| 1 | 1 | Item Description/ Heading | BI01010001010000000000000515BI0100001112 | | |
|---|
| 2 | 1.01 | Transportation of 2x150kw, 6.6kv, Dual Drive unit complete with Drive Drum, Driven Drum, Two Gear Boxes, Two motors, Couplings, Bearing Blocks, Dust Collector, Fenchings, etc. after loading it on MUV from surface and installation at -12R/-30L | BI01010001010000000000000515BI0100001113 | 12 | MT |
|---|
| 3 | 1.02 | Transportation of Discharge Unit complete with cleaner, after loading it on MUV from surface and installation at -12R/-30L | BI01010001010000000000000515BI0100001114 | 3 | MT |
|---|
| 4 | 1.03 | Transportataion of Tail End Unit complete, after loading it on MUV from surface and installation at -12R/-34L | BI01010001010000000000000515BI0100001115 | 1 | MT |
|---|
| 5 | 1.04 | Transportation and installation of 128 mtr of belt structure after loading it on MUV from surface to installation site | BI01010001010000000000000515BI0100001116 | 10.88 | MT |
|---|
| 6 | 1.05 | Transportation, laying, lapping and jointing of 256 meters of belting | BI01010001010000000000000515BI0100001117 | 1 | Work |
|---|
| 7 | 1.06 | Laying/ placement of Starter, VCB, Cables and lockout devices after transporting as detailed below:- \n1)Transporting of one 6.6 kv, 2x150 kw, from surface to -12R/-30L after loading it on MUV then unloading and placing manually on platform,\n2)Transporting of two nos 6.6 KV, 400A, VCB from surface to -12R/-30L, 8R/-29/L after loading them on MUV then unloading and placing manually on platform,\n3)Transporting of 640 mtr, 6.6kv grade, 70 sqmm armoured cable from surface to 18R/-4AL with the help of MUV and laying it from 8R/-29L to -12R/-31L,\n4)Laying of pull cord and audio cable throughout the belt line of 128 mtr. fitting of lockout and communication devices along the belt\n5)Establishing of G.I. wire signalling system,\n6)Fitting of dust collectorat the Tail End and fenching of all moving drums | BI01010001010000000000000515BI0100001118 | 1 | Work |
|---|
| 8 | 1.07 | Civil foundation for Drive head and discharge, platform for VCB and starter at -4AL in between 18R and 17 R\nRecess cutting in hard stone- 5.3633 cum,\nP/Laying cement concrete 1:1.5:3 in foundation mannual mixing - 6.1980 cum\nProvinding & laying PCC work 1:3:6 for foundation & plinth Manual Mixing - 2.6685 cum\nBrick work with fly ash bricks 1:6 in foundation - 2.0000 cum\n12mm th. Cement Plaster (1:6) - 9.0000 sqm\nLoading Materials (Stone aggregate and sand) into MUV and unloading at UG - 12.5771 cum\nLoading materials (Cement) into MUV and unloading at UG - 1.9171 Cum\nLoading Materials (bricks) into MUV and unloading at UG - 888.00 nos\n | BI01010001010000000000000515BI0100001119 | 1 | Work |
|---|
| 9 | 1.08 | Supply of M.S nuts and bolts (M16X40) | BI01010001010000000000000515BI0100001120 | 86 | kg |
|---|
| 10 | 1.09 | Supply of G.I wire 8 SWG | BI01010001010000000000000515BI0100001121 | 26.37 | kg |
|---|
| 11 | 1.1 | Supply of Bobbin insulator | BI01010001010000000000000515BI0100001122 | 30 | Nos |
|---|
| 12 | 1.11 | Supply of M.S nuts and bolts (3/8\" x 3\") with washer | BI01010001010000000000000515BI0100001123 | 3.75 | kg |
|---|
| 13 | 1.12 | Trial Run | BI01010001010000000000000515BI0100001124 | 1 | Work |
|---|
| 14 | 2 | Total impact of GST for the purpose of CTC | BI01010001010000000000000515BI0100001125 | 1 | Nos |
|---|