A Mtc Of W S And Sewerage Scheme In Sec 6 Dharuhera Construction Of Toilet Block On Tubewells No 6 Dharuhera And Raising Of Boundary Wall
Tender Value
Ref. Documents
Estimated cost
Bid Submission
16 Jun 2021
0 days left
EMD
4000
Bank guarantee accepted
Document Fee
295
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Dharuhera → Haryana
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Annual Maintenance Of W S And Sewerage Scheme In Sec 6 Dharuhera Construction Of Toilet Block On Tubewells No 6 Dharuhera And Raising Of Boundary Wall
BOQ
| Name of work :- A/Mtc. of W/S & Sewerage Scheme in Sec-6 Dharuhera. “Construction of toilet block on tubewells No. 6 Dharuhera & raising of boundary wall and all other works contingent thereto”. A/C Rs. 2.00 Lacs | |||||
|---|---|---|---|---|---|
| Sl.No. | Item Description | Item Code / Make | Quantity | Units | |
| 1 | 1 | App.Item\nEarth work in embankment including excavation of all kind of soil, rock, carriage including loading and unloading and laying earth as per specification for compaction of 25 cm layer including dressing the bank and side slops of levels and excluding cost of rolling and watering complete rate to be quoted by the contractor shall be taken into account all allowances for labour hardness and wetness total lead and lift of earth and to the entire satisfaction of the Engineer-in-charge confirming to PWD specification as mended till date of payment of \nsupply of earth filing. \n | BI01010001010000000000000515BI0100001113 | 155 | per cum |
| 2 | 2 | 6.6\nEarth work in excavation in foundation trenches etc. in all kind of soil, not exceeding 2 Mt depth including dressing of bottom and sides of trenches stacking of excavated of soil clear from the edge of excavation and subsequent filling around masonry in 15 cm layers with compaction including disposal of all surplus soil as directed within a lead of 30 Mtr\n | BI01010001010000000000000515BI0100001114 | 25 | per cum |
| 3 | 3 | 10.28\nCement concrete 1:8:16 with stone aggregate 40mm nominal size in foundation and plinth. | BI01010001010000000000000515BI0100001115 | 4 | per cum |
| 4 | 4 | 10.29\nCement concrete 1:8:16 with stone aggregate 20mm nominal size in foundation and plinth. (under flooring) | BI01010001010000000000000515BI0100001116 | 10 | per cum |
| 5 | 5 | 11.23\nFirst class brick work laid in cement stone dust (from crusher) mortar 1:5 in foundation and plinth | BI01010001010000000000000515BI0100001117 | 18 | per cum |
| 6 | 6 | 11.28\nFirst class brickwork laid in cement, stone dust (from crusher) mortar 1:5 in first storey upto 4 Mt above plinth levels. | BI01010001010000000000000515BI0100001118 | 5 | per cum |
| 7 | 7 | 10.114\nDamp proof course 40 mm thick of cement, concrete 1:2:4 with stone aggregate 20mm nominal size with 2 coats of bitumen 20/30 penetration at 1.65 Kg. Per Sqm.. laid hot and sanded. | BI01010001010000000000000515BI0100001119 | 10 | per sqm |
| 8 | 8 | 10.41\nCement conc. 1:2:4 with stone gg. 20mm nominal size in foundation and plinth. | BI01010001010000000000000515BI0100001120 | 7 | per sqm |
| 9 | 9 | 15.3 + 15.75\n12mm thick cement plater & cement rendering on plaster 1mm thick. | BI01010001010000000000000515BI0100001121 | 77 | per sqm |
| 10 | 10 | 11.53\n11.43 cm thick brick wall laid in cement stone dust (from crusher) mortar 1 : 4 in super structure | BI01010001010000000000000515BI0100001122 | 60 | per sqm |
| 11 | 11 | 10.82 + 10.95 a)\nCement concrete 1:2:4 with stone aggregate 20mm nominal size for reinforced concrete work in slabs with inclination not exceeding 25 degrees with horizontal excluding steel reinforcement, but including centering and shuttering laid in position complete in all respects.\na) Extra over item no. 10.79 to 10.94, if 1:1.5:3 mix is used, instead of 1:2:4.\n | BI01010001010000000000000515BI0100001123 | 1.2 | per cum |
| 12 | 12 | 18.22\nFe-500 TMT steel bars of the companys TISCO, SAIL, RINL or TISCO bars for RCC works where not included in the complete rate of RCC including beinding, binding and placing in position. | BI01010001010000000000000515BI0100001124 | 1.2 | per qtl |
AI Tender Summary
Tender Timeline
Jun 08, 2021
11:30 IST
Tender Published
Tender notice published.
CompletedJun 16, 2021
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedJun 17, 2021
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender