Supply , Installation And Commissioning Of Steam Distillation Units- 08 Nos ( 2 . 5 Qtl , 5 Qtl , 10 Qtl , 15 Qtl And 20 Qtl Capacities ) Supply , Installation And Commissioning Of Steam Distillation Units- 08 Nos ( 2 . 5 Qtl , 5 Qtl , 10 Qtl ,
Tender Overview
Project Description
Supply , Installation And Commissioning Of Steam Distillation Units- 08 Nos ( 2 . 5 Qtl , 5 Qtl , 10 Qtl , 15 Qtl And 20 Qtl Capacities ) Supply , Installation And Commissioning Of Steam Distillation Units- 08 Nos ( 2 . 5 Qtl , 5 Qtl , 10 Qtl , 15 Qtl And 20 Qtl Capacities ) , Supply , Installation & Commissioning Of Steam Distillation Unit With Cohobation System For Flowers 2 . 5 Qtl As Per Specifications Mentioned In Annexure 1 ( A ) Including Cost Of Essential Spares & Consumables Required For Trouble Free Operation During Warranty Period , Cost Of Essential Spares & Consumables Required For Trouble Free Operation After Warranty Period , Supply , Installation & Commissioning Of Steam Distillation Unit , Multipurpose Design With Multiple Separators For Spices , Roots/Rhizome Etc 2 . 5 Qtl As Per Specifications Mentioned In Annexure 1 ( B ) Including Cost Of Essential Spares & Consumables Required For Trouble Free Operation During Warranty Period , Cost Of Essential Spares & Consumables Required For Trouble Free Operation After Warranty Period , Supply , Installation & Commissioning Of Steam Distillation Unit , Multipurpose Design With Multiple Separators For Spices , Roots/Rhizome Etc 5 Qtl As Per Specifications Mentioned In Annexure 1 ( C ) Including Cost Of Essential Spares & Consumables Required For Trouble Free Operation During Warranty Period , Cost Of Essential Spares & Consumables Required For Trouble Free Operation After Warranty Period , Supply , Installation & Commissioning Of Steam Distillation Unit With Cohobation System For Grasses 10 Qtl As Per Specifications Mentioned In Annexure 1 ( D ) Including Cost Of Essential Spares & Consumables Required For Trouble Free Operation During Warranty Period , Cost Of Essential Spares & Consumables Required For Trouble Free Operation After Warranty Period , Supply , Installation & Commissioning Of Steam Distillation Unit For Grasses 10 Qtl As Per Specifications Mentioned In Annexure 1 ( E ) Including Cost Of Essential Spares & Consumables Required For Trouble Free Operation During Warranty Period , Cost Of Essential Spares & Consumables Required For Trouble Free Operation After Warranty Period , Supply , Installation & Commissioning Of Steam Distillation Unit For Grasses 15 Qtl As Per Specifications Mentioned In Annexure 1 ( F ) Including Cost Of Essential Spares & Consumables Required For Trouble Free Operation During Warranty Period , Cost Of Essential Spares & Consumables Required For Trouble Free Operation After Warranty Period , Supply , Installation & Commissioning Of Steam Distillation Unit For Grasses 20 Qtl As Per Specifications Mentioned In Annexure 1 ( G ) Including Cost Of Essential Spares & Consumables Required For Trouble Free Operation During Warranty Period , Cost Of Essential Spares & Consumables Required For Trouble Free Operation After Warranty Period
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 27-Jul-2021 | Date extended | Date | 24-Aug-2021 |
BOQ
| Name of Work: Supply, Installation & Commissioning of Steam Distillation Units (2.5 Qtl, 5 Qtl, 10 Qtl, 15 Qtl and 20 Qtl Capacities) along with all Pipeline Connection, Pipe Fittings & Structure Stand etc complete-Total 08 Nos. | |||||
|---|---|---|---|---|---|
| Sl.No. | Description | Item Code / Make | Quantity | Units | |
| 1 | 1 | Supply, Installation & Commissioning of Steam Distillation Unit with Cohobation System for Flowers 2.5 Qtl as per specifications mentioned in Annexure 1 (A) including Cost of Essential Spares & Consumables required for trouble free operation during warranty period | item1 | 1 | No, |
| 2 | 1.1 | Cost of Essential Spares & Consumables required for trouble free operation after warranty period | item2 | 1 | No, |
| 3 | 2 | Supply , Installation & Commissioning of Steam Distillation Unit , Multipurpose Design with Multiple separators for Spices, Roots/Rhizome etc 2.5 Qtl as per specifications mentioned in Annexure 1 (B) including Cost of Essential Spares & Consumables required for trouble free operation during warranty period | item3 | 1 | No, |
| 4 | 2.1 | Cost of Essential Spares & Consumables required for trouble free operation after warranty period | item4 | 1 | No, |
| 5 | 3 | Supply , Installation & Commissioning of Steam Distillation Unit , Multipurpose Design with Multiple separators for Spices, Roots/Rhizome etc 5 Qtl as per specifications mentioned in Annexure 1 (C) including Cost of Essential Spares & Consumables required for trouble free operation during warranty period | item5 | 2 | No, |
| 6 | 3.1 | Cost of Essential Spares & Consumables required for trouble free operation after warranty period | item6 | 1 | No, |
| 7 | 4 | Supply, Installation & Commissioning of Steam Distillation Unit with Cohobation System for Grasses 10 Qtl as per specifications mentioned in Annexure 1 (D) including Cost of Essential Spares & Consumables required for trouble free operation during warranty period | item7 | 1 | No, |
| 8 | 4.1 | Cost of Essential Spares & Consumables required for trouble free operation after warranty period | item8 | 1 | No, |
| 9 | 5 | Supply , Installation & Commissioning of Steam Distillation Unit for Grasses 10 Qtl as per specifications mentioned in Annexure 1 (E) including Cost of Essential Spares & Consumables required for trouble free operation during warranty period | item9 | 1 | No, |
| 10 | 5.1 | Cost of Essential Spares & Consumables required for trouble free operation after warranty period | item10 | 1 | No, |
| 11 | 6 | Supply , Installation & Commissioning of Steam Distillation Unit for Grasses 15 Qtl as per specifications mentioned in Annexure 1 (F) including Cost of Essential Spares & Consumables required for trouble free operation during warranty period | item11 | 1 | No, |
| 12 | 6.1 | Cost of Essential Spares & Consumables required for trouble free operation after warranty period | item12 | 1 | No, |
| 13 | 7 | Supply , Installation & Commissioning of Steam Distillation Unit for Grasses 20 Qtl as per specifications mentioned in Annexure 1 (G) including Cost of Essential Spares & Consumables required for trouble free operation during warranty period | item13 | 1 | No, |
| 14 | 7.1 | Cost of Essential Spares & Consumables required for trouble free operation after warranty period | item14 | 1 | No, |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender