns, Pillars, Piers, Abutments, Posts and Struts with shuttering ply |
| 12 | First class brick work in foundation and plinth including cost of all materials as required complete:-In cement mortar 1:3 ( 1 cement : 3 fine sand ). |
| 13 | 1st class brick work inperstructure above plith level& upto floor five level in/c cost of all materials as required complete. n cement mortar 1:6 ( 1 cement : 6 fine sand ). |
| 14 | Half brick masonry work with first class bricks in superstructure upto floor five level in/c cost of all materials as required complete:-In cement mortar 1:4 ( 1 cement : 4 fine sand ). |
| 15 | 12 mm cement plaster of mixIn cement mortar 1:4 ( 1 cement : 4 fine sand ). |
| 16 | Neat cement punning. |
| 17 | Providing and laying lter media with granular crushed agg. As per specification to a thickness of not less then 600mm with smaller size towards the the soil & bigger size towards the wall & providing over the entire surface behind abutment,wing wall,return wall to the full ht. compacted to firm condition complete as per drawing and Mord technical specification clause 1204.3.8 |
| 18 | Providing weep holes in brick masonary/stone masonary, plain/reinforced concrete abutment,wing wall,return wall with 100mm dia AC pipe or PVC pipe(110mm OD of 6.0 kg/cm2 pressure) extending through the full width of the structure with slope of 1(V): 20(H) towards drwing and MoRD technical specification clauses 614,709,1204.3.7 |
| 19 | Charge. |
AI Tender Summary
Tender Timeline
Aug 17, 2021
11:30 IST
Tender Published
Tender notice published.
CompletedAug 31, 2021
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedAug 31, 2021
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender