Annual Rate Contract For Mechanical Maintenance Item Rate Jobs At Ompl-I Safety Helmet 2 Safety Shoe 3 Safety Goggles 4 Rain Shoe 5 Rain Coat 6 Boiler Suit
Tender Value
Ref. Documents
Estimated cost
Bid Submission
01 Jun 2021
0 days left
EMD
Ref. Documents
Bank guarantee accepted
Document Fee
Ref. Documents
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
OMPL, Mangalore → Karnataka
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Annual Rate Contract For Mechanical Maintenance Item Rate Jobs At Ompl-I Safety Helmet 2 Safety Shoe 3 Safety Goggles 4 Rain Shoe 5 Rain Coat 6 Boiler Suit
BOQ
| Sl. No. | Item Description |
| 1 | Items List : |
| 2 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 3 | Fixing the coupling spacer , tightening the bolts & Alignment rectification |
| 4 | Loosening /Tightening the Motor foundation bolts . |
| 5 | Checking Seal flushing lines,lube oil ,Motor Bolt,casing bolt ,coupling bolts |
| 6 | De-coupling,pump seal flushing lines removal,pump opening,casing gasket replacement, pump box up ,Alignment & coupling |
| 7 | consist of removing the connecting rod pin,remove the connecting rod.Check the bearing and replace elements if necessary |
| 8 | De-coupling,pump seal flushing lines removal,pump opening,casing gasket replacement,seal opening,bearing replacement, pump box up ,Alignment & coupling |
| 9 | Decoupling and coupling including alignment,DBSE Checking ,Coupling Inspection,Motorfoundation bolts tightening , |
| 10 | Seal oil make up |
| 11 | Over Hauling of the Pump includes,bearing replacement ,Seal Replacement,coupling,casing gasket replacement,& all the pump accessories ,Seal lines opening and boxup Maint & including hot bolting if required,Decoupling ,coupling and Alignment of Pump |
| 12 | Seal cooler tubes dechocking includes opening and boxup of seal lines,blinding and deblinding of lines required for seal cooler cleaning, seal cooler opening and Boxing up of the seal lines and Seal cooler,Hose connection for Seal cooler cleaning |
| 13 | Loosening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 14 | Fixing the coupling spacer , tightening the bolts & Alignment rectification |
| 15 | Loosening /Tightening the Motor foundation bolts |
| 16 | Checking Seal flushing lines,lube oil ,Motor Bolt,casing bolt ,coupling bolts |
| 17 | De-coupling,pump seal flushing lines removal,pump opening,casing gasket replacement, pump box up ,Alignment & coupling |
| 18 | De-coupling,pump seal flushing lines removal,pump opening,casing gasket replacement,Seal Replacement pump box up ,Coupling,Alignment |
| 19 | De-coupling,pump seal flushing lines removal,pump opening,casing gasket replacement,seal opening,bearing replacement, pump box up ,Alignment & coupling |
| 20 | Decoupling and coupling including alignment,DBSE Checking ,Coupling Inspection,Motorfoundation bolts tightening , |
| 21 | Seal oil make up |
| 22 | Over Hauling of the Pump includes,bearing replacement ,Seal Replacement,coupling,casing gasket replacement,& all the pump accessories ,Seal lines opening and boxup Maint & including hot bolting if required,Decoupling ,coupling and Alignment of Pump |
| 23 | Seal cooler tubes dechocking includes opening and boxup of seal lines,blinding and deblinding of lines required for seal cooler cleaning, seal cooler opening and Boxing up of the seal lines and Seal cooler,Hose connection for Seal cooler cleaning |
| 24 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 25 | Fixing the coupling spacer , tightening the bolts & Alignment rectification |
| 26 | Checking Seal flushing lines,lube oil ,Motor Bolt,casing bolt ,coupling bolts Etc |
| 27 | Seal Locking,NDE bearing replacement,Alignment checking |
| 28 | Seal lines removal and boxup,Seal Locking,NDE bearing removal,seal replacement,box up,Alignment |
| 29 | De-coupling,seal lock,bearing removal, box up,coupling & Alignment |
| 30 | Seal lines removal and boxup,Seal Locking,DE bearing removal,seal replacement,box up,Alignment |
| 31 | Loosening /Tightening the Motor foundation bolts .coupling |
| 32 | Seal cooler tubes dechocking includes opening and boxup of seal lines,blinding and deblinding of lines required for seal cooler cleaning, seal cooler opening and Boxing up of the seal lines and Seal cooler,Hose connection for Seal cooler cleaning |
| 33 | Over Hauling of the Pump includes,bearing replacement ,Seal Replacement,coupling,casing gasket replacement,& all the pump accessories ,Seal lines opening and boxup Maint & including hot bolting if required,Decoupling ,coupling and Alignment of Pump& Hot Bolting if required |
| 34 | Loosening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 35 | Fixing the coupling spacer & tightening the bolts |
| 36 | Decoupling and coupling including alignment,DBSE Checking ,Coupling Inspection,Motorfoundation bolts tightening , |
| 37 | Checking Seal flushing lines,lube oil ,Motor Bolt,casing bolt ,coupling bolts Etc |
| 38 | Seal Locking,NDE bearing replacement,Alignment checking |
| 39 | Seal lines removal and boxup,Seal Locking,NDE bearing removal,seal replacement,box up,Alignment |
| 40 | De-coupling,seal lock,bearing removal, box up,coupling & Alignment checking |
| 41 | Seal lines removal and boxup,Seal Locking,DE bearing removal,seal replacement,box up,Alignment |
| 42 | Loosening /Tightening the Motor foundation bolts .couplb |
| 43 | Seal cooler tubes dechocking includes opening and boxup of seal lines,blinding and deblinding of lines required for seal cooler cleaning, seal cooler opening and Boxing up of the seal lines and Seal cooler,Hose connection for Seal cooler cleaning |
| 44 | Over Hauling of the Pump includes,bearing replacement ,Seal Replacement,coupling,casing gasket replacement,& all the pump accessories ,Seal lines opening and boxup Maint & including hot bolting if required,Decoupling ,coupling and Alignment of Pump& Hot Bolting if required |
| 45 | Fixing the coupling spacer & tightening the bolts |
| 46 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 47 | Opening Suction & discharge valves,servicing/Replacement,box up |
| 48 | Opening of crank case.Bearing overhaul ,inspection.Check bearing clearances |
| 49 | Remove and replace gland |
| 50 | Open the liquid end,remove plunger ,clean,Check dimensions,replace plunger if necessary |
| 51 | Remove liquid end remove pluger mechanism and replace parts which ever are damaged or worn out.clean the internals and the elements of the equipment |
| 52 | Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 53 | Remove the pulsation dampner.Check internals and replace if necessary |
| 54 | Includes lube oil replacement.Attending on line leaks. |
| 55 | Remove coupling,remove motor,Make arrangements to hold the pump either via crane or mono rail,remove the pump.Remove impeller, all connected shafts(spline) ,remove and clean strainers.Replace parts if necessary. And pump boxup |
| 56 | Top up lube oil or replace totally .Replace gland packing if necessary.Tighetening or arresting leaks |
| 57 | Remove coupling,remove motor,Make arrangements to hold the pump either via crane or mono rail,remove the pump.Replace servie pump.Fix the bearing.Fix motor.Align and couple |
| 58 | Remove motor,coupling.Remove bearing housing replace bearings.Fix the bearing housing back .Fix motor and align. |
| 59 | Remove motor,coupling.Bearings.Replace seal,take run out readings check for stuffing box squareness.Replace spares or complete seal depending on the condition.Fix bearings.Fix motor.Align and fix coupling |
| 60 | Measure distance between shaft ends(DBSE)-ensure the DBSE is within limits.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges For coupling:once the equipment is aligned fix thecoupling by bolts and shim pack. |
| 61 | Motor must be deenergised.Remove coupling bolt,remove shims and measure DBSE |
| 62 | Ensure equipment is on by pass filter.Remove the clogged filter.Dip in a solvent or Hydrocrabon or as advised by Engineer In charge.Clean the filter element and box up |
| 63 | Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 64 | Gear Alignment |
| 65 | Includes lube oil replacement.Attending on line leaks.or any other specifically defined by EIC |
| 66 | once the equipment is aligned fix thecoupling by bolts and shim pack. |
| 67 | Motor must be deenergised.Remove coupling bolt,remove shims and measure DBSE |
| 68 | Job includes removal of old belt.Alignment checks ,ensure distance between the belt pulleys are appropriate and fix belt accordingly |
| 69 | Remove the lube oil cooler .Clean the internals,remove scaling and test the cooler.Put it back into service |
| 70 | Open the gear box.Flush out lube oil andpour fresh lubricant as per specification |
| 71 | Open the bearing house replace bearing as per specification and provide lubrication as specified |
| 72 | Bellows are flanged to the inlet or outlet duct.Remove the bellows and replace the bellows as site location |
| 73 | Balancingof machine,includes running of machine at site and adding or remove weight either by providing fasteners ,or welding weights or any other suitable method at site |
| 74 | Job includes removal of bearing and replacing of seal or gland arrangement |
| 75 | Job includes decoupling,removing the casing ,remove impeller,remove seal/glandand bearing. |
| 76 | Ensure equipment is on by pass filter.Remove the clogged filter.Dip in a solvent or Hydrocrabon or as advised by Engineer In charge.Clean the filter element and box up |
| 77 | Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 78 | Gear Alignment |
| 79 | Includes lube oil replacement.Attending on line leaks.or any other specifically defined by EIC |
| 80 | once the equipment is aligned fix thecoupling by bolts and shim pack. |
| 81 | Motor must be deenergised.Remove coupling bolt,remove shims and measure DBSE |
| 82 | Job includes removal of old belt.Alignment checks ,ensure distance between the belt pulleys are appropriate and fix belt accordingly |
| 83 | Remove the lube oil cooler .Clean the internals,remove scaling and test the cooler.Put it back into service |
| 84 | Open the gear box.Flush out lube oil andpour fresh lubricant as per specification |
| 85 | Open the bearing house replace bearing as per specification and provide lubrication as specified |
| 86 | Bellows are flanged to the inlet or outlet duct.Remove the bellows and replace the bellows as site location |
| 87 | Job includes removal of bearing and replacing of seal or gland arrangement |
| 88 | Job includes decoupling,removing the casing ,remove impeller,remove seal/glandand bearing. |
| 89 | Job includes removal of unloader,dismantling the unloader.Removal and replacement of unloader elements if necessary |
| 90 | Job includes cleaning of filters if required by solvent/hydrocarbon or air.Replacement of strainer elements/filter elemets |
| 91 | consist of removing the connecting rod pin,remove the connecting rod.Check the bearing and replace elements if necessary |
| 92 | This is inclusive of removing the stuffing box flange ,removal of rod packing cup,remove the rod packing.replace rod packing if necessary |
| 93 | Include Lubrication,tightening f flanges,checking oil levels,replace oil,arresting leaks etc |
| 94 | Includes removal of valve ,cleaning the valve plates servicing the plates ,replacing broken worn out parts |
| 95 | includes replacement of piston ring,rider ring and replacement with new items.Includes dismantling of cylinder head,removal of pistonnut,piston,removal of piston ring and rider ring.Job includes fixing the parts back as per assembly procedures,includesn coupling and decoupling of the compressor |
| 96 | Includes ,decoupling,removal of cylinder head,piston and its accessories,overhauling compressor valves,cross head maintenance,crankshaft maintenance,checking lubricator ,cooling systems,Compressor Auxillaries,Important compressor overhaul checks like web deflection,rod drop checks,cylinder and piston clearances and other important check,Assembling the compressor,alignment and coupling of the compressor |
| 97 | Includes decoupling,freeing connecting rod from cross head,initial inspection,removal of existing bearing,replace bearing ,assemble back elements |
| 98 | Job includes remove the flanges of the equipment containing the filters.Remove the filters clean the filters or replace the filters if required |
| 99 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 100 | Fixing the coupling spacer , tightening the bolts & Alignment rectification |
| 101 | Job includes checking the shims,cheking small end bearing,bearing clearances etc |
| 102 | consisting of checking the pump,checking feeders,replacing spares if required |
| 103 | Consisiting of servicing the pump.replacing damaged parts. |
| 104 | Consisiting of servicing the pump.replacing damaged parts. |
| 105 | Job includes remove the flanges of the equipment containing the filters.Remove the filters clean the filters or replace the filters if required |
| 106 | Open the gear box.Flush out lube oil andpour fresh lubricant as per specification |
| 107 | Job includes draining of lube oil ,cleaning and refilling with fresh lube oil |
| 108 | Remove the lube oil cooler .Clean the internals,remove scaling and test the cooler.Put it back into service |
| 109 | Remove the cooler .Clean the internals,remove scaling and test the cooler.Put it back into service |
| 110 | Job includes removal of view glass,cleaning the view glass and fitting the view glass back in position.Job includes replacement of new view glass if required |
| 111 | overhauling of ID/FD fan including coupling & alignment |
| 112 | Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 113 | job includes lube oil change ,topping up lube oil,arresting on line leaks,cleaning, IGV link greasing etc |
| 114 | Job includes decoupling,removal of non drive end bearing,checking dimension,replacing bearing ,alignment and coupling etc |
| 115 | Job includes decoupling,removal of drive end bearing,checking dimension,replacing bearing ,alignment and coupling etc |
| 116 | Job includes,decoupling,removal of foundation bolts,helping riggers to load it into tractor /trailer or truck.Fixing back motor(after service),bolting the motor,alignment,coupling |
| 117 | Job includes remove the flanges of the equipment containing the filter element.Remove the filter element, clean the filter element or replace the filter elementif required |
| 118 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 119 | Job includes adjusting the speed of the turbine,topping up or replenshing oil,Preventive maintenance jobs,overhaul or replacement of coupling |
| 120 | IGV servicing |
| 121 | Job includes general servicing,repair work,freeing the damper /SOB etc |
| 122 | Job includes oil cooler opening, dechoking, cleaning & box up. Auxilary lines cleaning & box up |
| 123 | Replacement of individual suction filter replacement |
| 124 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 125 | once the equipment is aligned fix thecoupling by bolts and shim pack. |
| 126 | Gear Box Service |
| 127 | Remove motor,coupling.Bearings.Replace seal,take run out readings check for stuffing box squareness.Replace spares or complete seal depending on the condition.Fix bearings.Fix motor.Align and fix coupling |
| 128 | Includes lube oil replacement.Attending on line leaks.or any other specifically defined by EIC |
| 129 | Includes decoupling,removal of pump casing,removal of internals like seal bearing impeller,checking shaft run out,checking stuffing box clearance,replacement of pump internals etc |
| 130 | Job includes removal of cooler bundle cleaning,testing of bundle,repair of bundle,etc |
| 131 | Job includes removal of lube oil system or cooling system,doing related repair jobs,ovedrhauling or repair of lube pumps etc |
| 132 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 133 | once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 134 | Job includes decoupling,removal of bearing,setting the timing gear,replacment of timing gear if necessary,fixing the bearing etc,alignment and coupling |
| 135 | Job includes decoupling,removal of bearings,removal of seal or insitu repair if required,replacement of seal ,fixing the bearing,alignment and coupling |
| 136 | Job includes decoupling,removal of bearings,removal of seal or insitu repair if required,replacement of seal ,fixing the bearing,alignment and coupling |
| 137 | Job includes lube top up,lube flushing,lube change over,arresting on line leaks,replacing gaskets of auxillary pipe and fittings |
| 138 | Job includes decoupling,removal of beairng,seals,pump casing,pump internals like impeller,cleaning or replacement of impellers if required,reassembly,alignment and coupling |
| 139 | Job includes decoupling,removal of bearing ,replacement if necessary etc,alignment and coupling |
| 140 | Job includes decoupling,removal of bearing ,replacement if necessary etc,alignment and coupling |
| 141 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 142 | Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 143 | Job includes lube top up,lube flushing,lube change over,arresting on line leaks,replacing gaskets of auxillary pipe and fittings |
| 144 | Remove coupling,remove motor,Make arrangements to hold the pump either via crane or mono rail,remove the pump.Replace service pump.Fix the bearing.Fix motor.Align and couple |
| 145 | Remove motor,coupling.Remove bearing housing replace bearings.Fix the bearing housing back .Fix motor and align. |
| 146 | Job includes decoupling,removal of bearings,removal of seal or insitu repair if required,replacement of seal ,fixing the bearing,alignment and coupling |
| 147 | Includes decoupling,removal of pump casing,removal of internals,replacement of internals,etc |
| 148 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 149 | Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 150 | Job includes lube top up,lube flushing,lube change over,arresting on line leaks,replacing gaskets of auxillary pipe and fittings |
| 151 | Includes decoupling,removal of screw compressor ,removal of internals,replacement of internals,etc |
| 152 | Job includes removal of cooler bundle cleaning,testing of bundle,repair of bundle,etc |
| 153 | Job includes removal of lube oil system or cooling system,doing related repair jobs,ovedrhauling or repair of lube pumps etc |
| 154 | Job includes greasing ofbearing as per PM schedule |
| 155 | Job includes removal of old belt.Alignment checks ,ensure distance between the belt pulleys are appropriate and fix belt accordingly and Greasing of bearing |
