| 1 | Clearing grass and removal of rubbish up to a distance of 50 metres outside the periphery ofthe area . |
| 2 | Supplying trap/granite/quartzite/gneiss stone metal of required size by bringing the boulders / Rubble at the road side breaking them to required gradation including conveying the boulders/Rubbleandstackingthebrokenmetaletc.complete.(Priorapprovalofsamplestackof brokenmetalbytheEx.Engineerisnecessarythedateofapprovalwillformpartofthe measurements)a)40 mm Metal, By breaking Boulders (Hand broken). |
| 3 | Supplying soft murum at the road site, including conveying and stacking complete. |
| 4 | Supplying hard murum/ kankar at the road site, including conveying and stacking complete. |
| 5 | Spreading80/40 mm metal for road work including sectionong etc complete as directed by Engineer in charge . |
| 6 | Spreading hard murum/ soft murrum/ gravel or kankar for side width complete |
| 7 | Compactingthehardmurumsidewidthsincludinglayinginlayersoneachsidewithvibratory roller including artificial watering etc. complete. |
| 8 | Compactingthesubgrade/gravel/sizemetal(100mm loose)layersforallwidthswith Power roller having weight 8 to 10 MT. including necessary, labour, materials and artificialwatering complete. |
| 9 | Providingandconstructing50mm.thickModified PenetrationMacadam(MPM) road surface including all mataerials, preparing the existing road surface, spreading 40mm. stone metal layers 30% crusher broken metal + 70% Hand broken (by breaking rubbleobtained by blasting)heatingandsprayingthe [email protected]/Square Metre, spreading 12mm.size chips compacting withstatic roller having weight 8 to 10 MT. to achivethedesireddegreeofcompactionasperTechnicalSpecificationClause506 etc. complete. IncludingpickingofexistingWBMsurface.(VG-30bulkbitumenratesare considered to arrive at rates) |
| 10 | Providingandconstructing50mm.thick Modified PenetrationMacadam(MPM)road surfaceincluding allmaterials,preparingthe existingroadsurface,spreading 40mm.stone layersmetal30% crusherbrokenmetal+70%Handbrokenmetal(BybreakingRubble obtained by blasting) , heating and spraying the bitumen of specified grade @ 1.75Kilogram/ Square Metre, spreading 12mm.size chips compacting with Static roller having weight 8 to 10 MT. to achive the desired degree of compactionas per TechnicalSpecificationClause 506 etc.complete,includingapplyingtackcoatofbitumen0fspecifiedgradeattherateof 0.30KilogramSquare Metre.(on existing bitumen surface.) |
| 11 | ProvidingandapplyingtackcoatonthepreparedsurfaceheatingbyfamesinBoilerand sprayingbitumensetfootedinbitumenbolleronB.T.surface2.5Kilogram/10Square Metre.(VG-30 bulk bitumen rates are considered to arrive at rates) |
| 12 | Open Graded Premix Surfacing- Providing and Laying OGC 20 mm thickness composed of13.2 mm to 5.6 mm aggregates premixed with bituminous binder transported to site with VTS, laid over a previously prepared surface, finished to the required grade, level, alignment, and rollingtoachievethedesiredcompactionbutexcludingprime/tackandSealcoat.For Bitumen of specified grade--USING drum mix type hot mix plant with SCADA, Paver and Vibratory roller( over BT Surface) (VG-30 bulk bitumen rates are considered to arrive at rates) |
| 13 | Providing bituminous Type A liquid seal coat on bituminous surface including supplying all materialsandbitumenofspecifiedgrade preparingexistingroadsurface,heatingand applying bitumen @ 0.98 KilogramSquare Metre. by mechanical means, spreading chips and rolling, by static roller having weight 8 to 10 MT. etc. complete. (VG-30 bulk bitumen rates are considered to arrive at rates) |
| 14 | Excavation for catch / side water gutter in all sorts of soils to the specified section including stacking the excavated stuff in a regular bund and disposing of unsuitable or excess stuff asdirected all sorts of soils. |
| 15 | Providingandfixingboarddisplayinginformation,suchas\"Nameofwork,Tendercost, Name of Contractor, Work completion and liability period etc\", having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x75cmincluding,excavation,refilling,transportation,andlabouretccomplete.Spec. Number As directed by Engineer in Charge |
| 16 | For Murum Liquid Limit And Plastic Limit |
| 17 | For CoarseSieve Analysis |
| 18 | BITUMENPenetration, Softening Point, Flash & Fire Point, SpecificGravity |
| 19 | Royalty Charges For Other Minerals |