municipality has published Extension Of 11 Kv Line To 5 Tpd Mcc Of Birmitrapur Municipality At Banmunda Daffai . Submission Date for this Tender is 05-08-2021. Transmission Line Tenders in Birmitrapur Odisha. Bidders can get complete Tender details and download the document.
Sl. No. | Item Description |
1 | Supports 9mtr long PSC Pole for 63KVA 11/0.4KV SUB station |
2 | 9 mtr long PSC Pole for 3Ph 11KV line& Cut point |
3 | Stock, Storage & Insurance @ 3% of A=B |
4 | T&P @2% of C |
5 | Contingency @ 3% of C |
6 | Transporation @7.5% of C+ GST on transportation cost |
7 | Erection charges @20% of C =GST on erection charge |
8 | Cost of 11/0.4 KV 63kva transformer |
9 | Stock, Storage & Insurance @ 3% of A=B |
10 | T&P @2% of C |
11 | Contingency @ 3% of C |
12 | Transporation @7.5% of C+ GST on transportation cost |
13 | Erection charges @20% of C =GST on erection charge |
14 | Cost of common meterials for 11/.4 KV 63 KVA S/S with double disc arrangement (excluding cost of Pole) |
15 | Cost of common materials for 3-ph.,3-Wire 11KV Line on 9mtr. Long PSC Pole for Pin Pint and two nos Cut Points with double disc arrangement of 55mm2 AAAC (60MTR.Span)(excluding cost of Pole) |
16 | Cost of common materials for 11 KV Cut Point with Double Disc Arrangement (excluding cost of Pole |
17 | 11 KV 3-Ph line with 35mm sq. XLPE Cable |
18 | 11 kv O/D type jointing kit |
19 | Stock, Storage & Insurance @ 3% of A=B |
20 | T&P @2% of C |
21 | Contingency @ 3% of C |
22 | Transporation @7.5% of C+ GST on transportation cost |
23 | Erection charges @20% of C =GST on erection charge |
24 | Construction of plinth using first class KB bricks masonry in CM(1:6) of size L 1.5 xW 5"xH4 and 4" thick reinforcement on the top using steel bar and 20 mm thick cement plaster over bricks masonry in CM(1;6). The foundation shall be providing of 4" thick sand filling and height of 1; 10" bricks masonry of size L5xW5" in CM (1;6) First footing wall size 1" X 3" Second Footing of wall size 10" Middle porting filled with sand+Applicable Tax |
25 | Construction of Boundary Wall with grill gate+Application GST |
26 | Metal Spreading + Applicable Tax |
27 | other Over Heads (Including supervision charges) @ 6% of D=E |
28 | Labour Cess @ 1% of F |
29 | GSt @ 18% of E |
30 | Meteral Arrangement |
31 | Inspection Fee for S/S & line |
32 | Drawing Approval |
33 | Processing Fee + GST on Processing Fee |