| 1 | EXCAVATION FOR PIPE TRENCHES IN EARTH SOILS OF ALL TYPES SAND GRAVEL,ETC.Non-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |
| 2 | EXCAVATION FOR PIPE TRENCHES IN HARD MURUM BOULDER ROAD INCLUDING REMOVING THE EXCAVATED MATERIAL.Non-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |
| 3 | EXCAVATION FOR PIPE TRENCHES IN SOFT ROCK, OLD CEMENT AND LIMW MASONRY FOR FOUNDATION AS INCLUDING REMOVING THE EXCAVATED MATERIAL.Non-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |
| 4 | EXCAVATION FOR FOUNDATION /PIPE TRENCHES IN HARD ROCK AND CONCRETE ROAD BY CHESELLING ,WEDGING ,LINE DRILLING BY MECHANICAL BY MEANS OR BY ALL MEANS OTHER THAN BLASTNG INCLUDING TRMMING AND LEVELLING THE BED,Non-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |
| 5 | FILLING IN PLINTH AND FLOOR MURUM BEDDING IN TRENCHES EITH APPROVED MURUM FROM EXCAVATED MATERIAL FROM EXCAVATED MATERIAL FROM FOUNDATION 15CM S TO 20CM S LAYERSNon-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |
| 6 | PROVIDING ,SUPPLYING ,LOWERING,LAYING AND JOINTING IN STANDARD LENGHTS ISI MARK RIGID UNSPLATICISED PVC PIPES SUITABLE FOR PORTABLE WATER WITH SOLVENT CEMENT JOINT ,ETC.a)PVC 90MM DIA 4KG/CM2Non-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |
| 7 | PROVIDING ,SUPPLYING ,LOWERING,LAYING AND JOINTING IN STANDARD LENGHTS ISI MARK RIGID UNSPLATICISED PVC PIPES SUITABLE FOR PORTABLE WATER WITH SOLVENT CEMENT JOINT ,ETC.B)PVC 75MM DIA 4KG/CM2Non-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |
| 8 | PROVIDING DOUBLE FLANGE SLUICE VALVE CONFIRMING FOR IS 2906/14846 INCLUDING ORN GEAR ARRANGEMENT (CENTRAL/LOCAL)RAILWAY FREIGHT INSPECTION CHARGES UNLOADING FROM RAILWAY WAGON,A)80MM DIA SLUICE VALVE PN-1Non-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |
| 9 | PROVIDING DOUBLE FLANGE SLUICE VALVE CONFIRMING FOR IS 2906/14846 INCLUDING ORN GEAR ARRANGEMENT (CENTRAL/LOCAL)RAILWAY FREIGHT INSPECTION CHARGES UNLOADING FROM RAILWAY WAGON,A)65MM DIA SLUICE VALVE PN-2Non-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |
| 10 | REFILLING THE TRENCHES WITH AVAILABLE EXCAVATED STUFF WITH SOFT MATERIAL FIRST OVER PIPELINE AND THEN HARD MATERIAL IN 15 CM. LAYER WITH ALL LEADS AND LIFTS INCLUDING CONSOLIDATION SURCJARGE ETC.Non-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |
| 11 | ADD G.S.T. 12%Non-Dsr ItemAdditional Specifications : The work shall be carried out as per the instructions of Engineer in-charge. |