Bridge And Roof Company I Limited has published Mechanical Works Pertaining To Mechanical Works-I For Residual Utilities And Offsite ( Ru And O ) Facilities For Rajasthan Refinery Project Mechanical Works ( Fabrication And Erection Of Above Ground Piping Works , Equipment Erection Works , Fabrication. Submission Date for this Tender is 09-08-2021. Mechanical engineering Service Tenders in Rajasthan Refinery Project of Ms.HRRL Rajasthan. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 12-Jul-2021 | Addendium-I | Fee | 23-07-2021 |
2 | 23-Jul-2021 | Extension of Due date I | Date | 31-07-2021 |
3 | 31-Jul-2021 | Extension of Due date II | Date | 09-08-2021 |
Name of Work : “Mechanical Works (Fabrication & Erection of Aboveground Piping Works, Equipment Erection Works, Fabrication & Erection of Structural Steel Works etc.) pertaining to “Mechanical Works-I for Residual Utilities and Offsite (RU&O) Facilities for Rajasthan Refinery Project of M/s.HRRL-For Part-B” | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | PIPING-OFFSITES | M20000000000 | ||
2 | 2 | FABRICATION OF PIPING SPECIALS FROM PIPES (SUPPLIED BY OWNER):- Fabrication of the following specials from pipes of all types & thicknesses including transportation of materials from Owner's storage points to work site/workshop, cutting, fitup, edge preparing, welding, bending, testing (Including DP) & inspection as per specs etc. supply of all necessary quipment, consumables, labour, supervision etc. The work shall be carried out as per the specificatons, drawings and instructions of Engineer-in-Charge.Note: Sizes mentioned under the heading of Reducers (Conc. / Ecc.) are for large end. | M20100000000 | ||
3 | 3 | C.S MITRE BENDS-90; THK. <= 10MM | M20101000000 | ||
4 | 4 | NB 16.000 INCHES | M20101002000 | 8 | Nos |
5 | 5 | NB 18.000 INCHES | M20101002100 | 1 | Nos |
6 | 6 | NB 20.000 INCHES | M20101002200 | 2 | Nos |
7 | 7 | NB 24.000 INCHES | M20101002400 | 2 | Nos |
8 | 8 | NB 26.000 INCHES | M20101002500 | 5 | Nos |
9 | 9 | NB 28.000 INCHES | M20101002600 | 1 | Nos |
10 | 10 | NB 30.000 INCHES | M20101002700 | 1 | Nos |
11 | 11 | NB 32.000 INCHES | M20101002800 | 1 | Nos |
12 | 12 | NB 34.000 INCHES | M20101002900 | 1 | Nos |
13 | 13 | NB 36.000 INCHES | M20101003000 | 1 | Nos |
14 | 14 | NB 38.000 INCHES | M20101003100 | 1 | Nos |
15 | 15 | C.S MITRE BENDS-45; THK. <= 10MM | M20104000000 | ||
16 | 16 | NB 16.000 INCHES | M20104002000 | 3 | Nos |
17 | 17 | NB 18.000 INCHES | M20104002100 | 1 | Nos |
18 | 18 | NB 20.000 INCHES | M20104002200 | 1 | Nos |
19 | 19 | NB 24.000 INCHES | M20104002400 | 1 | Nos |
20 | 20 | NB 26.000 INCHES | M20104002500 | 1 | Nos |
21 | 21 | NB 28.000 INCHES | M20104002600 | 1 | Nos |
22 | 22 | NB 30.000 INCHES | M20104002700 | 1 | Nos |
23 | 23 | NB 32.000 INCHES | M20104002800 | 1 | Nos |
24 | 24 | NB 34.000 INCHES | M20104002900 | 1 | Nos |
25 | 25 | NB 36.000 INCHES | M20104003000 | 1 | Nos |
26 | 26 | NB 38.000 INCHES | M20104003100 | 1 | Nos |
27 | 27 | C.S CONC. REDUCERS; THK. <= 10MM | M20107000000 | ||
28 | 28 | NB 16.000 INCHES | M20107002000 | 1 | Nos |
29 | 29 | NB 18.000 INCHES | M20107002100 | 1 | Nos |
30 | 30 | NB 20.000 INCHES | M20107002200 | 1 | Nos |
31 | 31 | NB 24.000 INCHES | M20107002400 | 1 | Nos |
32 | 32 | NB 26.000 INCHES | M20107002500 | 1 | Nos |
33 | 33 | NB 28.000 INCHES | M20107002600 | 1 | Nos |
34 | 34 | NB 30.000 INCHES | M20107002700 | 1 | Nos |
35 | 35 | NB 32.000 INCHES | M20107002800 | 1 | Nos |
36 | 36 | NB 36.000 INCHES | M20107003000 | 1 | Nos |
37 | 37 | NB 38.000 INCHES | M20107003100 | 1 | Nos |
38 | 38 | C.S CONC. REDUCERS; THK. > 10MM AND <= 20MM | M20108000000 | ||
39 | 39 | NB 40.000 INCHES | M20108003200 | 1 | Nos |
40 | 40 | NB 42.000 INCHES | M20108003300 | 1 | Nos |
41 | 41 | NB 44.000 INCHES | M20108003400 | 1 | Nos |
42 | 42 | NB 46.000 INCHES | M20108003500 | 1 | Nos |
43 | 43 | NB 48.000 INCHES | M20108003600 | 1 | Nos |
44 | 44 | C.S ECC. REDUCERS; THK. <= 10MM | M20110000000 | ||
45 | 45 | NB 16.000 INCHES | M20110002000 | 3 | Nos |
46 | 46 | NB 18.000 INCHES | M20110002100 | 1 | Nos |
47 | 47 | NB 20.000 INCHES | M20110002200 | 1 | Nos |
48 | 48 | NB 24.000 INCHES | M20110002400 | 1 | Nos |
49 | 49 | NB 28.000 INCHES | M20110002600 | 1 | Nos |
50 | 50 | NB 30.000 INCHES | M20110002700 | 1 | Nos |
51 | 51 | NB 32.000 INCHES | M20110002800 | 1 | Nos |
52 | 52 | NB 36.000 INCHES | M20110003000 | 1 | Nos |
53 | 53 | C.S FUNNELS | M20113000000 | ||
54 | 54 | NB 4.000 INCHES | M20113001300 | 46 | Nos |
55 | 55 | NB 6.000 INCHES | M20113001500 | 39 | Nos |
56 | 56 | NB 8.000 INCHES | M20113001600 | 13 | Nos |
57 | 57 | NB 10.000 INCHES | M20113001700 | 13 | Nos |
58 | 58 | NB 12.000 INCHES | M20113001800 | 7 | Nos |
59 | 59 | PIPING (ABOVE GROUND) :-Transportation of all piping items from Owner's storage point to work site/work shop; fabrication including cutting, edge preparation, (inclusive of grinding the edges of pipe, pipe spools, fittings, flanges etc. to match with the mating edges of uneven/different thickness wherever required); fitup, bending, preheating wherever required, welding, threading, and laying of pipes and pipe spools (spools along with supports) of all types and thickness over sleepers, overhead on racks and at all elevations, hook-ups with existing piping, connecting with equipment nozzles, strainers, steam traps, orifice assemblies, spray nozzles, rotameters, tappings for pressure gauges, thermowells, sample connections, sample coolers, closed sample system cabinets etc. and fixing of gaskets, bolts, nuts including application of torque wherever required & all other inline instruments and fittings, like elbows, reducers, tees, flanges, spectacle blinds and spacer&blinds, piping specials such as mitres and fabricated fittings, vents, drains (but excluding reinforcing pads), SW valves upto 1.5 NB, Steam Supply/ Condensate Recovery stations(Cast/Fabricated), Welding of Strip as per EIL Std 7-51-0112 to all pipes before hydro-testing at exit points of Units for earthing purpose; alignment, cleaning & flushing by water/compressed air, hydrostatic, pneumatic, vacuum, spark testing and any other type of testing as specified draining, drying by compressed air, performing Positive Material Identification(PMI) using alloy analysers, completing all such works in all respects as per the specifications, drawings and instructions of Engineer-in-Charge. PMI shall be performed by third party as defined in PMI spec. Rates for tubing (if any) shall include rates for valves, fittings, all in line instruments and testing etc. Carbon steel piping includes LTCS piping also. | M20900000000 | ||
60 | 60 | CARBON STEEL PIPING (NON IBR); THK. <= 10MM | M20901000000 | ||
61 | 61 | FABRICATION (BUTT WELD) | M20901010000 | ||
62 | 62 | NB UPTO 1.5 INCH | M20901019100 | 1575 | Inch Dia |
63 | 63 | NB 2 INCH - 6 INCH | M20901019200 | 93845 | Inch Dia |
64 | 64 | NB 8 INCH - 14 INCH | M20901019300 | 84935 | Inch Dia |
65 | 65 | NB 16 INCH - 24 INCH | M20901019400 | 18125 | Inch Dia |
66 | 66 | NB 26 INCH - 36 INCH | M20901019500 | 5547 | Inch Dia |
67 | 67 | NB 38 INCH - 48 INCH | M20901019600 | 1640 | Inch Dia |
68 | 68 | FABRICATION (FILLET WELD) | M20901020000 | ||
69 | 69 | NB UPTO 1.5 INCH | M20901029100 | 14920 | Inch Dia |
70 | 70 | NB 2 INCH - 6 INCH | M20901029200 | 1800 | Inch Dia |
71 | 71 | NB 8 INCH - 14 INCH | M20901029300 | 105 | Inch Dia |
72 | 72 | NB 16 INCH - 24 INCH | M20901029400 | 178 | Inch Dia |
73 | 73 | NB 26 INCH - 36 INCH | M20901029500 | 273 | Inch Dia |
74 | 74 | NB 38 INCH - 48 INCH | M20901029600 | 390 | Inch Dia |
75 | 75 | ERECTION (OTHER THAN SPOOL) | M20901040000 | ||
76 | 76 | NB UPTO 1.5 INCH | M20901049100 | 7760 | Inch M |
77 | 77 | NB 2 INCH - 6 INCH | M20901049200 | 440222 | Inch M |
78 | 78 | NB 8 INCH - 14 INCH | M20901049300 | 469100 | Inch M |
79 | 79 | NB 16 INCH - 24 INCH | M20901049400 | 110690 | Inch M |
80 | 80 | NB 26 INCH - 36 INCH | M20901049500 | 30460 | Inch M |
81 | 81 | NB 38 INCH - 48 INCH | M20901049600 | 14095 | Inch M |
82 | 82 | CARBON STEEL PIPING (NON IBR); THK. > 10MM AND <= 20MM | M20902000000 | ||
83 | 83 | FABRICATION (BUTT WELD) | M20902010000 | ||
84 | 84 | NB 2 INCH - 6 INCH | M20902019200 | 373 | Inch Dia |
85 | 85 | NB 8 INCH - 14 INCH | M20902019300 | 12742 | Inch Dia |
86 | 86 | NB 16 INCH - 24 INCH | M20902019400 | 15121 | Inch Dia |
87 | 87 | NB 26 INCH - 36 INCH | M20902019500 | 338 | Inch Dia |
88 | 88 | ERECTION (OTHER THAN SPOOL) | M20902040000 | ||
89 | 89 | NB 2 INCH - 6 INCH | M20902049200 | 173 | Inch M |
90 | 90 | NB 8 INCH - 14 INCH | M20902049300 | 74060 | Inch M |
91 | 91 | NB 16 INCH - 24 INCH | M20902049400 | 100753 | Inch M |
92 | 92 | NB 26 INCH - 36 INCH | M20902049500 | 728 | Inch M |
93 | 93 | CARBON STEEL PIPING (IBR); THK. <= TO 10MM | M20906000000 | ||
94 | 94 | FABRICATION (BUTT WELD) | M20906010000 | ||
95 | 95 | NB UPTO 1.5 INCH | M20906019100 | 170 | Inch Dia |
96 | 96 | NB 2 INCH - 6 INCH | M20906019200 | 5605 | Inch Dia |
97 | 97 | NB 8 INCH - 14 INCH | M20906019300 | 3095 | Inch Dia |
98 | 98 | NB 16 INCH - 24 INCH | M20906019400 | 480 | Inch Dia |
99 | 99 | FABRICATION (FILLET WELD) | M20906020000 | ||
100 | 100 | NB UPTO 1.5 INCH | M20906029100 | 920 | Inch Dia |
101 | 101 | ERECTION (OTHER THAN SPOOL) | M20906040000 | ||
102 | 102 | NB UPTO 1.5 INCH | M20906049100 | 235 | Inch M |
103 | 103 | NB 2 INCH - 6 INCH | M20906049200 | 20424 | Inch M |
104 | 104 | NB 8 INCH - 14 INCH | M20906049300 | 16087 | Inch M |
105 | 105 | NB 16 INCH - 24 INCH | M20906049400 | 740 | Inch M |
106 | 106 | STAINLESS STEEL PIPING (NON-IBR); THK. <= 10MM | M20911000000 | ||
107 | 107 | FABRICATION (BUTT WELD) | M20911010000 | ||
108 | 108 | NB UPTO 1.5 INCH | M20911019100 | 16 | Inch Dia |
109 | 109 | NB 2 INCH - 6 INCH | M20911019200 | 645 | Inch Dia |
110 | 110 | NB 8 INCH - 14 INCH | M20911019300 | 75 | Inch Dia |
111 | 111 | NB 16 INCH - 24 INCH | M20911019400 | 757 | Inch Dia |
112 | 112 | FABRICATION (FILLET WELD) | M20911020000 | ||
113 | 113 | NB UPTO 1.5 INCH | M20911029100 | 420 | Inch Dia |
114 | 114 | NB 2 INCH - 6 INCH | M20911029200 | 118 | Inch Dia |
115 | 115 | NB 8 INCH - 14 INCH | M20911029300 | 129 | Inch Dia |