| 156 | Remove motor,Belt, pulley.Remove bearing housing replace bearings.Fix the bearing housing back .Fix motor pulley belt and align.Greasing of Bearing |
| 157 | Job includes alignment setting and tigheteniong of all blade of AFCetc |
| 158 | Guard replacement ,repairs |
| 159 | Job includes removal of Allblades of AFC and replaceing/ repairing the blades .Setting up blade angles etc |
| 160 | Job includes removal of pulley tpaer lock bush,removal of pulley,replace or repair pulley and assemble the same |
| 161 | Job involves Belt fixing and Alignment |
| 162 | Job involves Belt removal and Base Bolt Removal |
| 163 | Dismantling of bearing block & refurbishment |
| 164 | Job includes removal of gear box oil seal holder and repair /replace the oil seal |
| 165 | Job includes lube top up,lube flushing,lube change over,arresting on line leaks,replacing gaskets of auxillary pipe and fittings |
| 166 | Job includes removaland replacement of gland or tightening the gland packing |
| 167 | Job includes repair/replacement or preventive maintenance of roller supports |
| 168 | Job includes removal of lancer tube and its fasteneing facility,cleaning,repair or replace of the lancer tube |
| 169 | Job includes removal of poppet valve,cleanign and repair/replace of internals if required |
| 170 | Job includes tightening of chain,cometimes the chain slips of the sprocket,repair of sprocket mechanism ,lubricating the chain etc |
| 171 | Job includes tightening of chain,cometimes the chain slips of the sprocket,replace of sprocket mechanism ,lubricating the chain etc |
| 172 | Includes removal of all the elements of soot blower,repair/replacing parts if required and assembling back the soot blower |
| 173 | Includes freeing the soot blower when stuck during operation |
| 174 | Job includes overhauling of gear boxx including repair /replacement of parts if required |
| 175 | Decoupling of motor |
| 176 | Coupling of motor |
| 177 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 178 | Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 179 | Job includes overhauling of gear boxx including repair /replacement of parts if required |
| 180 | Remove motor,coupling.Remove bearing housing replace bearings.Fix the bearing housing back .Fix motor and align. |
| 181 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 182 | TIghtening coupling bolts,includes the coupling spacer & tighteningthe motor foundation bolts if reqd |
| 183 | Job includes overhauling of gear boxx including repair /replacement of parts if required |
| 184 | Remove motor,coupling.Remove bearing housing replace bearings.Fix the bearing housing back .Fix motor and align. |
| 185 | Job includes flushing of oil and replenshing gear oil |
| 186 | Job includes applying grease mechanically or physically etc |
| 187 | Job includes overhauling of pump and repair/replacing of pump internals |
| 188 | Job includes topping of oil ,replenshing or replacing oil |
| 189 | lip seal replacement, diaphragm replacement, piston assembly servicing/replacement, Slide valve servicng/replacement, FLR unit servicing |
| 190 | Dismantling of seal cartridges,cleaning of seal spares and assembly |
| 191 | Dismantling of seal cartridges,cleaning of seal spares and assembly |
| 192 | Mechanical seal cartridges pneumatic testing at API seal tester |
| 193 | Lube oil top up works |
| 194 | Draining of existing lubeoil & putting new lube oil. |
| 195 | Replenish,replaceold grease. |
| 196 | Remove gland box,remove packing,replace packing,Box up |
| 197 | Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 198 | De-coupling,pump seal flushing lines removal,pump opening,casing gasket replacement,seal opening,bearing replacement, pump box up ,Alignment & coupling |
| 199 | Decople,remove bearing,seal,remove casing,check internals reassemble,align,decouple |
| 200 | Replace motor,remove coupling,shim pack,align equipment Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 201 | Replace motor,remove coupling,shim pack,align equipment Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 202 | Decouple,remove bearings,seal,remove casings,remove internals,NDT checks,repair/replace parts reassemble,align couple |
| 203 | Job include removal of each damaged nozzle and replacement/reinstallation of loose nozzles |
| 204 | Job include full set of nozzle removal and replacement/reinstallation of nozzles. |
| 205 | stack in-situ drilling , stack erection in position, tightning of stack bolts & anchor bolts(scope is for 1no cooling tower stack) |
| 206 | tightning of stack bolts & anchor bolts(scope is for 1no cooling tower fan) |
| 207 | Stack manway opeing |
| 208 | Stack manwaybox up |
| 209 | Decoupling- gearbox to motor |
| 210 | Decoupling-gearbox to fan |
| 211 | Coupling- gearbox to motor |
| 212 | Coupling-gearbox to fan |
| 213 | Dismantling of gearbox & replace/repair of internals & boxup |
| 214 | Oil seal replacement |
| 215 | Gearbox oil top up |
| 216 | Opening manway, cleaning of filter elements & manway box up |
| 217 | pump bearing greasing |
| 218 | Diaphragm valves Greasing |
| 219 | Includes cutting, coupling & laying |
| 220 | Manway opening / boxup |
| 221 | Dropping of rubber linedspool pieces & fixing after repairs |
| 222 | PM includes filter cleaning/changing , greasing/lubrication and minor repairs |
| 223 | Checking electric circuit,rectifying any problems |
| 224 | Topping up lube oil/filling the console/cleaning the console |
| 225 | Filling coolant ,topping up coolant |
| 226 | All jobs with respect to Repairs with respect to the generator |
| 227 | LRSB\"s is of 4 Mtrs Long, servicing of soot blowers includes poppet valve,gear mechanism,rollers,carriage assly,gear box,Lance tube & feed tube maintenance.Cooling air lines to be de-choked |
| 228 | Dismantling of valves & lapping the disc & seat ,box up of the valve ,gland packing renewal . |
| 229 | Bearing greasing/servicing,internal blades checking/rectification,gear box servicing,links checking & servicing. |
| 230 | MOV internals servicing,gears & bearing checking,mov box up |
| 231 | Guns servicing includes Tip cleaning/replacement,washers cleaning /replacement,all feed tubes cleaning |
| 232 | Peep hole door soot removal |
| 233 | Soot blowers Gland leak arresting |
| 234 | LRSB\"s is of 4 Mtrs Long, servicing of soot blowers includes poppet valve,gear mechanism,rollers,carriage assly,gear box,Lance tube & feed tube maintenance.Cooling air lines to be de-choked |
| 235 | LRSB\"s is of 3 Mtrs Long, servicing of soot blowers includes poppet valve,gear mechanism,rollers,carriage assly,gear box,Lance tube & feed tube maintenance.Cooling air lines to be de-choked |
| 236 | Dismantling of valves & lapping the disc & seat ,box up of the valve ,gland packing renewal . |
| 237 | Bearing greasing/servicing,internal blades checking/rectification,gear box servicing,links checking & servicing. |
| 238 | MOV internals servicing,gears & bearing checking,mov box up |
| 239 | Guns servicing includes Tip cleaning/replacement,washers cleaning /replacement,all feed tubes cleaning |
| 240 | Peep hole door soot removal |
| 241 | Soot blowers Gland leak arresting / PM jobs |
| 242 | LRSB\"s is of 3 Mtrs Long, servicing of soot blowers includes poppet valve,gear mechanism,rollers,carriage assly,gear box,Lance tube & feed tube maintenance.Cooling air lines to be de-choked |
| 243 | Manway opening & boxup |
| 244 | Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 245 | Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 246 | Open bearing housing,check dimensions ,boxing up etc |
| 247 | Ensure bypass filters is on,remove filter,clean filter,box up filter |
| 248 | Ensure bypass filters is on,remove filter,clean filter,box up filter |
| 249 | Fill oil into the lube oil tank |
| 250 | Includes pump draing,remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 251 | Check alignment procedure by laser alignment |
| 252 | Remove connected instruments,bearing housing removal,check dimensions,clean bearing housing ,cleaning cooling water piping to bearing housing ,box up bearing |
| 253 | Inccludes lube oil draining,oil flushing and oil replacement |
| 254 | Dismantle TTV,check valveseating area,repair if necessary,clean and repair replace parts |
| 255 | Romval of steam trap, maintenace and box up. Relacement of steam trap if req. |
| 256 | Blinding and deblinding of process lines .Decouple the compressor,inspection and check bearing clearances,repair replace parts of seal and bearing,do required NDTs assemble the compressor procedure,align and couple |
| 257 | Job includes removal of unloader,dismantling the unloader.Removal and replacement of unloader elements if necessary |
| 258 | Job includes cleaning of filters if required by solvent/hydrocarbon or air.Replacement of filter elemets |
| 259 | consist of removing the connecting rod pin,remove the connecting rod.Check the bearing and replace elements if necessary |
| 260 | This is inclusive of removing the stuffing box flange ,removal of rod packing cup,remove the rod packing.replace rod packing if necessary |
| 261 | Include Lubrication,tightening f flanges,checking oil levels,replace oil,arresting leaks etc |
| 262 | Includes removal of valve ,cleaning the valve plates servicing the plates ,replacing broken worn out parts |
| 263 | Includes cleaning of valve plates , replacing broken worn out parts and assembly |
| 264 | includes replacement of piston ring,rider ring and replacement with new items.Includes dismantling of cylinder head,removal of pistonnut,piston,removal of piston ring and rider ring.Job includes fixing the parts back as per assembly procedures,includesn coupling and decoupling of the compressor. Job also includes blinding and De-blinding of the job |
| 265 | Includes ,decoupling,removal of cylinder head,piston and its accessories,overhauling compressor valves,cross head maintenance,checking lubricator ,cooling systems,Compressor Auxillaries,Important compressor rod drop checks,cylinder and piston clearances and other important check,Assembling the compressor,alignment and coupling of the compressor |
| 266 | Includes decoupling,freeing connecting rod from cross head,initial inspection,removal of existing bearing,replace bearing ,assemble back elements |
| 267 | Job includes remove the flanges of the equipment containing the filters.Remove the filters clean the filters or replace the filters if required |
| 268 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 269 | Fixing the coupling spacer , tightening the bolts & Alignment rectification |
| 270 | Job includes checking the shims,cheking small end bearing,bearing clearances etc |
| 271 | consisting of checking the pump,checking feeders,replacing spares if required |
| 272 | Consisiting of servicing the pump.replacing damaged parts. |
| 273 | Consisiting of servicing the pump.replacing damaged parts. |
| 274 | Job includes remove the flanges of the equipment containing the filters.Remove the filters clean the filters or replace the filters if required |
| 275 | Job includes draining of lube oil ,cleaning and refilling with fresh lube oil |
| 276 | Job includes removal of view glass,cleaning the view glass and fitting the view glass back in position.Job includes replacement of new view glass if required |
| 277 | Remove the end cover of cylinder for internal cleaning and cylinder clearance checking.After inpection boxing up. Job includes blinding and de-blinding jobs of compressor. |
| 278 | This involves removal of cooling jacket and cleaning.After cleaning,boxing up |
| 279 | This involves removal of pump from position,dismantling and assembly of pump.Positioning of pump and alignment between pump & motor |
| 280 | Alignment checking between motor and pump. |
| 281 | Job includes removal of unloader,dismantling the unloader.Removal and replacement of unloader elements if necessary |
| 282 | Job includes cleaning of filters if required by solvent/hydrocarbon or air.Replacement of filter elemets |
| 283 | consist of removing the connecting rod pin,remove the connecting rod.Check the bearing and replace elements if necessary |
| 284 | This is inclusive of removing the stuffing box flange ,removal of rod packing cup,remove the rod packing.replace rod packing if necessary. Job includes blinding and de blinding |
| 285 | Include Lubrication,tightening of flanges,checking oil levels,replace oil,arresting leaks etc |
| 286 | Includes removal of valve ,cleaning the valve plates servicing the plates ,replacing broken worn out parts |
| 287 | Includes cleaning of valve plates , replacing broken worn out parts and assembly |
| 288 | includes replacement of piston ring,rider ring and replacement with new items.Includes dismantling of cylinder head,removal of pistonnut,piston,removal of piston ring and rider ring.Job includes fixing the parts back as per assembly procedures,includesn coupling and decoupling of the compressor. Job includes blindind and de blinding |
| 289 | Includes ,decoupling,removal of cylinder head,piston and its accessories,overhauling compressor valves,cross head maintenance,checking lubricator ,cooling systems,Compressor Auxillaries,Important compressor rod drop checks,cylinder and piston clearances and other important check,Assembling the compressor,alignment and coupling of the compressor |
| 290 | Includes decoupling,freeing connecting rod from cross head,initial inspection,removal of existing bearing,replace bearing ,assemble back elements |
| 291 | Job includes remove the flanges of the equipment containing the filters.Remove the filters clean the filters or replace the filters if required |
| 292 | Lossening coupling bolts,dropping the coupling spacer & loosening the motor foundation bolts if reqd |
| 293 | Fixing the coupling spacer , tightening the bolts & Alignment rectification |
| 294 | Job includes checking the shims,cheking small end bearing,bearing clearances etc |
| 295 | consisting of checking the pump,checking feeders,replacing spares if required |
| 296 | Consisiting of servicing the pump.replacing damaged parts. |
| 297 | Consisiting of servicing the pump.replacing damaged parts. |
| 298 | Job includes remove the flanges of the equipment containing the filters.Remove the filters clean the filters or replace the filters if required |
| 299 | Job includes draining of lube oil ,cleaning and refilling with fresh lube oil |
| 300 | Remove the lube oil cooler .Clean the internals,remove scaling and test the cooler.Put it back into service |
| 301 | Job includes removal of view glass,cleaning the view glass and fitting the view glass back in position.Job includes replacement of new view glass if required |
| 302 | Remove the end cover of cylinder for internal cleaning and clearance checking.After inpection boxing up. Job includes blinding and de blinding of compressor |
| 303 | This involves removal of cooling jacket and cleaning.After cleaning,boxing up |
| 304 | This involves removal of pump from position,dismantling and assembly of pump.Positioning of pump and alignment between pump & motor |
| 305 | Alignment checking between motor and pump. |
| 306 | Blinding and deblinding of all process lines. Removal of compressor casing .Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 307 | Open bearing housing,check dimensions ,boxing up etc |
| 308 | Ensure bypass filters is on,remove filter,clean filter,box up filter |
| 309 | Ensure bypass filters is on,remove filter,clean filter,box up filter |
| 310 | Fill oil into the lube oil tank |
| 311 | Inludes pump draining Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 312 | Check alignment procedure by laser alignment |
| 313 | Dismantle TTV,check valveseating area,repair if necessary,clean and repair replace parts |
| 314 | Remove connected instruments,bearing housing removal,check dimensions,clean bearing housing ,cleaning cooling water piping to bearing housing ,box up bearing |
| 315 | Includes oil draing, flushing and replacement. |
| 316 | Decouple,remove casing,bearing seal,diassemble the compresor ,diassemble ,check clearances,repair replace parts, assemble the compressor as per procedure,align and couple |
| 317 | Blinding and deblinding of all process lines. Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 318 | Blinding and deblinding of all process lines. Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 319 | Open bearing housing,check dimensions ,boxing up etc |
| 320 | Ensure bypass filters is on,remove filter,clean filter,box up filter |
| 321 | Ensure bypass filters is on,remove filter,clean filter,box up filter |
| 322 | Fill oil into the lube oil tank |
| 323 | Remove gland box,seal ,repair replace parts ,check required measurements and box up seal. Alignment with drive |
| 324 | Check alignment procedure by laser alignment |
| 325 | Dismantle TTV,check valveseating area,repair if necessary,clean and repair replace parts |
| 326 | Assistance for Compressor alignment checkingand correction of the alignment reading |
| 327 | Remove connected instruments,bearing housing removal,check dimensions,clean bearing housing ,cleaning cooling water piping to bearing housing ,box up bearing |
| 328 | Removal of coupling guard, coupling inspection. Decoupling and coupling |
| 329 | Decouple,remove casing,bearing seal,diassemble the compresor ,diassemble ,check clearances,repair replace parts, assemble the compressor as per procedure,align and couple |
| 330 | Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 331 | Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 332 | Open bearing housing,check dimensions ,boxing up etc |
| 333 | Ensure bypass filters is on,remove filter,clean filter,box up filter |
| 334 | Ensure bypass filters is on,remove filter,clean filter,box up filter |
| 335 | Fill oil into the lube oil tank |
| 336 | Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 337 | Check alignment procedure by laser alignment |
| 338 | Assistance for Compressor alignment checkingand correction of the alignment reading |
| 339 | Remove connected instruments,bearing housing removal,check dimensions,clean bearing housing ,cleaning cooling water piping to bearing housing ,box up bearing |
| 340 | Dismantle TTV,check valveseating area,repair if necessary,clean and repair replace parts |
| 341 | Decouple,remove casing,bearing seal,diassemble the compresor ,diassemble the turbine,check clearances,repair replace parts,do required NDTs assemble the compressor and turbine as per procedure,align and couple |
| 342 | Blinding and deblinding of process lines. Decouple,remove casing,remove crank case assembly,remove screw impellers,check clearances,do ndt if required ,check dimesnions,clean,repair/replace internals,assemble compressor,align,couple |
| 343 | Blinding and deblinding of process lines..Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 344 | Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 345 | Ensure bypass filters is on,remove filter,clean filter,box up filter |
| 346 | Include pump overhaul ,remove casing remove internals clean,repair/replace parts if required ,assemble the parts |
| 347 | Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 348 | Alignment procedure mentioned in 4.07.03 |
| 349 | Remove filter ,clean/replace/repair,box up coalescer |
| 350 | decouple,remove casing,seals rotor, bearing,remove internals,clean,check dimensions,,repair/replace parts,Box up,align and couple the compressor |
| 351 | Inludes compressor NDE side hood removal , decoupling and coupling |
| 352 | Removal of Motor hood and installation after instrumentation maintenance |
| 353 | Remove bearing, gland,remove seal,repair /replace seal,check dimensions,box up seal |
| 354 | Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 355 | Ensure bypass filters is on,remove filter,clean filter,box up filter |
| 356 | Include pump oil draining ,overhaul ,remove casing remove internals clean,repair/replace parts if required ,assemble the parts |
| 357 | Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 358 | Couling, decoupling &Alignment procedure mentioned in 4.08.03 |
| 359 | Remove filter ,clean/replace/repair,box up coalescer |
| 360 | Blinding, deblinding, open casing cover on end. Open bearing housing,check dimensions ,boxing up etc |
| 361 | Top up/replensih lube oil,clean console |
| 362 | Drain pot as per procedure |
| 363 | Ensure bypass filters,clean filters,replace/repair if required,box up filters |
| 364 | Ensure bypass filters,clean filters,replace/repair if required,box up filters |
| 365 | Opening of GB casing cover, opening and inspecion/replacemnt of bearing. Dimension check . Box up |
| 366 | Replace . Cleaning of console and all pipings,replenish oil,clean console |
| 367 | Removal of all the pipings & reassembly after hydrotest(shell & turbe side), remove cooler,clean cooler,hydrotest,replace cooler if required |
| 368 | Removal of all the pipings & reassembly after hydrotest(shell & turbe side), remove cooler,clean cooler,hydrotest,replace cooler if required |
| 369 | Removal of all the pipings & reassembly after hydrotest(shell & turbe side), remove cooler,clean cooler,hydrotest,replace cooler if required |
| 370 | Removal of all the pipings & reassembly after hydrotest(shell & turbe side), remove cooler,clean cooler,hydrotest,replace cooler if required |
| 371 | Decoupling & coupling.align equipment Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 372 | Remval / fixing of of holdinng boltsand cooling water lines of the cooler |
| 373 | Assistance for : Decouple, remove casings, remove impellers, remove labyrinths, clean ,check dimensions,re-assemble the parts,align,couple |
| 374 | Compressor Lube oil Topup including handling of barrel |
| 375 | Compressor De-Coupling & coupling for free rotation check/Any electrical related check |
| 376 | Remove gland box,seal ,repair replace parts ,check required measurements and box up seal |
| 377 | De-coupling,pump seal flushing lines removal,pump opening,casing gasket replacement,seal opening,bearing replacement, pump box up ,Alignment & coupling |
| 378 | Couplin and decoupling ,shim pack,align equipment Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 379 | ARV Servicing as per procedure |
| 380 | Replace motor,remove coupling,shim pack,align equipment Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 381 | Decouple,remove bearings,seal,remove casings,remove barrels internals,disassembly of impeller , diffusers.checks,repair/replace parts reassemble,align couple |
| 382 | Decouplig & coupling for free rotation check & Any electrical related work |
| 383 | Flushing of the old lube Oil , cleaning & refiling, Cooling water line dechocking |
| 384 | Filter removal,cleaning,repair/replacebox up |
| 385 | Replace of old oil from tank and all lines. Re fillingand handling of oil barrels |
| 386 | Filter removal,cleaning,repair/replacebox up |
| 387 | greasing requirement as per procedure for governor valves (HP,MP,LP) |
| 388 | Remove bearing housing,check beatrings as per procedure and box up |
| 389 | Remove motor,replace/repair,align and couple |
| 390 | Gear maintenance as per procedure |
| 391 | Emergency safety valve removal,clean,inspect check dimensions,replace/repair parts,box up |
| 392 | Check bearing ,repair,replace bearing if required |
| 393 | Check actuator repair replace parts if required |
| 394 | Check actuator repair replace parts if required |
| 395 | Check actuator repair replace parts if required |
| 396 | Accumulator to be removed and replaced as per procedure |
| 397 | Storke checking and adjustements as per procedure |
| 398 | Remove links and connections ,repair replace parts |
| 399 | Bearing removal check dimensions ,clearance and box up |
| 400 | Alignment as per procedure |
| 401 | Alignment as per procedure |
| 402 | Filter removal,cleaning,repair/replacebox up |
| 403 | Gear maintenance as per procedure & alignment |
| 404 | Expander overhauling as per procedure, alignment |
| 405 | alignment as per procedure |
| 406 | alignment as per procedure |
| 407 | Expander lube oil top up |
| 408 | Ensure bypass filters,clean filters,replace/repair if required,box up filters |
| 409 | Ensure bypass filters,clean filters,replace/repair if required,box up filters |
| 410 | Removal of the piping , casing and rotor assemblyof one stage check dimesnions,clean etc |
| 411 | Replace,replenish oil,clean console and piping and fill up in barrels |
| 412 | Removal of all the pipings & reassembly after hydrotest(shell & turbe side), remove cooler,clean cooler,hydrotest,replace cooler if required |
| 413 | Removal of all the pipings & reassembly after hydrotest(shell & turbe side), remove cooler,clean cooler,hydrotest,replace cooler if required |
| 414 | Removal of all the pipings & reassembly after hydrotest(shell & turbe side), remove cooler,clean cooler,hydrotest,replace cooler if required |
| 415 | Removal of all the pipings & reassembly after hydrotest(shell & turbe side), remove cooler,clean cooler,hydrotest,replace cooler if required |
| 416 | remove coupling,shim pack,align equipment Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 417 | Replace motor,remove coupling,shim pack,align equipment Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 418 | Decouple, removal o pipings ,remove casings, rotor assembly , bearings ,remove labyrinths/ seals,clean ,check dimensions,assemble the parts,align,couple |
| 419 | Compressor Lube oil Topup |
| 420 | Compressor De-Coupling & coupling for free rotation check/Any electrical related check |
| 421 | Filter removal,cleaning,repair/replacebox up |
| 422 | Filter removal,cleaning,repair/replacebox up |
| 423 | Filter removal,cleaning,repair/replacebox up |
| 424 | Filter removal(128 nos),cleaning,repair/replacebox up ( considering individual filter) |
| 425 | AOP, EOP & AHOP maintenance |
| 426 | lube oil mist seperator |
| 427 | Filter removal,cleaning,repair/replacebox up |
| 428 | Flow divider maintenance |
| 429 | Combustion chamber maintenance(One combustion chamber) |
| 430 | Remove bearing housing,check beatrings as per procedure |
| 431 | Bearing removal check dimensions ,clearance and box up |
| 432 | alignment as per procedure |
| 433 | alignment as per procedure |
| 434 | alignment as per procedure |
| 435 | Removal of coupling guard / coupling inspection |
| 436 | Filter removal,cleaning,repair/replacebox up |
| 437 | Filter elemenets removal,cleaning,repair/replacebox up |
| 438 | Filter removal,cleaning,repair/replacebox up |
| 439 | Filter removal,cleaning,repair/replacebox up |
| 440 | Remove Inlet manway,IGV blades cleaning and clearance checking.Boxing up of manway. |
| 441 | IGV drive mechanism dust cover removal,cleaning of rack & pinion,greasing of the same. |
| 442 | IGV actuator disconnection from IGV drive,removal of old actuator and replacing with new one.Connecting actuator with drive |
| 443 | Includes dissassembly of valves,clean internals,repair/replace parts,lubricate,check assembled valve |
| 444 | This activity involves shifting of nitrogen cylinder to the site,checking the precharge pressure.If pressure less than the desired pressure then charging nitrogen to the accumulator |
| 445 | Remove the accumulator from position and dismantled the internals.Assembly with cleaned or new spares.Positioning the accumulator at its position and precharge with nitrogen |
| 446 | Draining/Flushing and refilling |
| 447 | Checking all link, removal, cleaning, greasing if required and box up |
| 448 | Opening top cover, Removing bowls, Cleaning and box up |
| 449 | includes removing coupling cover, decoupling, disconnection of pipings, removal of foundation bolts and pump. |
| 450 | Dismantling JOP, Rotor checking, Replacement of O rings and gaskets and assembly |
| 451 | Opening the software database,Identify the Route, Download empty route, Data acquisition using portable hand held Analysers, reporting abnormalities noticed while data acquisition, troubleshooting minor data acquisition related problems, uploading the data to Software. Generate exception reports from the Route Data. |
| 452 | Opening the software database,Identify the Route, Download empty route, Data acquisition using portable hand held Analysers, reporting abnormalities noticed while data acquisition, troubleshooting minor data acquisition related problems, uploading the data to Software. Generate exception reports from the Route Data. |
| 453 | decoupling as removal of couppling and removal of motor foundation bolt if required |
| 454 | Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 455 | Includes remove,repair ,replacement of belts ,chains |
| 456 | Includes lubricating,topping up or refilling lubrication |
| 457 | Includes repair ,replacement of oil seal |
| 458 | Includes topping of oil |
| 459 | Includes removal of gear box,dissassembly,repair /replacement of parts,assembly |
| 460 | Includes servicing as per replacement/repair of parts |
| 461 | Overhauling includes disassembly,repair/replacement of parts |
| 462 | includes removal of existing belt,replacing belt ensuring proper tightness |
| 463 | decoupling as removal of couppling and removal of motor foundation bolt if required |
| 464 | Flush oil or grease as required |
| 465 | Includes repair ,replacement of oil seal |
| 466 | Includes removal of gear box,dissassembly,repair /replacement of parts,assembly |
| 467 | includes servicing the agitator mechanicsm,repairing and replacing parts if required |
| 468 | coupling and alignment |
| 469 | gear box PM jobs |
| 470 | Ensure equipment is on by pass filter.Remove the clogged filter.Dip in a solvent or Hydrocrabon or as advised by Engineer In charge.Clean the filter element and box up |
| 471 | Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 472 | Includes lube oil replacement.Attending on line leaks.or any other specifically defined by EIC |
| 473 | once the equipment is aligned fix thecoupling by bolts and shim pack. |
| 474 | Motor must be deenergised.Remove coupling bolt,remove shims and measure DBSE |
| 475 | Job includes removal of old belt.Alignment checks ,ensure distance between the belt pulleys are appropriate and fix belt accordingly |
| 476 | Open the bearing house replace bearing as per specification and provide lubrication as specified |
| 477 | Job includes removal of bearing and replacing of seal or gland arrangement |
| 478 | Job includes decoupling,removing the casing ,remove impeller,remove seal/glandand bearing. |
| 479 | as specified |
| 480 | includes removal of existing belt,replacing belt ensuring proper tightness |
| 481 | decoupling as removal of couppling and removal of motor foundation bolt if required |
| 482 | Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 483 | PM includes greasing/lubrication and minor repairs |
| 484 | Servicing the centrifuge,repair/replace spares |
| 485 | includes belt replacement,tightening,alignment |
| 486 | decouple the pump form the motor |
| 487 | Once the equipment is aligned fix thecoupling by bolts and shim pack.Alignment includes laser alignment or alignment with dial indicator .Alignment with Dial indicators can be face-radial or reverse indicator method.Includes removal of offset,angular and radial misalignment.For equipments where the shaft dia is small say less than 10 mm equipments are aligned using straight edge or feeler gauges |
| 488 | arrest gland leak by thightening or replacement of gland |
| 489 | decouple,remove casing ,remove bearing,dissassemble stator,replace /repair if required,assmeble,align and couple |
| 490 | decouple,remove casing ,remove bearing,dissassemble stator,replace /repair if required,assmeble,align and couple |
| 491 | Diapharam valveremoval and fixing |
| 492 | Diaphragm valve service |
| 493 | servicing includes tightening,lubricating etc |
| 494 | ensuring that the pump inlet is flooded before starting of the pump ,ensuring adequate NPSH |
| 495 | Opening of the Flanges(2 Nos.),Dropping of spool piece,Cleaning of the Filter/mesh, Boxing up of the Flanges( 2 Nos.) |
| 496 | Opening of the flange , filter removal and cleaning, boxing up of the flange |
| 497 | Connection of hoses as per operation requirement |
| 498 | Dropping PVRV |
| 499 | Boxing up PVRV once serviced |
| 500 | Open manway of the tank as required |
| 501 | Box up manway of the tank as required |
| 502 | Trough Fixing for oil removal & Removal |
| 503 | Fix exhaust fan/eductor for evacuating and taking man entry of the tank |
| 504 | Remove exhaust fan/eductor for evacuating and taking man entry of the tank |
| 505 | Attend seal leak,replace repair parts if required |
| 506 | Gear box servicing includes lubricating,repair /replacement of parts |
| 507 | Hydrotest of coil at the required pressure |
| 508 | Dropping PVRV |
| 509 | Boxing up PVRV once serviced |
| 510 | drop NRV for servicing |
| 511 | Fix NRV after servicing |
| 512 | Replace swivel joints |
| 513 | Replace swivel joints |
| 514 | Open manways for man entry |
| 515 | Box up manways |
| 516 | Open Manways |
| 517 | Box up manways |
| 518 | Remove the weather sheeting,replace with new sheet,repair if required |
| 519 | Opening & servicing / replacement of foam glass |
| 520 | Dropping emergency vent-EV and servicing |
| 521 | Boxing up emergency vent after servicing |
| 522 | Servicing of Slot dipping hatch |
| 523 | Servcing of LSHS Tank 31-FB-26A/B Goose Neck |
| 524 | Entering the tank internal floating roof from Top fixed manway and Lifting roof leg from 1.8mtrs(maintenance height) and lowering roof leg to 1.2 mtrs (Process Height) . |
| 525 | Hydrotest the pipelines as per procedure |
| 526 | Greasing ,removal of old grease & injection of fresh grease |
| 527 | Greasing ,removal of old grease & injection of fresh grease |
| 528 | Greasing ,removal of old grease & injection of fresh grease |
| 529 | Greasing ,removal of old grease & injection of fresh grease |
| 530 | Removal of leaking hose & fixing of new hose |
| 531 | Emergency release system servicing & operation |
| 532 | Swivel joints packing replacement. |
| 533 | Hydraulic cylinder opening, cleaning of ports,o-ring,packings replacement, cylinder & piston checking,box up |
| 534 | Coupler Alignment. |
| 535 | Replacement of ball valve (12 inch/16 inch) |
| 536 | Flange Bolts servicing |
| 537 | Checking& replacement hyd.oil/filter. |
| 538 | Testing of product pipe lines from OMPL to NMPT |
| 539 | Fixing of Fire hydrant adaptors to the flanges for flushing |
| 540 | CBD pump Mech. seal changing. |
| 541 | Dismantling of In-Board /Out Board arm,dropping of quick connecting dis connecting coupler,dropping of In-Board/out board arm /Horizontal cylinders,Emergency release system dropping ,Etc |
| 542 | Servicing includes dissembly, cleaning, repairing,lapping,replacement of parts and assembly |
| 543 | PSV overhauling>2<=4 |
| 544 | PSV overhauling>4<=6 |
| 545 | PSV overhauling>6<=8 |
| 546 | PSV overhauling>8<=10 |
| 547 | PSV overhaulingabove 10\" |
| 548 | Testing & calibration |
| 549 | Testing & calibration |
| 550 | Servicing includes cleaning ,repairing,lapping,replacement of parts |
| 551 | Testing / calibration |
| 552 | Servicing includes cleaning,testing ,repairing,replacement of parts |
| 553 | Servicing includes cleaning,testing ,repairing,replacement of parts |
| 554 | Servicing includes cleaning ,repairing,replacement of parts |
| 555 | Servicing includes cleaning ,repairing,replacement of parts |
| 556 | Servicing includes cleaning ,repairing,replacement of parts |
| 557 | Testing / calibration |
| 558 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 559 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 560 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 561 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 562 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 563 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 564 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 565 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 566 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 567 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 568 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 569 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 570 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 571 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 572 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 573 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 574 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 575 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 576 | Servicing includes disassembly, cleaning ,repairing,replacement of parts, assembly & testing |
| 577 | 1/2\"\" # 150 No of bolts 4 |
| 578 | 3/4\"\" # 150 No of bolts 4 |
| 579 | 1\"\" # 150 No of bolts 4 |
| 580 | 1 1/4\"\" # 150 No of bolts 4 |
| 581 | 1 1/2\"\" # 150 No of bolts 4 |
| 582 | 2\"\" # 150 No of bolts 4 |
| 583 | 2 1/2\"\" # 150 No of bolts 4 |
| 584 | 3\"\" # 150 No of bolts 4 |
| 585 | 3 1/2\"\" # 150 No of bolts 8 |
| 586 | 4\"\" # 150 No of bolts 8 |
| 587 | 5\"\" # 150 No of bolts 8 |
| 588 | 6\"\" # 150 No of bolts 8 |
| 589 | 8\"\" # 150 No of bolts 8 |
| 590 | 10\"\" # 150 No of bolts 12 |
| 591 | 12\"\" # 150 No of bolts 12 |
| 592 | 14\"\" # 150 No of bolts 12 |
| 593 | 16\"\" # 150 No of bolts 16 |
| 594 | 18\"\" # 150 No of bolts 16 |
| 595 | 20\"\" # 150 No of bolts 20 |
| 596 | 24\"\" # 150 No of bolts 20 |
| 597 | above 26\"\" # 150 |
| 598 | 1/2\"\" # 300 No of bolts 4 |
| 599 | 3/4\"\" # 300 No of bolts 4 |
| 600 | 1\"\" # 300 No of bolts 4 |
| 601 | 1 1/2\"\" # 300 No of bolts 4 |
| 602 | 2\"\" # 300 No of bolts 8 |
| 603 | 2 1/2\"\" # 300 No of bolts 8 |
| 604 | 3\"\" # 300 No of bolts 8 |
| 605 | 3 1/2\"\" # 300 No of bolts 8 |
| 606 | 4\"\" # 300 No of bolts 8 |
| 607 | 5\"\" # 300 No of bolts 8 |
| 608 | 6\"\" # 300 No of bolts 12 |
| 609 | 8\"\" # 300 No of bolts 12 |
| 610 | 10\"\" # 300 No of bolts 16 |
| 611 | 12\"\" # 300 No of bolts 16 |
| 612 | 14\"\" # 300 No of bolts 20 |
| 613 | 16\"\" # 300 No of bolts 20 |
| 614 | 18\"\" # 300 No of bolts 24 |
| 615 | 20\"\" # 300 No of bolts 24 |
| 616 | 24\"\" # 300 No of bolts 24 |
| 617 | above 26\"\" # 300 |
| 618 | 1/2\"\" # 600 No of bolts 4 |
| 619 | 3/4\"\" # 600 No of bolts 4 |
| 620 | 1\"\" # 600 No of bolts 4 |
| 621 | 1 1/4\"\" # 600 No of bolts 4 |
| 622 | 1 1/2\"\" # 600 No of bolts 4 |
| 623 | 2\"\" # 600 No of bolts 8 |
| 624 | 2 1/2\"\" # 600 No of bolts 8 |
| 625 | 3\"\" # 600 No of bolts 8 |
| 626 | 3 1/2\"\" # 600 No of bolts 8 |
| 627 | 4\"\" # 600 No of bolts 8 |
| 628 | 5\"\" # 600 No of bolts 8 |
| 629 | 6\"\" # 600 No of bolts 12 |
| 630 | 8\"\" # 600 No of bolts 12 |
| 631 | 10\"\" # 600 No of bolts 16 |
| 632 | 12\"\" # 600 No of bolts 20 |
| 633 | 14\"\" # 600 No of bolts 20 |
| 634 | 16\"\" # 600 No of bolts 20 |
| 635 | 18\"\" # 600 No of bolts 20 |
| 636 | 20\"\" # 600 No of bolts 24 |
| 637 | 24\"\" # 600 No of bolts 24 |
| 638 | above 26\"\" # 600 |
| 639 | 1/2\"\" # 900 No of bolts 4 |
| 640 | 3/4\"\" # 900 No of bolts 4 |
| 641 | 1\"\" # 900 No of bolts 4 |
| 642 | 1 1/4\"\" # 900 No of bolts 4 |
| 643 | 1 1/2\"\" # 900 No of bolts 4 |
| 644 | 2\"\" # 900 No of bolts 8 |
| 645 | 2 1/2\"\" # 900 No of bolts 8 |
| 646 | 3\"\" # 900 No of bolts 8 |
| 647 | 3 1/2\"\" # 900 No of bolts 8 |
| 648 | 4\"\" # 900 No of bolts 8 |
| 649 | 5\"\" # 900 No of bolts 8 |
| 650 | 6\"\" # 900 No of bolts 12 |
| 651 | 8\"\" # 900 No of bolts 12 |
| 652 | 10\"\" # 900 No of bolts 16 |
| 653 | 12\"\" # 900 No of bolts 20 |
| 654 | 14\"\" # 900 No of bolts 20 |
| 655 | 16\"\" # 900 No of bolts 20 |
| 656 | 18\"\" # 900 No of bolts 20 |
| 657 | 20\"\" # 900 No of bolts 20 |
| 658 | 24\"\" # 900 No of bolts 20 |
| 659 | above 26\"\" # 900 |
| 660 | Checking for any looseness of bolts, hand tightning under hot conditions |
| 661 | Torquing of reduction zone bolts under hot condition |
| 662 | Peep hole glass cleaning |
| 663 | Peep hole glass replacement |
| 664 | Peep Hole glass Rope replacement/Repair |
| 665 | Peep Hole glass cooling air hose replacement |
| 666 | Peep Hole mechanism Servicing |
| 667 | BurnerIndividual Gun dropping ,Cleaning & box up |
| 668 | Burner Pilot Dropping,cleaning & box up |
| 669 | Burner Block assembly Dropping,overhauling & box up |
| 670 | Burner Hose Connection( Per Hose) |
| 671 | Air registers Servicing |
| 672 | Oil Gun tip assembly overhauling |
| 673 | Burner Watch Glass cleaning (per glass) |
| 674 | Horizontal Coil support Replacement |
| 675 | Vertical Coil support replacement |
| 676 | Supports cleaning by opening the dummy( Per support) |
| 677 | Bellow leak |
| 678 | Bellow Repair |
| 679 | Duct bellows replacementSize Leass Than 1 Sq.Mtr |
| 680 | Duct bellows replacementSize 1 Sq.MtrTo 6 Sq.Mtr |
| 681 | Duct bellows replacementSize : 6Sq.Mtrs to12Sq.Mtr |
| 682 | Stack damper PM Job |
| 683 | Stack damper shaft bearing replacement |
| 684 | Stack damper overhualing |
| 685 | Stack damper minor repair |
| 686 | Stack damper -Actuator decoupling & Coupling |
| 687 | Job includes tightening of throat bush to arrest gland leak |
| 688 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 689 | Job includes greasing of stem |
| 690 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 691 | Job includes removal of bonnet gasket and replacement of new gasket |
| 692 | Job includes dropping of valves and replacement of spare valve |
| 693 | Job includes tightening of throat bush to arrest gland leak |
| 694 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 695 | Job includes greasing of stem |
| 696 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 697 | Job includes removal of bonnet gasket and replacement of new gasket |
| 698 | Job includes dropping of valves and replacement of spare valve |
| 699 | Job includes tightening of throat bush to arrest gland leak |
| 700 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 701 | Job includes greasing of stem |
| 702 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 703 | Job includes removal of bonnet gasket and replacement of new gasket |
| 704 | Job includes dropping of valves and replacement of spare valve |
| 705 | includes removal of gear box and servicing the gear box |
| 706 | Gear box greasing |
| 707 | Job includes tightening of throat bush to arrest gland leak |
| 708 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 709 | Job includes greasing of stem |
| 710 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 711 | Job includes removal of bonnet gasket and replacement of new gasket |
| 712 | Job includes dropping of valves and replacement of spare valve |
| 713 | includes removal of gear box and servicing the gear box |
| 714 | Gear box greasing |
| 715 | Job includes tightening of throat bush to arrest gland leak |
| 716 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 717 | Job includes greasing of stem |
| 718 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 719 | Job includes removal of bonnet gasket and replacement of new gasket |
| 720 | Job includes dropping of valves and replacement of spare valve |
| 721 | includes removal of gear box and servicing the gear box |
| 722 | Gear box greasing |
| 723 | Job includes tightening of throat bush to arrest gland leak |
| 724 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 725 | Job includes greasing of stem |
| 726 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 727 | Job includes removal of bonnet gasket and replacement of new gasket |
| 728 | Job includes dropping of valves and replacement of spare valve |
| 729 | includes removal of gear box and servicing the gear box |
| 730 | Gear box greasing |
| 731 | Job includes tightening of throat bush to arrest gland leak |
| 732 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 733 | Job includes greasing of stem |
| 734 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 735 | Job includes removal of bonnet gasket and replacement of new gasket |
| 736 | Job includes dropping of valves and replacement of spare valve |
| 737 | Job includes tightening of throat bush to arrest gland leak |
| 738 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 739 | Job includes greasing of stem |
| 740 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 741 | Job includes removal of bonnet gasket and replacement of new gasket |
| 742 | Job includes dropping of valves and replacement of spare valve |
| 743 | includes removal of gear box and servicing the gear box |
| 744 | Gear box greasing |
| 745 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 746 | Job includes greasing of stem |
| 747 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 748 | Job includes removal of bonnet gasket and replacement of new gasket |
| 749 | Job includes dropping of valves and replacement of spare valve |
| 750 | includes removal of gear box and servicing the gear box |
| 751 | Gear box greasing |
| 752 | Job includes tightening of throat bush to arrest gland leak |
| 753 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 754 | Job includes greasing of stem |
| 755 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 756 | Job includes removal of bonnet gasket and replacement of new gasket |
| 757 | Job includes dropping of valves and replacement of spare valve |
| 758 | includes removal of gear box and servicing the gear box |
| 759 | Gear box greasing |
| 760 | Job includes tightening of throat bush to arrest gland leak |
| 761 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 762 | Job includes greasing of stem |
| 763 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 764 | Job includes removal of bonnet gasket and replacement of new gasket |
| 765 | Job includes dropping of valves and replacement of spare valve |
| 766 | includes removal of gear box and servicing the gear box |
| 767 | Gear box greasing |
| 768 | Job includes tightening of throat bush to arrest gland leak |
| 769 | Job includes removal of throat bush,replacement of gland packing ,tightening of throat bush and arresting leak during running |
| 770 | Job includes greasing of stem |
| 771 | Job includes removal of yoke bush ,cleraing the treads or rethreading or replacment of yoke bush |
| 772 | Job includes removal of bonnet gasket and replacement of new gasket |
| 773 | Job includes dropping of valves and replacement of spare valve |
| 774 | includes removal of gear box and servicing the gear box |
| 775 | Gear box greasing |
| 776 | Valve replacement |
| 777 | Valve replacement |
| 778 | Valve replacement |
| 779 | Valve replacement |
| 780 | includes replacement of gland or replacement of seal |
| 781 | involves removal of internals and replacing the seat |
| 782 | includes removal of gear box and servicing the gear box |
| 783 | Includes servicing of valve and gear box parts in total |
| 784 | includes replacement of gland or replacement of seal |
| 785 | involves removal of internals and replacing the seat |
| 786 | includes removal of gear box and servicing the gear box |
| 787 | Includes servicing of valve and gear box parts in total |
| 788 | includes replacement of gland or replacement of seal |
| 789 | involves removal of internals and replacing the seat |
| 790 | includes removal of gear box and servicing the gear box |
| 791 | Includes servicing of valve and gear box parts in total |
| 792 | includes replacement of gland or replacement of seal |
| 793 | involves removal of internals and replacing the seat |
| 794 | includes removal of gear box and servicing the gear box |
| 795 | Includes servicing of valve and gear box parts in total |
| 796 | includes replacement of gland or replacement of seal |
| 797 | involves removal of internals and replacing the seat |
| 798 | includes removal of gear box and servicing the gear box |
| 799 | Includes servicing of valve and gear box parts in total |
| 800 | includes replacement of gland or replacement of seal |
| 801 | involves removal of internals and replacing the seat |
| 802 | includes removal of gear box and servicing the gear box |
| 803 | Includes servicing of valve and gear box parts in total |
| 804 | includes replacement / injection of gland or replacement of seal |
| 805 | involves removal of internals and replacing the seat |
| 806 | includes removal of gear box and servicing the gear box |
| 807 | Includes servicing of valve and gear box parts in total |
| 808 | includes replacement / injection of gland or replacement of seal |
| 809 | involves removal of internals and replacing the seat |
| 810 | includes removal of gear box and servicing the gear box |
| 811 | Includes servicing of valve and gear box parts in total |
| 812 | includes replacement / injection of gland or replacement of seal |
| 813 | involves removal of internals and replacing the seat |
| 814 | includes removal of gear box and servicing the gear box |
| 815 | Includes servicing of valve and gear box parts in total |
| 816 | includes replacement / injection of gland or replacement of seal |
| 817 | involves removal of internals and replacing the seat |
| 818 | includes removal of gear box and servicing the gear box |
| 819 | Includes servicing of valve and gear box parts in total |
| 820 | includes replacement / injection of gland or replacement of seal |
| 821 | involves removal of internals and replacing the seat |
| 822 | includes removal of gear box and servicing the gear box |
| 823 | Includes servicing of valve and gear box parts in total |
| 824 | includes replacement / injection of gland or replacement of seal |
| 825 | involves removal of internals and replacing the seat |
| 826 | includes removal of gear box and servicing the gear box |
| 827 | Includes servicing of valve and gear box parts in total |
| 828 | Cv Dropping (Size-1/2\" to 11/2\") |
| 829 | CV Fixing(Size-1/2\" to 11/2\") |
| 830 | CV Dropping(Size-2\" to 4\") |
| 831 | CV Fixing(Size-2\" to 4\") |
| 832 | CV Dropping(Size-6\" to 10\") |
| 833 | CV Fixing(Size-6\" to 10\") |
| 834 | CV Dropping(Size-12\" to 18\") |
| 835 | CV Fixing(Size-12\" to 18\") |
| 836 | CV Dropping(Size-20\" to 24\") |
| 837 | CV Fixing(Size-20\" to 24\") |
| 838 | CV Dropping (above 24\") |
| 839 | CV Fixing(above 24\") |
| 840 | Cv Dropping (Size-1/2\" to 11/2\") |
| 841 | CV Fixing(Size-1/2\" to 11/2\") |
| 842 | CV Dropping(Size-2\" to 4\") |
| 843 | CV Fixing(Size-2\" to 4\") |
| 844 | CV Dropping(Size-6\" to 10\") |
| 845 | CV Fixing(Size-6\" to 10\") |
| 846 | CV Dropping(Size-12\" to 18\") |
| 847 | CV Fixing(Size-12\" to 18\") |
| 848 | CV Dropping(Size-20\" to 36\") |
| 849 | CV Fixing(Size-20\" to 36\") |
| 850 | Opening of PSV (0.5\" to 1.5\") |
| 851 | Dropping of PSV (0.5\" to 1.5\") |
| 852 | Erection of PSV (0.5\" to 1.5\") |
| 853 | Boxup of PSV (0.5\" to 1.5\") |
| 854 | Opening of PSV (2\" to 4\") |
| 855 | Dropping of PSV (2\" to 4\") |
| 856 | Erection of PSV (2\" to 4\") |
| 857 | Boxup of PSV (2\" to 4\") |
| 858 | Opening of PSV (6\" to 10\") |
| 859 | Boxup of PSV (6\" to 10\") |
| 860 | Opening of PSV (Above10\") |
| 861 | Boxup of PSV (Above 10\") |
| 862 | Pipe line HT upto 2\" |
| 863 | Pipe line HT upto 6\" |
| 864 | Pipe line HT upto 12\" |
| 865 | Pipe line HT upto 20\" |
| 866 | Pipe line HT above 20\" |
| 867 | Pipe line HT uto 2\" |
| 868 | Pipe line HT upto 6\" |
| 869 | Pipe line HT upto 12\" |
| 870 | Pipe line HT upto 20\" |
| 871 | Pipe line HT above 20\" |
| 872 | Clamps fixing upto 4\" |
| 873 | Clamps fixingupto 10\" |
| 874 | Clamps fixingabove 10\" |
| 875 | Dismantling of all trap internals, servicing & box up |
| 876 | Trap reconditioning by without dismantling the trap internals |
| 877 | Hydraulic cylinder & hydraulic pumphose replacement |
| 878 | Hyd cylinder gland tightening |
| 879 | Cylinder removal, gland replacement, fixing cylinder back and other related jobs |
| 880 | Knuckle pin replacement |
| 881 | CMI rotor plate inspection |
| 882 | Accumulator bladder replacement |
| 883 | Accumulator bladder N2 charging |
| 884 | CMI primary & secondary seal replacement, actuator assembly and other related jobs |
| 885 | Rotor seal sheet replacement and other related jobs till completion |
| 886 | Full Greasing of each ports as per drawing |
| 887 | Job includes remove the flanges of the equipment containing the coalescers.Remove the coalescers clean the coalescers or replace the coalescers if required |
| 888 | Job includes remove the flanges of the equipment containing the filter elements. Remove the filters clean the filters or replace the filters if required & box up. |
| 889 | Opening of dome bolts, removing all elements from the filter & shifted to cleaning area& Blinding and deblinding for draining and Flange opening for dome opening and hose connection and disconnection for draining purpose |
| 890 | Chemical cleaning & air cleaning |
| 891 | Shifting all elements from cleaning area to filter location & Final box up& Blinding and deblibnding for system normalizing and hose connection disconnection |
| 892 | Opening, Cleaning,box up including blidnding works for draining |
| 893 | Opening, Cleaning,box up including blidnding works for draining |
| 894 | Opening, Cleaning,box up including blidnding works for draining |
| 895 | Opening, Cleaning,box up including blidnding works for draining |
| 896 | Job includes removal of ejector .Remove the nozzle and clean the nozzle.Replace nozzle if required |
| 897 | Job includes providing eductors at various location like column manholes/vessel manholes heater manholes and properly binding them either with bolts or binding wire as per site conditions |
| 898 | Strainer cleaning upto 2 inch |
| 899 | Strainer cleaning (2- 6 inch) |
| 900 | Strainer cleaning (8- 12 inch) |
| 901 | Strainer cleaning (14- 24 inch) |
| 902 | Strainer cleaning (26- 36 inch) |
| 903 | Strainer cleaning (Above 36 inch) |
| 904 | Includes dome opening, filter cleaning & boxup |
| 905 | Replacement of peddles, springs & fittings |
| 906 | Full set replacement |
| 907 | material like hoses, gaskets, blinds,etc. shifting from plant store to job location & vice versa |
| 908 | material like hoses, gaskets, blinds,etc. shifting from Non plant yard to job location & vice versa |
| 909 | Hot Bolting of Casing |
| 910 | Motor Base Bolt removal/Boxup |
| 911 | CMI Hydraulic Pump Overhauling including Hydraulic hose removal and base bolt opening |
| 912 | CMI Hydraulic Hose Replacement |
| 913 | Bolted seal plate inside furnace to be opened inside the furnace & refixing after the job |
| 914 | Job includes removal & installation of yoke bush ,cleraing the treads or rethreading or replacment of diaphragm |
| 915 | Job includes removal & installation of yoke bush ,cleraing the treads or rethreading or replacment of diaphragm |
| 916 | Job includes removal & installation of yoke bush ,cleraing the treads or rethreading or replacment of diaphragm |
| 917 | Job include removal of old pipe line and installation of cpvc pipe line in DM plant. |
| 918 | Job include removal of old pipe line and installation of cpvc pipe line in DM plant. |
| 919 | Job include removal of old pipe line and installation of cpvc pipe line in DM plant. |
| 920 | Job includes blinding , bearing inspection and replacement,Seal inspection and replacement,alignment and box up as per procedure |
| 921 | Removal , Inspection and servicing ofIGV |
| 922 | Filter removal,cleaning,repair/replacebox up |
| 923 | Filter removal,cleaning,repair/replacebox up |
AI Tender Summary
Tender Timeline
May 12, 2021
11:30 IST
Tender Published
Tender notice published.
CompletedJun 01, 2021
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
CompletedJun 02, 2021
Bid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender