| 1 | 1 | Excavation in soil mixed with moorum/shingle, kankar requiring the use of special tools & plant such as pick axes sabbals etc. foundation in ordinary Soil (Loam, Cley or sand) including, lift up to 1.50 M and lead up to 30 M and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge up to a distance of 30 M form the foundation trenches. Including royalty. | BI01010001010000000000000515BI0100001112 | 30.38 | cum |
|---|
| 2 | 2 | Cartage of silt, sludge kankar and other disposable organic material etc. all complete with labor T&P including cartage of 8 km. | BI01010001010000000000000515BI0100001113 | 30.38 | cum |
|---|
| 3 | 3 | P/L spreading and compacting 45-63 mm stone aggregates of specific sixes to water bound macadam specification including spreading in uniform thickness and packing, rolling with 3 wheeled steel/vibratory roller 8-10 tones in stage to proper grade and camber applying and brooming requisite type of screening/binding materials to fill up the interstices of coarse aggregate, watering and compacting to the required density. | BI01010001010000000000000515BI0100001114 | 15.19 | cum |
|---|
| 4 | 4 | P/L GSB with graded stone ballast with moram with stone grit size, stone ballast with hand ramming watering including all material labor T&P etc. all complete. | BI01010001010000000000000515BI0100001115 | 10.13 | cum |
|---|
| 5 | 5 | Providing and applying primer coat with bitumen emulsion (bulk) on prepared surface of granular base including clearing of road surface and spraying primer at the rate of 0.75 kg/sqm using mechanical means. | BI01010001010000000000000515BI0100001116 | 101.25 | sqm |
|---|
| 6 | 6 | Providing and applying tack coat with bitumen BG-10 using pressure distributor at the of 0.20 kg per sqm on the prepared bituminous/granular surface cleaned with mechanical broom. | BI01010001010000000000000515BI0100001117 | 757.5 | sqm |
|---|
| 7 | 7 | Providing and laying dense graded bituminous macadam with 100-120 TPH batch type HMP producing an average output of 75 tonne per hour using crushed aggregates of specified grading, premixed with bituminous bider @ 3.00 to 3.50 percent by weight of total mix and filler, transporting the hot mix to work site laying with hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause 507 complete in all respects. | BI01010001010000000000000515BI0100001118 | 12.38 | mt |
|---|
| 8 | 8 | Providing and laying semi-dense bituminous concrete with 100-120 TPH batch type HMP producing an average output of 75 tonne per hour using crushed aggregates of specified grading, premixed with bituminous bider @ 4.50 to 5.00 percent by weight of total mix and filler, transporting the hot mix to work site laying with hydrostatic paver finisher with sensor control to the required grade level and alignment, rolling with smooth wheeled vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause 508 complete in all respects. | BI01010001010000000000000515BI0100001119 | 60.38 | mt |
|---|
| 9 | 9 | Providing and laying hot applied thermo plastic compound 2.5 mm thick including refletrorising glass beads @250 gm/sqm. Area, thickness of 2.5 mm is exclusive of surface applied glass beads as per I.R.C. 35. The finish surface to be level, uniform and free from steaks and holes. Composition of thermo plastic material shall be as per table 800–3 of clause 803 of MORTH including cost of work as direction E/IC. | BI01010001010000000000000515BI0100001120 | 28 | sqm |
|---|
| 10 | 10 | Supply and fixing of black granite stone board and approved standard matter with brick work, plaster & paint etc. all complete. | BI01010001010000000000000515BI0100001121 | 1 | Nos |
|---|
| 11 | 11 | Sub Total (A) | BI01010001010000000000000515BI0100001157 | 1 | Rs |
|---|
| 12 | 12 | Add 12% G.S.T. of Sub Total (A) | BI01010001010000000000000515BI0100001160 | 1 | Rs |
|---|
| 13 | 13 | Sub Total (B) | BI01010001010000000000000515BI0100001161 | 1 | Rs |
|---|
| 14 | 14 | Add / Deduction For Estimate Figure Amount Match | BI01010001010000000000000515BI0100001162 | 1 | Rs |
|---|
| 15 | 15 | Grand Total | BI01010001010000000000000515BI0100001163 | 1 | Rs |
|---|