116 | 116 | NB 16 INCH - 24 INCH | M20911029400 | 155 | Inch Dia |
117 | 117 | ERECTION (OTHER THAN SPOOL) | M20911040000 | ||
118 | 118 | NB UPTO 1.5 INCH | M20911049100 | 471 | Inch M |
119 | 119 | NB 2 INCH - 6 INCH | M20911049200 | 1433 | Inch M |
120 | 120 | NB 8 INCH - 14 INCH | M20911049300 | 264 | Inch M |
121 | 121 | NB 16 INCH - 24 INCH | M20911049400 | 5269 | Inch M |
122 | 122 | ALLOY STEEL PIPING (NON-IBR); THK. <= 10MM | M20925000000 | ||
123 | 123 | FABRICATION (BUTT WELD) | M20925010000 | ||
124 | 124 | NB UPTO 1.5 INCH | M20925019100 | 6 | Inch Dia |
125 | 125 | NB 2 INCH - 6 INCH | M20925019200 | 2 | Inch Dia |
126 | 126 | FABRICATION (FILLET WELD) | M20925020000 | ||
127 | 127 | NB UPTO 1.5 INCH | M20925029100 | 45 | Inch Dia |
128 | 128 | ERECTION (OTHER THAN SPOOL) | M20925040000 | ||
129 | 129 | NB UPTO 1.5 INCH | M20925049100 | 6 | Inch M |
130 | 130 | NB 2 INCH - 6 INCH | M20925049200 | 32 | Inch M |
131 | 131 | ALLOY STEEL PIPING (NON-IBR); THK. > 10MM AND <= 20MM | M20926000000 | ||
132 | 132 | FABRICATION (BUTT WELD) | M20926010000 | ||
133 | 133 | NB 2 INCH - 6 INCH | M20926019200 | 772 | Inch Dia |
134 | 134 | ERECTION (OTHER THAN SPOOL) | M20926040000 | ||
135 | 135 | NB 2 INCH - 6 INCH | M20926049200 | 4700 | Inch M |
136 | 136 | CARBON STEEL GALVANIZED | M20937000000 | ||
137 | 137 | NB 0.500 INCHES | M20937000400 | 15 | Metres |
138 | 138 | NB 0.750 INCHES | M20937000500 | 105 | Metres |
139 | 139 | NB 1.000 INCHES | M20937000600 | 15 | Metres |
140 | 140 | NB 1.500 INCHES | M20937000800 | 315 | Metres |
141 | 141 | NB 2.000 INCHES | M20937000900 | 8145 | Metres |
142 | 142 | NB 3.000 INCHES | M20937001100 | 185 | Metres |
143 | 143 | NB 4.000 INCHES | M20937001300 | 1555 | Metres |
144 | 144 | NB 6.000 INCHES | M20937001500 | 15 | Metres |
145 | 145 | NB 8.000 INCHES | M20937001600 | 15 | Metres |
146 | 146 | STEAM TRACERS CARBON STEEL | M20944000000 | ||
147 | 147 | NB 0.500 INCHES | M20944000400 | 1105 | Metres |
148 | 148 | NB 0.750 INCHES | M20944000500 | 85 | Metres |
149 | 149 | VALVES :- Transportation of all types of valves (Including special valves, motor operated valves, PRDS, PSVs, TSVs, Control valves, On-Off/Shutdown valves, Self actuating valves) from Owner's storage points to contractor's stores/ worksite and installation of valves for all rating including assembly of valves accessories like air bottles etc, if any, fixing of gaskets bolts/nuts wherever required and performing Positive Material Identification(PMI) using alloy analysers as per specification, drawings and directions of Engineer-in-Charge. | M21600000000 | ||
150 | 150 | FLANGED/WAFER VALVES INCLUDING MOV (UPTO 600#) | M21601000000 | ||
151 | 151 | NB 0.500 INCHES | M21601000400 | 61 | Nos |
152 | 152 | NB 0.750 INCHES | M21601000500 | 902 | Nos |
153 | 153 | NB 1.000 INCHES | M21601000600 | 49 | Nos |
154 | 154 | NB 1.500 INCHES | M21601000800 | 14 | Nos |
155 | 155 | NB 2.000 INCHES | M21601000900 | 842 | Nos |
156 | 156 | NB 3.000 INCHES | M21601001100 | 272 | Nos |
157 | 157 | NB 4.000 INCHES | M21601001300 | 295 | Nos |
158 | 158 | NB 6.000 INCHES | M21601001500 | 412 | Nos |
159 | 159 | NB 8.000 INCHES | M21601001600 | 129 | Nos |
160 | 160 | NB 10.000 INCHES | M21601001700 | 82 | Nos |
161 | 161 | NB 12.000 INCHES | M21601001800 | 92 | Nos |
162 | 162 | NB 14.000 INCHES | M21601001900 | 92 | Nos |
163 | 163 | NB 16.000 INCHES | M21601002000 | 1 | Nos |
164 | 164 | NB 18.000 INCHES | M21601002100 | 1 | Nos |
165 | 165 | NB 20.000 INCHES | M21601002200 | 1 | Nos |
166 | 166 | NB 24.000 INCHES | M21601002400 | 8 | Nos |
167 | 167 | NB 26.000 INCHES | M21601002500 | 1 | Nos |
168 | 168 | NB 28.000 INCHES | M21601002600 | 1 | Nos |
169 | 169 | NB 30.000 INCHES | M21601002700 | 7 | Nos |
170 | 170 | FLANGED/WAFER VALVES INCLUDING MOV (900# & ABOVE) | M21602000000 | ||
171 | 171 | NB 4.000 INCHES | M21602001300 | 3 | Nos |
172 | 172 | NB 6.000 INCHES | M21602001500 | 3 | Nos |
173 | 173 | CONTROL VALVES (UPTO 600#) | M21603000000 | ||
174 | 174 | NB 1.000 INCHES | M21603000600 | 15 | Nos |
175 | 175 | NB 1.500 INCHES | M21603000800 | 7 | Nos |
176 | 176 | NB 2.000 INCHES | M21603000900 | 16 | Nos |
177 | 177 | NB 3.000 INCHES | M21603001100 | 25 | Nos |
178 | 178 | NB 4.000 INCHES | M21603001300 | 14 | Nos |
179 | 179 | NB 6.000 INCHES | M21603001500 | 24 | Nos |
180 | 180 | NB 8.000 INCHES | M21603001600 | 8 | Nos |
181 | 181 | NB 10.000 INCHES | M21603001700 | 14 | Nos |
182 | 182 | NB 12.000 INCHES | M21603001800 | 1 | Nos |
183 | 183 | NB 14.000 INCHES | M21603001900 | 3 | Nos |
184 | 184 | NB 16.000 INCHES | M21603002000 | 1 | Nos |
185 | 185 | NB 18.000 INCHES | M21603002100 | 1 | Nos |
186 | 186 | CONTROL VALVES (900# & ABOVE) | M21604000000 | ||
187 | 187 | NB 8.000 INCHES | M21604001600 | 1 | Nos |
188 | 188 | CARBON STEEL BW VALVES INCLUDING MOV (NON IBR) | M21605000000 | ||
189 | 189 | NB 0.500 INCHES | M21605000400 | 3 | Nos |
190 | 190 | NB 0.750 INCHES | M21605000500 | 20 | Nos |
191 | 191 | NB 1.000 INCHES | M21605000600 | 8 | Nos |
192 | 192 | NB 1.500 INCHES | M21605000800 | 3 | Nos |
193 | 193 | NB 2.000 INCHES | M21605000900 | 9 | Nos |
194 | 194 | NB 3.000 INCHES | M21605001100 | 9 | Nos |
195 | 195 | NB 4.000 INCHES | M21605001300 | 14 | Nos |
196 | 196 | NB 6.000 INCHES | M21605001500 | 10 | Nos |
197 | 197 | NB 8.000 INCHES | M21605001600 | 5 | Nos |
198 | 198 | NB 10.000 INCHES | M21605001700 | 3 | Nos |
199 | 199 | NB 12.000 INCHES | M21605001800 | 5 | Nos |
200 | 200 | PRESS. RELIEF/ SAFETY VALVES, PILOT OP. SAFETY VALVES (UPTO 600#) (Size are valve inlet size) | M21618000000 | ||
201 | 201 | NB 0.750 INCHES | M21618000500 | 373 | Nos |
202 | 202 | NB 1.000 INCHES | M21618000600 | 1 | Nos |
203 | 203 | NB 1.500 INCHES | M21618000800 | 1 | Nos |
204 | 204 | NB 2.000 INCHES | M21618000900 | 1 | Nos |
205 | 205 | NB 3.000 INCHES | M21618001100 | 5 | Nos |
206 | 206 | NB 4.000 INCHES | M21618001300 | 1 | Nos |
207 | 207 | NB 6.000 INCHES | M21618001500 | 1 | Nos |
208 | 208 | NB 8.000 INCHES | M21618001600 | 3 | Nos |
209 | 209 | METERING ASSEMBLY :- Transportation of parts of Metering assembly consisting of PD meter / Mass flow meter, strainers, air eleminator, shut off valves, spool piece etc. from owner's storage points to contractor's stores/work site and installation of the assembly of all ratings including assembly of all parts and fixing of gaskets, bolts, nuts wherever required, as per drawings, specifications, and directions of Engineer- in-charge. | M21700000000 | ||
210 | 210 | NB 0.500 INCHES | M21700000400 | 4 | Nos |
211 | 211 | NB 2.000 INCHES | M21700000900 | 1 | Nos |
212 | 212 | NB 3.000 INCHES | M21700001100 | 1 | Nos |
213 | 213 | NB 6.000 INCHES | M21700001500 | 1 | Nos |
214 | 214 | NB 12.000 INCHES | M21700001800 | 3 | Nos |
215 | 215 | NB 14.000 INCHES | M21700001900 | 3 | Nos |
216 | 216 | NB 16.000 INCHES | M21700002000 | 1 | Nos |
217 | 217 | NB 24.000 INCHES | M21700002400 | 1 | Nos |
218 | 218 | NB 42.000 INCHES | M21700003300 | 1 | Nos |
219 | 219 | SPRING SUPPORT ASSEMBLIES :- Transportation of all types of spring support assemblies from Owner's storage points to contractor's stores/worksite and installation of spring support assemblies for all rating including assembly, if any, fixing of gaskets bolts/nuts, welding attachments wherever required and performing Positive Material Identification(PMI) using alloy analysers as per specification, drawings and directions of Engineer-in-Charge. Contractor to ensure that travel stops are removed and spring is locked in cold load position for Hydrotest. It shall be ensured that locking devices are removed and springs are properly set at hot load position during commissioning. | M21900000000 | 1 | MT |
220 | 220 | BOLT TENSIONING :- Carrying out tensioning of bolted joints on all types of piping as called for in EIL Specification No.6-76-0002 on already erected system including supply of all materials, recording devices, instruments etc; Providing all normal and special equipment and gadgets, skilled / un skilled labour, specialist, supervisory staff and completing the work in all respects as per specifications and instructions of engineer-in-charge. some joints may require bolt tensioning more than once, but, payment for one joint shall be made only once. | M22000000000 | ||
221 | 221 | 150# JOINTS | M22001000000 | ||
222 | 222 | NB 14.000 INCHES | M22001001900 | 36 | Nos |
223 | 223 | NB 16.000 INCHES | M22001002000 | 8 | Nos |
224 | 224 | NB 18.000 INCHES | M22001002100 | 3 | Nos |
225 | 225 | NB 20.000 INCHES | M22001002200 | 1 | Nos |
226 | 226 | NB 24.000 INCHES | M22001002400 | 20 | Nos |
227 | 227 | NB 26.000 INCHES | M22001002500 | 1 | Nos |
228 | 228 | NB 28.000 INCHES | M22001002600 | 1 | Nos |
229 | 229 | NB 30.000 INCHES | M22001002700 | 14 | Nos |
230 | 230 | NB 32.000 INCHES | M22001002800 | 1 | Nos |
231 | 231 | NB 34.000 INCHES | M22001002900 | 1 | Nos |
232 | 232 | NB 36.000 INCHES | M22001003000 | 1 | Nos |
233 | 233 | NB 40.000 INCHES | M22001003200 | 1 | Nos |
234 | 234 | NB 42.000 INCHES | M22001003300 | 1 | Nos |
235 | 235 | 300# JOINTS | M22002000000 | ||
236 | 236 | NB 10.000 INCHES | M22002001700 | 48 | Nos |
237 | 237 | NB 12.000 INCHES | M22002001800 | 32 | Nos |
238 | 238 | NB 14.000 INCHES | M22002001900 | 60 | Nos |
239 | 239 | NB 16.000 INCHES | M22002002000 | 25 | Nos |
240 | 240 | NB 18.000 INCHES | M22002002100 | 1 | Nos |
241 | 241 | NB 20.000 INCHES | M22002002200 | 1 | Nos |
242 | 242 | NB 24.000 INCHES | M22002002400 | 1 | Nos |
243 | 243 | NB 26.000 INCHES | M22002002500 | 1 | Nos |
244 | 244 | NB 28.000 INCHES | M22002002600 | 1 | Nos |
245 | 245 | NB 30.000 INCHES | M22002002700 | 1 | Nos |
246 | 246 | NB 32.000 INCHES | M22002002800 | 1 | Nos |
247 | 247 | NB 34.000 INCHES | M22002002900 | 1 | Nos |
248 | 248 | NB 36.000 INCHES | M22002003000 | 13 | Nos |
249 | 249 | 600# JOINTS | M22004000000 | ||
250 | 250 | NB 6.000 INCHES | M22004001500 | 14 | Nos |
251 | 251 | NB 8.000 INCHES | M22004001600 | 1 | Nos |
252 | 252 | NB 10.000 INCHES | M22004001700 | 5 | Nos |
253 | 253 | 900# JOINTS | M22005000000 | ||
254 | 254 | NB 4.000 INCHES | M22005001300 | 10 | Nos |
255 | 255 | NB 6.000 INCHES | M22005001500 | 10 | Nos |
256 | 256 | NB 8.000 INCHES | M22005001600 | 3 | Nos |
257 | 257 | NB 10.000 INCHES | M22005001700 | 1 | Nos |
258 | 258 | NB 12.000 INCHES | M22005001800 | 10 | Nos |
259 | 259 | NB 14.000 INCHES | M22005001900 | 1 | Nos |
260 | 260 | NB 16.000 INCHES | M22005002000 | 10 | Nos |
261 | 261 | 1500# JOINTS | M22006000000 | ||
262 | 262 | NB 0.750 INCHES | M22006000500 | 1 | Nos |
263 | 263 | NB 1.000 INCHES | M22006000600 | 1 | Nos |
264 | 264 | 2500# JOINTS | M22007000000 | ||
265 | 265 | NB 0.750 INCHES | M22007000500 | 1 | Nos |
266 | 266 | NB 1.000 INCHES | M22007000600 | 1 | Nos |
267 | 267 | NB 1.500 INCHES | M22007000800 | 1 | Nos |
268 | 268 | NB 2.000 INCHES | M22007000900 | 1 | Nos |
269 | 269 | NB 3.000 INCHES | M22007001100 | 1 | Nos |
270 | 270 | NB 4.000 INCHES | M22007001300 | 1 | Nos |
271 | 271 | NB 6.000 INCHES | M22007001500 | 1 | Nos |
272 | 272 | NB 8.000 INCHES | M22007001600 | 1 | Nos |
273 | 273 | NB 10.000 INCHES | M22007001700 | 23 | Nos |
274 | 274 | REINFORCING PADS FOR PIPES :- Fabrication of reinforcing pads for pipe connection wherever required (from pipes only supplied by the Owner) and erection, fitup, welding & testing (including DP) if required of the same and performing Positive Material Identification(PMI) using alloy analysers as per the specifications, drawings and instructions of the Engineer in-Charge. Note: Sizes mentioned for Reinforcing Pads are for branch pipe | M22100000000 | ||
275 | 275 | C.S REINFORCING PADS | M22101000000 | ||
276 | 276 | NB 2.000 INCHES | M22101000900 | 25 | Nos |
277 | 277 | NB 3.000 INCHES | M22101001100 | 8 | Nos |
278 | 278 | NB 4.000 INCHES | M22101001300 | 21 | Nos |
279 | 279 | NB 6.000 INCHES | M22101001500 | 1 | Nos |
280 | 280 | NB 8.000 INCHES | M22101001600 | 16 | Nos |
281 | 281 | NB 10.000 INCHES | M22101001700 | 7 | Nos |
282 | 282 | NB 12.000 INCHES | M22101001800 | 8 | Nos |
283 | 283 | NB 14.000 INCHES | M22101001900 | 3 | Nos |
284 | 284 | NB 16.000 INCHES | M22101002000 | 1 | Nos |
285 | 285 | NB 18.000 INCHES | M22101002100 | 1 | Nos |
286 | 286 | NB 20.000 INCHES | M22101002200 | 1 | Nos |
287 | 287 | NB 24.000 INCHES | M22101002400 | 4 | Nos |
288 | 288 | NB 26.000 INCHES | M22101002500 | 1 | Nos |
289 | 289 | NB 28.000 INCHES | M22101002600 | 1 | Nos |
290 | 290 | NB 30.000 INCHES | M22101002700 | 1 | Nos |
291 | 291 | NB 32.000 INCHES | M22101002800 | 1 | Nos |
292 | 292 | NB 34.000 INCHES | M22101002900 | 1 | Nos |
293 | 293 | NB 36.000 INCHES | M22101003000 | 1 | Nos |
294 | 294 | NB 38.000 INCHES | M22101003100 | 1 | Nos |
295 | 295 | NB 40.000 INCHES | M22101003200 | 1 | Nos |
296 | 296 | NB 42.000 INCHES | M22101003300 | 1 | Nos |
297 | 297 | A.S REINFORCING PADS | M22102000000 | ||
298 | 298 | NB 2.000 INCHES | M22102000900 | 2 | Nos |
299 | 299 | NB 3.000 INCHES | M22102001100 | 1 | Nos |
300 | 300 | NB 4.000 INCHES | M22102001300 | 2 | Nos |
301 | 301 | NB 6.000 INCHES | M22102001500 | 2 | Nos |
302 | 302 | NB 8.000 INCHES | M22102001600 | 1 | Nos |
303 | 303 | NB 10.000 INCHES | M22102001700 | 1 | Nos |
304 | 304 | NB 12.000 INCHES | M22102001800 | 1 | Nos |
305 | 305 | S.S REINFORCING PADS | M22103000000 | ||
306 | 306 | NB 2.000 INCHES | M22103000900 | 1 | Nos |
307 | 307 | NB 3.000 INCHES | M22103001100 | 1 | Nos |
308 | 308 | NB 4.000 INCHES | M22103001300 | 1 | Nos |
309 | 309 | NB 6.000 INCHES | M22103001500 | 1 | Nos |
310 | 310 | NB 8.000 INCHES | M22103001600 | 1 | Nos |
311 | 311 | NB 10.000 INCHES | M22103001700 | 1 | Nos |
312 | 312 | DYE PENETRATION TEST :- Performance of magnetic particle/ dye penetrant test including supply of all necessary materials, equipment and labour for carrying out the work as per specification and directions of Engineer-in-Charge. | M22300000000 | ||
313 | 313 | DYE PENETRANT TEST | M22301000000 | 12000 | Inches |
314 | 314 | PIPE SUPPORTS (FROM MATERIALS SUPPLIED BY OWNER):- Fabrication, erection(at all elevations) of pipe supports like shoes, cradles, hangers, clamps (of all sizes/thicknesses manufactured by forming method using die), turn buckles, saddles, guides, special supports, pads (including corrosion pads & protection shields), providing and welding of stiffeners as per drawings, T post etc. of all types including supply of all necessary equipments, consumables, labour, returning surplus materials and scrap etc to owners storage points and completing work as per drawings, specifications and instructions of Engineer-in-charge. Modifications/rectifications, if required; and adjustment/ alignment during precommisioning, commisioning as per the instructions of Engineer-in-charge. | M22400000000 | ||
315 | 315 | DUMMY PIPE SUPPORTS FOR C.S (OWNER SUPPLIED) | M22404000000 | 153 | MT |
316 | 316 | DUMMY PIPE SUPPORTS FOR S.S (OWNER SUPPLIED) | M22405000000 | 1 | MT |
317 | 317 | DUMMY PIPE SUPPORTS FOR A.S (OWNER SUPPLIED) | M22406000000 | 1 | MT |
318 | 318 | PIPE SUPPORTS (FROM MATERIALS SUPPLIED BY B&R):- Fabrication, erection (at all elevations) of pipe supports like shoes, cradles, hangers, clamps (of all sizes/thicknesses manufactured by forming method using die), turn buckles, saddles, guides, special supports, pads (including corrosion pads & protection shields), welding of stiffeners as per drawings, T post etc. of all types including supply of all necessary equipments, consumables, labour, and completing work as per drawings, specifications and instructions of Engineer-incharge. Modifications/ rectifications, if required; and adjustment/ alignment during precommisioning, commisioning as per the instructions of Engineer-in-charge. | M22500000000 | ||
319 | 319 | C.S STRUCTURAL STEEL | M22501000000 | 18 | MT |
320 | 320 | S.S STRUCTURAL STEEL | M22502000000 | 1 | MT |
321 | 321 | A.S STRUCTURAL STEEL | M22503000000 | 1 | MT |
322 | 322 | WOODEN/HIGH DENSITY PUF SUPPORTS FOR COLD LINES:- Shaping, positioning and fixing of cold line supports as per EIL pipe support standard having the following specifications: Wood specification: Hard wood, chemically treated with creosote under pressure. Quality of wood to conform class-I durability as per IS-3629 & Grade-I timber of Group-A with permissible compression strength of 70 Kg/cm2 perpendicular to grains as per IS-883. PUF specifications: Density for lines upto 6" NB : 240 kg/cm3 Density for lines above 6" NB : 320 kg/cm3 | M22800000000 | ||
323 | 323 | WOODEN BLOCKS | M22801000000 | 4 | Cu. M |
324 | 324 | HIGH DENSITY (240 Kg/Cu.M) PUF BLOCKS | M22802000000 | 1 | Cu. M |
325 | 325 | HIGH DENSITY (320 Kg/Cu.M) PUF BLOCKS | M22803000000 | 1 | Cu. M |
326 | 326 | FABRICATION & ERECTION OF BLINDS/SPECTACLE BLINDS/SPACER & BLINDS ETC.:- Transportation from owner's storage point to work site, fabrication and erection of blinds, spectacle blinds, spacers & blinds of all ratings from plate material of all thicknesses supplied by owner as free issue; cutting, edge preparation, rolling, fit up, welding, cleaning, testing (hydrotesting, DP), wherever required bolts nuts & gaskets including supply of necessary equipment, consumables, labour etc as per standards / specifications and directions of Engineer-in-charge. | M23200000000 | ||
327 | 327 | BLINDS | M23201000000 | ||
328 | 328 | NB 0.500 INCHES | M23201000400 | 3 | Nos |
329 | 329 | NB 0.750 INCHES | M23201000500 | 3 | Nos |
330 | 330 | NB 1.000 INCHES | M23201000600 | 3 | Nos |
331 | 331 | NB 1.500 INCHES | M23201000800 | 3 | Nos |
332 | 332 | NB 2.000 INCHES | M23201000900 | 3 | Nos |
333 | 333 | NB 3.000 INCHES | M23201001100 | 3 | Nos |
334 | 334 | NB 4.000 INCHES | M23201001300 | 3 | Nos |
335 | 335 | NB 6.000 INCHES | M23201001500 | 3 | Nos |
336 | 336 | NB 8.000 INCHES | M23201001600 | 3 | Nos |
337 | 337 | NB 10.000 INCHES | M23201001700 | 3 | Nos |
338 | 338 | NB 12.000 INCHES | M23201001800 | 3 | Nos |
339 | 339 | NB 14.000 INCHES | M23201001900 | 3 | Nos |
340 | 340 | NB 16.000 INCHES | M23201002000 | 3 | Nos |
341 | 341 | NB 18.000 INCHES | M23201002100 | 3 | Nos |
342 | 342 | NB 20.000 INCHES | M23201002200 | 3 | Nos |
343 | 343 | NB 24.000 INCHES | M23201002400 | 3 | Nos |
344 | 344 | NB 26.000 INCHES | M23201002500 | 3 | Nos |
345 | 345 | NB 28.000 INCHES | M23201002600 | 3 | Nos |
346 | 346 | NB 30.000 INCHES | M23201002700 | 3 | Nos |
347 | 347 | MODIFICATION/EXTRA WORKS (IF ANY):- Cutting, bevelling, fitup, welding of different sizes of CS/AS/SS/Higher Alloy piping of all types and thicknessess in shop, in position, on ground/overhead on rack and at all elevations; transportation of pipes, fittings, flanges etc from owner's storage point to work site/ work shop, making necessary scaffoldings, consumables, machinery, tools, tackles, labour and supervision including attending repairs for completing the work as per the instruction of Engineer-in-charge. | M23700000000 | ||
348 | 348 | FLAME CUTTING C.S PIPING IBR/NON IBR | M23701000000 | 4070 | Inch Dia |
349 | 349 | HACKSAW CUTTING C.S PIPING IBR/NON IBR | M23702000000 | 1365 | Inch Dia |
350 | 350 | BEVELLING C.S PIPING IBR/NON IBR | M23703000000 | 5430 | Inch Dia |
351 | 351 | FITUP & WELDING C.S PIPING IBR/NON IBR | M23704000000 | 5430 | Inch Dia |
352 | 352 | FLAME CUTTING S.S PIPING IBR/NON IBR | M23705000000 | 30 | Inch Dia |
353 | 353 | HACKSAW CUTTING S.S PIPING IBR/NON IBR | M23706000000 | 10 | Inch Dia |
354 | 354 | BEVELLING S.S PIPING IBR/NON IBR | M23707000000 | 40 | Inch Dia |
355 | 355 | FITUP & WELDING S.S PIPING IBR/NON IBR | M23708000000 | 40 | Inch Dia |
356 | 356 | FLAME CUTTING A.S PIPING IBR/NON IBR | M23709000000 | 15 | Inch Dia |
357 | 357 | HACKSAW CUTTING A.S PIPING IBR/NON IBR | M23710000000 | 5 | Inch Dia |
358 | 358 | BEVELLING A.S PIPING IBR/NON IBR | M23711000000 | 20 | Inch Dia |
359 | 359 | FITUP & WELDING A.S PIPING IBR/NON IBR | M23712000000 | 20 | Inch Dia |
360 | 360 | FLAME CUTTING NICKEL/MONEL/INCOLOY PIPING | M23713000000 | 10 | Inch Dia |
361 | 361 | HACKSAW CUTTING NICKEL/MONEL/INCOLOY PIPING | M23714000000 | 10 | Inch Dia |
362 | 362 | BEVELLING NICKEL/MONEL/INCOLOY PIPING | M23715000000 | 10 | Inch Dia |
363 | 363 | FITUP & WELDING NICKEL/MONEL/INCOLOY PIPING | M23716000000 | 10 | Inch Dia |
364 | 364 | REMOVAL ERECTED PIPING(ABOVE GROUND):- Removal of piping existing/ erected including SW valves for modification as required as per Drawings/ P&IDs/instructions of Engineer-in-charge at all elevations, including providing assistance to owner for draining, cleaning and purging of the lines to be removed, unbolting of flanged joints /cutting of pipe lines wherever required, installation of flanges and blind flanges, removal of insulation from insulated lines, removing supports, steam tracers, all fittings and flanges, instruments etc, cutting of pipes in appropriate length for transporting purposes, cleaning, flushing, drying and transporting all materials to storage point (within the complex battery limits) designated by Owner/EIL including stacking of material and disposing of waste etc as instructed by Engineer-in-charge. | M23800000000 | ||
365 | 365 | C.S/A.S PIPING | M23801000000 | 27315 | Inch M |
366 | 366 | S.S PIPING | M23802000000 | 160 | Inch M |
367 | 367 | NICKEL/MONEL/INCOLOY PIPING | M23803000000 | 20 | Inch M |
368 | 368 | LOW FRICTION PADS: Fabrication and fixing of low friction pads with suitable bonding materials / fasteners, as specified in Drawings / Isometrics / Special support sketches. | M24100000000 | ||
369 | 369 | TEFLON PAD WITH COMPRESSIVE STRENGTH (0.25 OFFSET) :1870 PSI | M24101000000 | 0.05 | Cu. M |
370 | 370 | GRAPHITE PAD WITH COMPRESSIVE STRENGTH : 2877 PSI | M24102000000 | 0.05 | Cu. M |
371 | 371 | PRE-COMMISSIONING / COMMISSIONING ASSISTANCE: Carrying out Pre-commissioning / Commissioning activities such as dropping the valves, control valves and spool pieces, air and water flushing and air-blasting, steam blowing, air drying, re-installing the valves, control valves and spool pieces, leak testing etc. as per pre-commissioning / commissioning specification/ procedure and instruction of Engineer-incharge including supply of necessary hand tools, equipments/ machinery, consumables (electrodes, filler wire, gas, card board, target plate, scaffolding etc. wherever required) and with single point responsibility of Contractor's supervision.\n\nNote : This manpower will be utilized for Pre-commissioning & Commissioning requirement over and above that already described elsewhere in this SOR.One Man day is 12 hour duty. | M24200000000 | ||
372 | 372 | SKILLED (WITH HAND TOOLS, EQUIPMENT/' MACHINERY, CONSUMABLES | M24201000000 | 939 | MANDAY |
373 | 373 | SEMI SKILLED (WITH HAND TOOLS) | M24202000000 | 939 | MANDAY |
374 | 374 | HELPER/ UNSKILLED | M24203000000 | 2860 | MANDAY |
375 | 375 | CALLIBRATION OF SAFETY VALVES : Cleaning, set pressure tests of pressure relief and thermal relief valves before installation, providing equipments, necessary test jig, instrument air, nitrogen cylinders, all consumables including dropping/shifting of the PSV's/TSV's from the installed position (if required) to workshop for calibration/re-calibration/re-checking, etc., and reinstall back to original location including parts replacement, gasket, stud/bolts etc., re-fixing of the PSV's /TSV's including lapping (if required) but excludes flow calibration, calibration/test reports and excluding supply of valves.\nNote : Size mentioned below are Safety Valve Inlet Size | M25100000000 | ||
376 | 376 | NB 0.750 INCHES | M25100000500 | 373 | Nos |
377 | 377 | NB 1.000 INCHES | M25100000600 | 1 | Nos |
378 | 378 | NB 1.500 INCHES | M25100000800 | 1 | Nos |
379 | 379 | NB 2.000 INCHES | M25100000900 | 1 | Nos |
380 | 380 | NB 3.000 INCHES | M25100001100 | 5 | Nos |
381 | 381 | NB 4.000 INCHES | M25100001300 | 1 | Nos |
382 | 382 | NB 6.000 INCHES | M25100001500 | 1 | Nos |
383 | 383 | NB 8.000 INCHES | M25100001600 | 3 | Nos |
384 | 384 | PIPE DAVITS | M25200000000 | ||
385 | 385 | Fabrication & erection of pipe davits as per EIL std. 7-12-023 for lowering of aircooler motors/safety valves from structural platforms, fixing the same to platforms, inspection as per specs., supply of all necessary equipment, consumables, labour, supervision etc. The work shall be carried out as per the specifications, drawings & instruction of Engineer-in-charge. | M25201000000 | 1 | MT |
386 | 386 | DISMANTLING AND RE-ERECTION OF VALVES: Debolting / Dismantling / dropping of all types & ratings of erected valves viz. Control Valves, Safety Valves, Remote Operated Valves, Motor Operated Valves, Shut-Down Valves & Non Return Valve and re-erection at all elevation/location, installation & tightening of gaskets, bolts nuts by consumable, tools and tackles etc. & complete the work in all respect as per the drawing, instruction of owner¿s / Engineers-in-Charge. | M26000000000 | ||
387 | 387 | CONTROL VALVES (UPTO 600#) | M26003000000 | ||
388 | 388 | NB 1.000 INCHES | M26003000600 | 17 | Nos |
389 | 389 | NB 1.500 INCHES | M26003000800 | 9 | Nos |
390 | 390 | NB 2.000 INCHES | M26003000900 | 18 | Nos |
391 | 391 | NB 3.000 INCHES | M26003001100 | 27 | Nos |
392 | 392 | NB 4.000 INCHES | M26003001300 | 16 | Nos |
393 | 393 | NB 6.000 INCHES | M26003001500 | 26 | Nos |
394 | 394 | NB 8.000 INCHES | M26003001600 | 10 | Nos |
395 | 395 | NB 10.000 INCHES | M26003001700 | 16 | Nos |
396 | 396 | NB 12.000 INCHES | M26003001800 | 1 | Nos |
397 | 397 | NB 14.000 INCHES | M26003001900 | 3 | Nos |
398 | 398 | NB 16.000 INCHES | M26003002000 | 1 | Nos |
399 | 399 | NB 18.000 INCHES | M26003002100 | 1 | Nos |
400 | 400 | CONTROL VALVES (900# & ABOVE) | M26004000000 | ||
401 | 401 | NB 8.000 INCHES | M26004001600 | 1 | Nos |
402 | 402 | PRESS. RELIEF/ SAFETY VALVES, PILOT OP. SAFETY VALVES (UPTO 600#) ( Size are valve inlet size) | M26011000000 | ||
403 | 403 | NB 0.750 INCHES | M26011000500 | 373 | Nos |
404 | 404 | NB 1.000 INCHES | M26011000600 | 1 | Nos |
405 | 405 | NB 1.500 INCHES | M26011000800 | 1 | Nos |
406 | 406 | NB 2.000 INCHES | M26011000900 | 1 | Nos |
407 | 407 | NB 3.000 INCHES | M26011001100 | 5 | Nos |
408 | 408 | NB 4.000 INCHES | M26011001300 | 1 | Nos |
409 | 409 | NB 6.000 INCHES | M26011001500 | 1 | Nos |
410 | 410 | NB 8.000 INCHES | M26011001600 | 1 | Nos |
411 | 411 | MANHOLE OPENING AND BOX UP (FOR SIZE FROM 20" TO 40" DIA., ALL RATINGS) : Opening of manhole flanges of static equipments at any elevation & re-boxing up of the same, cleaning of mating surfaces of flanges, Cleaning & greasing of bolts & nuts, providing gaskets, stud nuts ( gaskets & stud nuts to be issued from owner store & transported to site if required), tightening the bolts by manual / torque wrench/ tensioner by providing all necessary manpower, tools & tackles, Torque wrench / Bolt tensioner ( wherever required), Lapping Paste, scaffolding, consumables etc. and complete the job in all respect up to the satisfaction / instruction of owner's / engineer in charge. | M26200000000 | 20 | Nos |
412 | 412 | Installation of Static Fuel Gas Mixture, providing supports, etc. as per vendor drawings. | M29900400000 | ||
413 | 413 | NB 10.000 INCHES | M29900430000 | 1 | Nos |
414 | 414 | NB 4.000 INCHES | M29900440000 | 1 | Nos |
415 | 415 | Fabrication and fixing of low friction pad (SS 304 mirror finish) with suitable bonding material/ fasteners as specified in drawing/ documents/special support sketches/isometrics/Gads etc. | M29900500000 | ||
416 | 416 | STAINLESS STEEL 6 MM THK WITH MIRROR FINISH SS304 | M29900510000 | 0.65 | Cu. M |
417 | 417 | Transportation of pre-fabricated spool piece from Owner'storage points to Contractor's store / work site, including rectification of damaged bevelling, if any erection of spools on rack and at all elevations,connecting with equipment Nozzles including fixing of gaskets,nuts,bolts, cutting of spools, edge preparation, wherever required, fitup ,welding, hydrotesting, alignment, cleaning, flushing by water / compressed air,drying (excluding support which shall be paid seperately). Contractor also have to modify and use the existing pipes and fittings to create new spools to suit at site conditions. The work shall be carried out as per drawing / document and as per the instruction of Engineer-In-Charge. | M29900700000 | ||
418 | 418 | ERECTION OF PRE-FABRICATED SPOOLS ALL TYPES OF MATERIAL (CS / AS / SS) | M29900710000 | ||
419 | 419 | UP TO 1.5 INCHES | M29900711000 | 585 | Inch M |
420 | 420 | NB 2.0 INCHES - 6.0 INCHES | M29900712000 | 1950 | Inch M |
421 | 421 | NB 8.0 INCHES - 14.0 INCHES | M29900713000 | 2340 | Inch M |
422 | 422 | NB 16.0 INCHES - 24.0 INCHES | M29900714000 | 2210 | Inch M |
423 | 423 | FIELD JOINTS OF PRE-FABRICATED SPOOLS ALL TYPES OF MATERIAL (CS / AS / SS) | M29900720000 | ||
424 | 424 | UP TO 1.5 INCHES | M29900721000 | 325 | Inch Dia |
425 | 425 | NB 2.0 INCHES - 6.0 INCHES | M29900722000 | 520 | Inch Dia |
426 | 426 | NB 8.0 INCHES - 14.0 INCHES | M29900723000 | 780 | Inch Dia |
427 | 427 | NB 16.0 INCHES - 24.0 INCHES | M29900724000 | 650 | Inch Dia |
428 | 428 | STIFFNER RING FROM PLATE :(CS/ AS/ SS PLATE) Fabrication of stiffner rings from Plates (MAX - 10 mm thk/Structural steel wherever required at all elevations (material supplied by B&R) including erection, fit up,welding, testing (including DP) on pipe as per specifications, drawings and as per instructions of Engineer-in-charge. | M29904000000 | ||
429 | 429 | Stiffner Rings from CS Plate | M29904010000 | 3 | MT |
430 | 430 | Stiffner Rings from AS Plate | M29904020000 | 0.13 | MT |
431 | 431 | Stiffner Rings from SS Plate | M29904030000 | 0.13 | MT |
432 | 432 | MECHANICAL EQUIPMENT: | Q101.00.00 | ||
433 | 433 | Transportation of Equipment from owners storage point to work site/contractors stores. Assembly of subassemblies placing the equipment on foundations, levelling, aligning, fixing of foundation bolts including chipping and dressing of foundations, grouting (grouting material will be provided by B&R as free issue), cleaning and flushing with water, draining and drying with compressed air, erection of inter- connecting piping including some amount of cutting and welding where ever required. Purging the line with air/gas providing manpower for carrying out trial and start up runs and testing under the supervision guidance of manufacturer/clients- personnel and rectifying defects of any and completing the work in all respects as per drawing, specifications and instructions of engineer in charge for each equipment including drives and accessories, as listed below : | Q101.01.00 | ||
434 | 434 | Unloading Arms & Vapour Return Arms | Q101.01.11M01 | 5.4 | MT |
435 | 435 | Miscellaneous | Q999.00.00 | ||
436 | 436 | Miscellaneous | Q999.99.00 | ||
437 | 437 | Vapour Recovery System (323-LZ-1003):- Transportation of Equipment from owner's storage point to work site / contractors stores. Assembly of subassemblies, placing the equipment on foundations, levelling, aligning, fixing of foundation bolts including chipping and dressing of foundations, grouting (grouting material will be provided by B&R as free issue), cleaning and flushing with water, draining and drying with compressed air, erection of inter - connecting piping including some amount of cutting and welding where-ever required. Filling of adsorbent in vessels, Purging the line with air / gas, providing manpower for carrying out trial and start up runs and testing under the supervision / guidance of manufacturer / client's personnel and rectifying defects if any and completing the work in all respects as per drawing, specifications and instructions of Engineer-In-Charge for the following equipment including drives and accessories. Refer scope of work for details. | Q999.99.99V01 | 75 | MT |
438 | 438 | Vapour Recovery System (323-LZ-1004):- Transportation of Equipment from owner's storage point to work site / contractors stores. Assembly of subassemblies, placing the equipment on foundations, levelling, aligning, fixing of foundation bolts including chipping and dressing of foundations, grouting (grouting material will be provided by B&R as free issue), cleaning and flushing with water, draining and drying with compressed air, erection of inter - connecting piping including some amount of cutting and welding where-ever required.Filling of activated Carbon in vessels, Purging the line with air / gas, providing manpower for carrying out trial and start up runs and testing under the supervision / guidance of manufacturer / client's personnel and rectifying defects if any and completing the work in all respects as per drawing, specifications and instructions of Engineer-In-Charge for the following equipment including drives and accessories. Refer scope of work for details. | Q999.99.99V02 | 65 | MT |
439 | 439 | 0.5 MT Capacity CPB with associated geared trolley\n\nTransportation of Equipment from owner's storage point to work site/contractors stores. Assembly of subassemblies, placing the equipment on monorail, levelling, aligning, fixing of bolts, providing manpower for carrying out trial and start up runs and testing under the supervision guidance of manufacturer/clients- personnel and rectifying defects of any and completing the work in all respects as per drawing, specifications and instructions of engineer in charge for each equipment including accessories. Also refer Scope of work attached with the tender. | Q999.99.99V10 | 1 | NOS |
440 | 440 | 1 MT Capacity CPB with associated geared trolley\n\nTransportation of Equipment from owner's storage point to work site/contractors stores. Assembly of subassemblies, placing the equipment on monorail, levelling, aligning, fixing of bolts, providing manpower for carrying out trial and start up runs and testing under the supervision guidance of manufacturer/clients- personnel and rectifying defects of any and completing the work in all respects as per drawing, specifications and instructions of engineer in charge for each equipment including accessories. Also refer Scope of work attached with the tender. | Q999.99.99V11 | 1 | NOS |
441 | 441 | 2 MT Capacity CPB with associated geared trolley\n\nTransportation of Equipment from owner's storage point to work site/contractors stores. Assembly of subassemblies, placing the equipment on monorail, levelling, aligning, fixing of bolts, providing manpower for carrying out trial and start up runs and testing under the supervision guidance of manufacturer/clients- personnel and rectifying defects of any and completing the work in all respects as per drawing, specifications and instructions of engineer in charge for each equipment including accessories. Also refer Scope of work attached with the tender. | Q999.99.99V12 | 1 | NOS |
442 | 442 | 3 MT Capacity CPB with associated geared trolley\n\nTransportation of Equipment from owner's storage point to work site/contractors stores. Assembly of subassemblies, placing the equipment on monorail, levelling, aligning, fixing of bolts, providing manpower for carrying out trial and start up runs and testing under the supervision guidance of manufacturer/clients- personnel and rectifying defects of any and completing the work in all respects as per drawing, specifications and instructions of engineer in charge for each equipment including accessories. Also refer Scope of work attached with the tender. | Q999.99.99V13 | 1 | NOS |
443 | 443 | 5 MT Capacity CPB with associated geared trolley\n\nTransportation of Equipment from owner's storage point to work site/contractors stores. Assembly of subassemblies, placing the equipment on monorail, levelling, aligning, fixing of bolts, providing manpower for carrying out trial and start up runs and testing under the supervision guidance of manufacturer/clients- personnel and rectifying defects of any and completing the work in all respects as per drawing, specifications and instructions of engineer in charge for each equipment including accessories. Also refer Scope of work attached with the tender. | Q999.99.99V14 | 1 | NOS |
444 | 444 | 7.5 MT Capacity CPB with associated geared trolley\n\nTransportation of Equipment from owner's storage point to work site/contractors stores. Assembly of subassemblies, placing the equipment on monorail, levelling, aligning, fixing of bolts, providing manpower for carrying out trial and start up runs and testing under the supervision guidance of manufacturer/clients- personnel and rectifying defects of any and completing the work in all respects as per drawing, specifications and instructions of engineer in charge for each equipment including accessories. Also refer Scope of work attached with the tender. | Q999.99.99V15 | 1 | NOS |
445 | 445 | 10 MT Capacity CPB with associated geared trolley\n\nTransportation of Equipment from owner's storage point to work site/contractors stores. Assembly of subassemblies, placing the equipment on monorail, levelling, aligning, fixing of bolts, providing manpower for carrying out trial and start up runs and testing under the supervision guidance of manufacturer/clients- personnel and rectifying defects of any and completing the work in all respects as per drawing, specifications and instructions of engineer in charge for each equipment including accessories. Also refer Scope of work attached with the tender. | Q999.99.99V16 | 1 | NOS |
446 | 446 | Rotating Equipment | R000.00.00 | ||
447 | 447 | Transportation of Rotating Equipment & miscellaneous items from Owner's storage points to work site / contractor's stores, assembly of sub-assemblies, placing the equipments on foundations, erection of interconnecting piping, levelling, aligning, including chipping & dressing of foundations, grouting (grouting material will be provided by B&R as free issue), and providing manpower for testing, rectifying defects if any and completing the work in all respects as per drawings, Job specification for Mechanical Tender (Rotating Equipment) enclosed and instructions of Engineer-incharge. | R001.00.00 | ||
448 | 448 | All Types of Pumps with Drivers (Electric Motor or General Purpose Steam Turbine) and accessories | R001.01.00 | 465 | MT |
449 | 449 | Reciprocating Compressors with Electric Motor Driver and accessories mounted on foundation block | R001.08.00 | 30 | MT |
450 | 450 | STATIC EQUIPMENT | V151.00.00 | ||
451 | 451 | Transportation of reactors, columns, vessels, silencers, heat exchangers (shell and tube, plate fin, plate) and electric heater etc. from owner's storage point to work site, assembly of parts, subassemblies, erection at all elevations, aligning, verticality checking, grouting (grouting material will be provided by B&R as free issue), tightening of foundation bolts, welding of washer on anchor chairs, erection of wooden pillow for cold equipments, stacking of multi-tier exchanger (which are stored in unstacked condition), providing hooks for test ring/ test flanges in heat exchangers, installation of demister, internal gratings, distributor, pipe davit, installation of mixer/agitator, cleaning and flushing by water, draining, drying by compressed air, providing all tools, tackles, machinery, consumables, transportation equipment, erection equipment, instruments, labour, ancillary, etc. to complete the work in all respects as per drawings, equipment detail, specifications and instructions of the Engineer-in-Charge. | V151.02.00 | ||
452 | 452 | Equipment weighing less than 30 MT but 10 MT and above | V151.02.04 | 15.5 | MT |
453 | 453 | Equipment weighing less than 10 MT | V151.02.05 | 21.8 | MT |
454 | 454 | Hydrostatic Testing | V170.00.00 | ||
455 | 455 | HYDROSTATIC TESTING OF EXCHANGERS (shell and tube): Hydrostatic testing of exchangers single tier or multitier including dismantling and reassembling of piping connections wherever required, providing blinds and gaskets on nozzles, piping, water hoses, gauges, valves, test pumps and all other temporary arrangements, labour and materials, drying by hot compressed air as per specifications and instructions of Engineer-in-Charge. In case, if leakage is found in gaskets and gaskets are replaced, then rehydrotest to be done with new gasket after reassembly. | V170.01.00 | ||
456 | 456 | Hydrotesting of shell side | V170.01.01 | 1 | NOS |
457 | 457 | Hydrotesting of tube side | V170.01.02 | 1 | NOS |
458 | 458 | Erection of Air Fin Coolers | V263.00.00 | ||
459 | 459 | ERECTION OF AIR COOLERS(AFC) - NON-MODULAR CONSTRUCTION:- Transportation of air cooler Components Consisting Tube bundles/ Sections/ Bays, Motors, Fans, Plenum chambers etc. along with structural columns/beams (dispatched as loose by others) from Owner's storage points to erection site, erection / assembly of complete Air Fin Cooler(as per the setting plan attached else ehere in the tender) including erection/installation of structural columns, assembly of parts & sub-assemblies, erection at all elevations, aligning, verticality checking, grouting (grouting material will be provided by B&R as free issue), tightening of foundation/ anchor bolts, removing the temporary bracing and installing the permanent bracings, installation of ladder, staircase, handrails and platforms all around, matching of TOG level of platforms as mentioned in respective datasheets, laying cables, installation of junction boxes, trial run of one bay for each tag number after erection, ensuring vibration free operation, carrying out necessary modification required in case of any vibration, arranging all tools, tackles, machinery, consumables, transportation equipment, erection equipment, instruments, labour, ancillary, etc. to complete the work in all respects as per drawings, equipment detail, specifications and instructions of the Engineer-in-Charge.\n\nNote: Installation, erection, trial run and any modification work in case of vibration shall be carried out under supervision of air cooler supplier. | V263.02.00 | ||
460 | 460 | Equipment/AFC Package weighing less than 10 MT | V263.02.05 | 5 | MT |
461 | 461 | ERECTION OF BURIED EQUIPMENT : Transportation of vessels from Owner's storage point to worksite, supply of all accessories, equipments, labour etc., placing/erection of vessel in trenches/pits including assembly of parts, subassemblies, aligning, verticality checking, grouting (grouting material will be provided by B&R as free issue), tightening of foundation bolts, providing all tools, tackles, machinery, consumables etc to complete the work in all respects as per drawings, equipment detail, specifications and instructions of the Engineer-in-Charge. | V266.01.00 | ||
462 | 462 | Equipment weighing less than 30 MT but 10 MT and Above | V266.01.04 | 150.4 | MT |
463 | 463 | Welding of Cut Nozzles/Sump/Boot of burried vessels\nAssembly of cut nozzles/Sump/Boot (as shown in Respective Engg. Data Sheet), vertically checking, alignment, Welding of cut nozzles, providing all tools and tackles, machinery, consumables, transportation/handling of equipment, labour etc to complete the work in all respects as per drawings & instruction of Engineer-in charge. | V267.01.00 | ||
464 | 464 | MOC : Carbon Steel ,Nozzle size : 4" | V267.01.03 | 6 | Nos |
465 | 465 | MOC : Carbon Steel ,Nozzle size : 6" | V267.01.04 | 6 | Nos |
466 | 466 | MOC : Carbon Steel ,Nozzle size : 8" | V267.01.05 | 6 | Nos |
467 | 467 | MOC : Carbon Steel ,Nozzle size : 16" | V267.01.09 | 6 | Nos |
468 | 468 | MOC : Carbon Steel ,Nozzle size : 24" | V267.01.12 | 24 | Nos |
469 | 469 | Hydro testing of Vessels in IBR service | V274.00.00 | ||
470 | 470 | HYDROSTATIC TESTING OF VESSEL UNDER IBR SERVICE: Hydrostatic testing of vessels including dismantling and reassembling of piping connections wherever required, providing blinds and gaskets on nozzles, piping, water hoses, gauges, valves, test pumps and all other temporary arrangements, labour and materials, drying by hot compressed air as per specifications and instructions of Engineer-in-Charge. In case, if leakage is found in gaskets and gaskets are replaced, then re-hydro test to be done with new gasket after reassembly.\nObtaining necessary IBR approvals/ certificates on this account, as per the instructions of Engineer-In-Charge, is also be included in contractor scope within the quoted price. | V274.01.00 | ||
471 | 471 | Hydrotesting of Vessel (IBR) with Equipment (Equipment no: 323-V-1001) | V274.01.01V20 | 1 | LS |
472 | 472 | STRUCTURAL STEEL WORKS (REFER SPECIFICATION NO. 6-68-0006) | S004.00.00 | ||
473 | 473 | General Steel Works - FIM Items | S004.01.00 | ||
474 | 474 | Transporting from storage yard (or any other location as specified by engineer-in-charge), Storing, Assembling and Erecting in position and testing/ examining, bolted and/ or welded, already Fabricated STRUCTURAL STEEL (of any Grade) at all locations and levels UPTO & INCLUSIVE OF 20 m ABOVE HPP/ FGL, including all builtup sections/ compound sections made out of rolled/ hollow sections and/or plates/ bent plates in all types of structural frameworks, fixing in line and level with temporary staging & bracing and removal of the same after erection, grouting with Ordinary Grout or premix free flow Nonshrink Grout (grouting material will be provided by B&R as free issue) as specified etc., all complete.\nALREADY FABRICATED STRUCTURAL STEEL SHALL (WITH CONNECTION BOLTS) BE PROVIDED TO CONTRACTOR FREE OF COST. SUPPLY OF ALL OTHER MATERIAL IN CONTRACTOR'S SCOPE. | S004.01.05 | 15 | MT |
475 | 475 | Transporting from storage yard (or any other location as specified by engineer-in-charge), Storing, Assembling and Erecting in position and testing/ examining, bolted and/ or welded, already Fabricated STRUCTURAL STEEL (of any Grade) at all locations and levels MORE THAN 20 m ABOVE HPP/ FGL, including all builtup sections/ compound sections made out of rolled/ hollow sections and/or plates/ bent plates in all types of structural frameworks, fixing in line and level with temporary staging & bracing and removal of the same after erection, grouting with Ordinary Grout or premix free flow Nonshrink Grout (grouting material will be provided by B&R as free issue) as specified etc., all complete.\nALREADY FABRICATED STRUCTURAL STEEL SHALL (WITH CONNECTION BOLTS) BE PROVIDED TO CONTRACTOR FREE OF COST. SUPPLY OF ALL OTHER MATERIAL IN CONTRACTOR'S SCOPE. | S004.01.06 | 6 | MT |
476 | 476 | Dismantling, modification & re-erecting in position and testing/ examining bolted and/ or welded STRUCTURAL STEEL WORKS ALREADY ERECTED BY OTHERS at all locations and levels UPTO & INCLUSIVE OF 20 m ABOVE HPP/ FGL, including all builtup sections/ compound sections made out of rolled sections and/or plates/ bent plates in all types of structural frameworks, floor beams, stairs, or any other structural items or accessories to support equipments, piping, conveyor galleries, towers, masts, etc., but excluding silos, bunkers, hoppers, etc., cutting to required size, straightening/ bending if required, edge preparation, cleaning, preheating, bolting/ welding of joints, (including sealing the joints of box sections with continuous welding and plugging any open ends & holes of box sections), finishing edges by grinding, fixing in line and level with temporary staging & bracing and removal of the same after erection, grouting with Ordinary Grout or premix free flow Nonshrink Grout (grouting material will be provided by B&R as free issue) as specified etc., all complete.\nSUPPLY OF ALL OTHER MATERIAL (OTHER THAN ALREADY ERECTED STRUCTURAL STEEL) IN CONTRACTOR'S SCOPE. | S004.01.07 | 40 | MT |
477 | 477 | Dismantling, modification & re-erecting in position and testing/ examining bolted and/ or welded STRUCTURAL STEEL WORKS ALREADY ERECTED BY OTHERS at all locations and levels MORE THAN 20 m ABOVE HPP/ FGL, including all builtup sections/ compound sections made out of rolled sections and/or plates/ bent plates in all types of structural frameworks, floor beams, stairs, or any other structural items or accessories to support equipments, piping, conveyor galleries, towers, masts, etc., but excluding silos, bunkers, hoppers, etc., cutting to required size, straightening/ bending if required, edge preparation, cleaning, preheating, bolting/ welding of joints, (including sealing the joints of box sections with continuous welding and plugging any open ends & holes of box sections), finishing edges by grinding, fixing in line and level with temporary staging & bracing and removal of the same after erection, grouting with Ordinary Grout or premix free flow Nonshrink Grout (grouting material will be provided by B&R as free issue) as specified etc., all complete. SUPPLY OF ALL OTHER MATERIAL (OTHER THAN ALREADY ERECTED STRUCTURAL STEEL) IN CONTRACTOR'S SCOPE. | S004.01.08 | 15 | MT |
478 | 478 | Modification and testing/ examining bolted and/ or welded STRUCTURAL STEEL WORKS ALREADY FABRICATED BY OTHERS, including all builtup/ compound sections made out of rolled/ hollow sections and/or plates/ bent plates in all types of structural frameworks, floor beams, stairs, or any other structural items or accessories to support equipments, piping, conveyor galleries, towers, masts, etc., but excluding silos,bunkers, hoppers, etc., cutting to required size, straightening/ bending if required, edge preparation, cleaning, preheating, bolting/ welding of joints, (including sealing the joints of box sections with continuous welding and plugging any open ends & holes of box sections), finishing edges by grinding etc., all complete as specified and directed. SUPPLY OF ALL OTHER MATERIAL (OTHER THAN ALREADY FABRICATED STRUCTURAL STEEL) IN CONTRACTOR'S SCOPE. | S004.01.09 | 10 | MT |
479 | 479 | General Steel Works | S004.03.00 | ||
480 | 480 | Transporting, storing, fabricating & erecting in position and testing/ examining bolted and/ or welded STRUCTURAL STEEL WORKS of Grade E250A / E250BR / E250B0 (confirming to per IS:2062) at all locations and levels UPTO & INCLUSIVE OF 20 m ABOVE HPP/ FGL, including all builtup sections/ compound sections made out of rolled sections and/or plates/ bent plates in all types of structural frameworks, floor beams, stairs, or any other structural items or accessories to support equipments, piping, conveyor galleries, towers, masts, etc., but excluding silos, bunkers, hoppers, etc., cutting to required size, straightening/ bending if required, edge preparation, cleaning, preheating, bolting/ welding of joints, (including sealing the joints of box sections with continuous welding and plugging any open ends & holes of box sections), finishing edges by grinding, fixing in line and level with temporary staging & bracing and removal of the same after erection, grouting with Ordinary Grout or premix free flow Nonshrink Grout (grouting material will be provided by B&R as free issue) as specified (or as per Job Specification, wherever applicable) after fabrication etc., all complete. SUPPLY OF ALL MATERIAL IN CONTRACTOR'S SCOPE. | S004.03.03 | 100 | MT |
481 | 481 | Transporting, storing, fabricating & erecting in position and testing/ examining bolted and/ or welded STRUCTURAL STEEL WORKS of Grade E250A / E250BR / E250B0 (confirming to per IS:2062) at all locations and levels MORE THAN 20 m ABOVE HPP/FGL, including all builtup sections/ compound sections made out of rolled sections and/or plates/ bent plates in all types of structural frameworks, floor beams, stairs, or any other structural items or accessories to support equipments, piping, conveyor galleries, towers, masts, etc., but excluding silos, bunkers, hoppers, etc., cutting to required size, straightening/ bending if required, edge preparation, cleaning, preheating, bolting/ welding of joints, (including sealing the joints of box sections with continuous welding and plugging any open ends & holes of box sections), finishing edges by grinding, fixing in line and level with temporary staging & bracing and removal of the same after erection, grouting with Ordinary Grout or premix free flow Nonshrink Grout (grouting material will be provided by B&R as free issue) as specified, (or as per Job Specification, wherever applicable) after fabrication etc., all complete. SUPPLY OF ALL MATERIAL IN CONTRACTOR'S SCOPE. | S004.03.04 | 50 | MT |
482 | 482 | Transporting, storing, fabricating & erecting in position and testing/ examining bolted and/ or welded STRUCTURAL STEEL WORKS of Grade E350BR / E350B0 (conforming to IS:2062) at all locations and levels UPTO & INCLUSIVE OF 20 m ABOVE HPP/ FGL, including all builtup sections/ compound sections made out of rolled sections and/ or plates/ bent plates in all types of structural frameworks, floor beams, stairs, or any other structural items or accessories to support equipments, piping, conveyor galleries, towers, masts, etc., but excluding silos, bunkers, hoppers, etc., cutting to required size, straightening/ bending if required, edge preparation, cleaning, preheating, bolting/ welding of joints, (including sealing the joints of box sections with continuous welding and plugging any open ends & holes of box sections), finishing edges by grinding, fixing in line and level with temporary staging & bracing and removal of the same after erection, grouting with Ordinary Grout or premix free flow Nonshrink Grout (grouting material will be provided by B&R as free issue) as specified, (or as per Job Specification, wherever applicable) after fabrication etc., all complete. SUPPLY OF ALL MATERIAL IN CONTRACTOR'S SCOPE. | S004.03.13 | 50 | MT |
483 | 483 | Transporting, storing, fabricating & erecting in position and testing/ examining bolted and/ or welded STRUCTURAL STEEL WORKS of Grade E350BR / E350B0 (conforming to IS:2062) at all locations and levels MORE THAN 20 m ABOVE HPP/ FGL, including all builtup sections/ compound sections made out of rolled sections and/or plates/ bent plates in all types of structural frameworks, floor beams, stairs, or any other structural items or accessories to support equipments, piping, conveyor galleries, towers, masts, etc., but excluding silos, bunkers, hoppers, etc., cutting to required size, straightening/ bending if required, edge preparation, cleaning, preheating, bolting/ welding of joints, (including sealing the joints of box sections with continuous welding and plugging any open ends & holes of box sections), finishing edges by grinding, fixing in line and level with temporary staging & bracing and removal of the same after erection, grouting with Ordinary Grout or premix free flow Nonshrink Grout (grouting material will be provided by B&R as free issue) as specified, (or as per Job Specification, wherever applicable) after fabrication etc., all complete. SUPPLY OF ALL MATERIAL IN CONTRACTOR'S SCOPE. | S004.03.14 | 20 | MT |
484 | 484 | Fabricating, Transporting and Erecting in position bolted and/ or welded Structural Steel works of Grade E350BR/ E350B0 (confirming to IS:2062) at all levels & locations, comprising of rolled/ built-up sections made of joists, channels, angles, flats rounds, plates cut and/ or bent to any shape and size, in beams, girders, trusses columns, brackets, bracings, ladders (with or without cage), safety chain brackets, staircases, handrailings and platforms of any shape and size (excluding chequered plates/ gratings), on vertical and/ or horizontal equipments, in miscellaneous valve operating platforms, pipe supports etc, straightening, cutting and/ or bending the steel to required size/ shape, edge preparation, preheating, bolting, welding of joints (including sealing of joints of box sections with continuous welding wherever shown), grinding the prepared edges/ surfaces to asmooth finish, fixing in line and level with temporary staging and removal of the same after erection, grouting below base plates with free flow non shrink/ ordinary grout (grouting material will be provided by B&R as free issue) as specified to bring them to required levels, removing from site of work all scrap/ unserviceable steel etc, all complete as shown, specified and directed. | S004.03.33M01 | 20 | MT |
485 | 485 | STRUCTURAL STEEL WORKS (TUBULAR/HOLLOW SECTION) | S005.00.00 | ||
486 | 486 | Yst310 IS4923 | S005.07.00 | ||
487 | 487 | Transporting, storing, fabricating, erecting in position & testing/examining at all locations and levels, bolted and/or welded STRUCTURAL STEEL WORKS of all types using "COLD FORMED (RECTANGULAR/SQUARE) HOLLOW SECTIONS conforming to IS: 4923, Grade Yst-310 of approved make" in all type of trusses, purlins, girders, side rails, columns, runners, beams, ties, portals, framework,bracing, brackets, sagrods etc. including all handling straightening/bending if required, cutting to required size & shape, edge preparation, welding & bolting of joints, fixing end caps and plugging holes, fixing in line and level with necessary temporary staging and removal of the same after erection, grouting with Ordinary/ premix free flow Non-Shrink Grout (grouting material will be provided by B&R as free issue) as specified, (or as per Job Specification, wherever applicable) etc. all complete as specified and directed (SUPPLY OF ALL MATERIALS INCLUDING PLATES IN CONTRACTOR'S SCOPE). | S005.07.03 | 10 | MT |
488 | 488 | MISCELLANEOUS STEEL WORKS | S006.00.00 | ||
489 | 489 | MS Chequered Plates | S006.03.00 | ||
490 | 490 | Fabricating and erecting in position at all levels and locations bolted, screwed and/or welded M.S. CHEQUERED PLATES of any thickness in walkways, platforms, stairtreads or any other place as directed, etc. including handling, transporting the same from owner's store/issue points to site workshop and site of work, cutting to required size, shape, making holes, notches, openings of required size, nosing, straightening if required, making the edges smooth, removing the burrs, fixing, welding and return of unused/ scrap/ unserviceable\nchequered plates to Owner's store and material reconciliation etc. all complete as specified and directed.\n | S006.03.01 | 2 | MT |
491 | 491 | MS Gratings - Cat. A | S006.04.00 | ||
492 | 492 | Transporting from storage yard (or any other location as specified by engineer-in-charge), storing & erecting in position at all levels and locations ELECTROFORGED GALVANISED GRATING ALREADY FABRICATED BY OTHERS conforming to EIL Standard No. 7-68-0697 (in walkways, platforms, stair treads etc.) and EIL Standard No. 7-65-0206 (in catch basins, drains, etc.) including cutting to required size, shape, making holes, notches, openings of required size, nosing, straightening if required, making the edges smooth, removing the burrs, fixing with welding or supplied galvanised clamps as applicable, all complete as specified and directed.\nALREADY FABRICATED GRATINGS SHALL BE PROVIDED TO CONTRACTOR FREE OF COST. SUPPLY OF ALL OTHER MATERIALS IN CONTRACTOR'S SCOPE. | S006.04.03 | 2 | MT |
493 | 493 | Hand Railing 1000mm | S006.06.00 | ||
494 | 494 | Transporting from storage yard (or any other location as specified by engineer-in-charge), storing & erecting in position at all levels and locations 1000 mm high HAND RAILING (HORIZONTAL & INCLINED) ALREADY FABRICATED BY OTHERS (for platforms, walkways or any other location as directed etc.) consisting of top rail, mid rail and vertical posts (maximum spacing 1500 mm c/c) with or without toe plates, including handling, straightening if required, cutting, bending, notching, welding, bolting, grouting with ordinary grout etc. and return of unused/ scrap/ unserviceable steel to owner's store & material reconciliation etc. all complete as specified, shown and directed. ALREADY FABRICATED HAND RAILINGS SHALL BE SUPPLIED FREE OF COST. SUPPLY OF ALL OTHER MATERIALS IN CONTRACTOR'S SCOPE. (Complete handrail work shall be measured as length of top rail only and not length of each element fixed). | S006.06.02 | 100 | m |
495 | 495 | MS Grating Cat. A,B | S006.19.00 | ||
496 | 496 | Erecting in position at all levels and locations ELECTROFORGED GALVANISED GRATING conforming to EIL Standard No. 7-68-0697 (in walkways, platforms, stair treads etc.) and EIL Standard No. 7-65-0206 (in catch basins, drains, etc.) including cutting to required size, shape, making holes, notches, openings of required size, nosing, straightening if required, making the edges smooth, removing the burrs, fixing with manufacturer's supplied galvanised clamps, all complete as specified and directed. | S006.19.06 | 20 | MT |
497 | 497 | Making openings in galvanized grating for pipes / ducts etc., at all levels and at at all locations by cutting the existing grating and providing 50x6 galvanised flat as toe protection for the openings by welding and application of galvanized paint as per EIL Standard No. 7-68-0697, all complete. Payment shall be made as per number of openings. All materials in Contractor's Scope. | S006.19.07 | 80 | EACH |
498 | 498 | Hand Railing 1000mm | S006.23.00 | ||
499 | 499 | Fabricating and fixing in position at all locations 1000mm high INCLINED HAND RAILING (for staircases) consisting of top rail, mid rail and vertical posts (Maximum spacing 1500mm c/c) with 32mm nominal diameter medium grade M.S. Tubes conforming to IS:1239 including straightening if required, cutting, bending, welding, bolting, grouting with ordinary grout, etc. all complete as specified, shown and directed. (Complete handrail work shall be measured as length of top rail only and not length of each element fixed). | S006.23.01M01 | 50 | m |
500 | 500 | Fabricating and fixing in position (to already erected vertical posts for Hand Railing) at all locations ONLY TOP RAIL 32mm nominal diameter medium grade M.S. Tubes conforming to IS:1239 including straightening if required, cutting, welding, bending, etc. all complete as specified, shown and directed. | S006.23.02M01 | 100 | m |
501 | 501 | Fabricating and fixing in position at all locations 1000mm high HORIZONTAL HAND RAILING (for platforms, walkways, etc. or any other location as directed) consisting of top rail, mid rail and vertical posts (Maximum spacing 1500mm c/c) with 32mm nominal diameter medium grade MS Tubes conforming to IS:1239 and 100x5 MS Toe Plate confirming to IS:2062 (Grade A/B), including straightening if required, cutting, bending, welding, bolting, grouting with ordinary grout, etc. all complete as specified, shown and directed. (Complete handrail work shall be measured as length of top rail only and not length of each element fixed). | S006.23.03M01 | 1000 | m |
502 | 502 | Hand Railing 500mm | S006.24.00 | ||
503 | 503 | Fabricating and fixing in position at all locations 500mm high HORIZONTAL HAND RAILING (for platforms, walkways, etc. or any other location as directed) consisting of top rail, mid rail and vertical posts (Maximum spacing 1500mm c/c) with 32mm nominal diameter medium grade MS Tubes conforming to IS:1239 and 100x5 MS Toe Plate confirming to IS:2062 (Grade A/B), including straightening if required, cutting, bending, welding, bolting, grouting with ordinary grout, etc. all complete as specified, shown and directed. (Complete handrail work shall be measured as length of top rail only and not length of each element fixed). | S006.24.02M01 | 20 | m |
504 | 504 | Mechanical works | S018.00.00 | ||
505 | 505 | Fabricating and erecting in position MS plates as per detailed drawings, conforming to grade A of IS:2062 on top of all RCC pedestals supporting the sliding saddles of equipments, including cutting, straightening where necessary, rounding rounding unfinished edges by grinding, machining the exposed top surface, making necessary bolt holes, laying ready mixed free flow non-shrink grout below the base plate at all levels & locations, machining top surfaces etc. all complete and as shown and directed. | S018.05.00 | 0.1 | MT |
506 | 506 | SAFETY (REFER EIL SPECIFICATION) | S023.00.00 | ||
507 | 507 | Safety Structures | S023.01.00 | ||
508 | 508 | Transporting, Storing, Fabricating & Erecting in position and testing/ examining bolted and/ or welded Structural Steel Works at all locations and levels in HANGER SCAFFOLDING below piperack, comprising of hangar channels, fabricated pen wen ladder beams, steel planks bent to shape and size and any other sections, if required, all as per sketches/ specifications and load tested for statisfactory performance, including cutting to required size, straightening/ bending if required, edge preparation, cleaning, preheating, bolting/ welding of joints (including sealing the joints of box sections with continuous welding and plugging any open ends & holes of box sections), finishing edges by grinding, fixing in line and level with temporary staging & bracing and removal of the same after erection, etc. all complete as specified and directed. All items shall be removed & carried back by Contractor as per instructions of Engineer-in-Charge after completion of works. | S023.01.01 | 500 | Sq M |
509 | 509 | Providing and fixing double scaffolding system of any height made with 40 mm dia MS tube 1.5 m centre to centre, horizontal & vertical tubes joining with MS tubes, MS tube challies, MS clamps and MS staircase system in the scaffolding for working platform/ staircase etc., and maintaining it in a serviceable condition for the required duration as approved and removing it thereafter. The scaffolding system shall be stiffened with bracings, runners, connection with the building etc., wherever required for inspection of work at required locations with essential safety features for the workmen etc., all complete as per directions and approval of Engineer-incharge. (Height shall be measured from Floor/ platform from where scaffolding is erected) including providing Aluminium ladders for safe acess of workers. | S023.01.03 | 1000 | Cu M |
510 | 510 | GENERAL CIVIL | GC | ||
511 | 511 | U/G AND A/G G.I. PIPELINE SYSTEM - WATER SERVICES | C012.00.00 | ||
512 | 512 | Laying above ground mild steel galvanised pipes conforming to IS:1239 (heavy grade) and fittings conforming to IS:1239/ASTM A 105 (GALVANISED) and as per piping materials specification Class including supply of teflon tapes, white lead, etc. cutting the pipes to required lengths, making threads, including laying of pipes on sleeper, walls, including erecting piping on columns, etc. for pump station, overhead tanks, etc. including joining the pipes and fittings with threaded connections, hydrostatic testing of the piping including fixing of necessary fittings etc & pipe supports. complete as per specifications, drawings and instructions of Engineer-in-Charge. For following Nom. Size in mm and piping class. | C012.03.00 | ||
513 | 513 | Nom. Dia 150 mm , Pipe class J2A | C012.03.01V21 | 30 | M |
514 | 514 | MISC. CIVIL AND STRUCTURAL WORKS FOR U/G PIPING | C025.00.00 | ||
515 | 515 | Fabrication and erection in position, funnels, clean outs, plugs, flame arrester in vent pipe etc. including the cost of cutting, bolting/welding, etc. complete as per drawings, specifications and direction of Engineer-in-Charge. | C025.46.00 | 500 | KG |
516 | 516 | UNDERGROUND CI PIPING SYSTEM | C026.00.00 | ||
517 | 517 | Laying to proper grade and alignment, cast iron double flanged spun pipes of approved make conforming to IS:1537 A/G ground on sleeper, pipe supports with all necessary specials such as bends, tees, reducers, flanges, tail piece, plugs etc. jointing with rubber gaskets and hexagonal bolts for pump station and at any other place as directed including cutting the pipes to required length, if necessary, grouting pipe body to masonry / concrete wall in cement mortar 1:2 (1 cement : 2 sand), watering, curing, hydrostatic testing for the complete pipe section, draining the water and cleaning the pipe line after testing etc. complete as per drawings, specifications and direction of Engineer-in-Charge.(All material shall be supplied by contractor) For following Pipe size and Class. | C026.06.00 | ||
518 | 518 | Nominal Dia 75 mm , Piping Material Class CI | C026.06.01V13 | 10 | M |
519 | 519 | Nominal Dia 100 mm , Piping Material Class CI | C026.06.01V14 | 250 | M |
520 | 520 | Transportation of all kind of valves (including special and motor operated valves) from owner's storage point to contractor's store/ work site and installation of valves for all rating including assembly of valve accessories, if any, fixing of gaskets, bolts/ nuts etc. complete as per specifications drawings and direction of Engineer-incharge including returning all unused/ surplus material to owner's storage point (valves along with accessories shall be supplied by owner as free issue material). | C163.00.00 | ||
521 | 521 | Flanged/ Wafer Valves | C163.01.00 | ||
522 | 522 | Nominal Dia 3 INCH | C163.01.01V12 | 18 | NOS |
523 | 523 | Installation of valve assembly consisting of valve, 2 no. flanges, 2 no. gaskets and 2 sets of nuts & bolts per valve assembly in position including fixing of nuts, bolts, gaskets, washers etc. complete as per drawings, specifications and directions of Engineer-in-Charge. | C189.00.00 | ||
524 | 524 | Gate valve assembly for following nominal sizes and piping material class | C189.01.00 | ||
525 | 525 | Dia 6 Inch , Piping Material Class J2A | C189.01.01V60 | 4 | EACH |
526 | 526 | Dia 4 Inch , Piping Material Class CI | C189.01.02V45 | 20 | EACH |
527 | 527 | Check valve assembly for following nominal sizes and piping material class | C189.02.00 | ||
528 | 528 | Dia 6 Inch , Piping Material Class J2A | C189.02.01V14 | 2 | EACH |
529 | 529 | Dia 4 Inch , Piping Material Class CI | C189.02.02V19 | 10 | EACH |
530 | 530 | PIPING (ABOVE GROUND): Transportation of all piping items from owner's storage point to work site/workshop, fabrication including cutting, edge preparation (including grinding the edges of pipe, fittings, flanges etc. to match with the mating edges of uneven/different thickness wherever required), fitup, bending, preheating wherever required, welding, threading, and laying of pipes of all type and thickness over pipe sleepers, overhead on racks and at all elevations, connecting with equipment nozzles, strainers, orifice assemblies, tapping for pressure gauges etc., providing reinforcing pads as per piping material specification, fixing of gaskets, bolts, nuts including application of torque wherever required and all other inline instruments and fitting like elbows, reducers, tees, vents, drains, SW valves upto 1.5 NB alignment, cleaning & flushing by water/compressed air, hydrostatic, pneumatic, vacuum, spark testing and any other type of testing as specified, draining, drying by compressed air completing all such works in all respects as per drawings, specifications and instruction of Engineer-in-charge. (Pipes and fittings shall be supplied by owner as free issue material). | C196.00.00 | ||
531 | 531 | For Water System (Pressure Piping) For CS Piping (Non IBR), Thickness <=10 mm, Fabrication, For following Nominal Sizes | C196.01.00 | ||
532 | 532 | Dia upto 1.5" | C196.01.01 | 10 | INCH DIA |
533 | 533 | Dia 2" - 6" | C196.01.02 | 500 | INCH DIA |
534 | 534 | For Water System (Pressure Piping) For CS Piping (Non IBR), Thickness <=10 mm, Erection for following Nominal Sizes | C196.02.00 | ||
535 | 535 | Dia upto 1.5" | C196.02.01 | 10 | INCH M |
536 | 536 | Dia 2" - 6" | C196.02.02 | 500 | INCH M |
537 | 537 | NOTE:-\nTHE ABOVE RATE SHALL BE INCLUSIVE OF ALL TAXES & DUTIES, ROYALTIES, CESS, ENVIORMENTAL & POLLUTION, FITNESS & SAFETY CLEARANCE CHARGES (IF ANY), OR ANY OTHER INCIDENTAL CHARGES ETC BUT EXCLUDING GST. |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail