Pkg Iii Construction Of 30Mtr Span Steel Bridge Over Bee Kyong In North Sikkim, North Sikkim-Sikkim

Pradhan Mantri Gram Sadak Yojana-PMGSY has published Pkg Iii Construction Of 30Mtr Span Steel Bridge Over Bee Kyong In North Sikkim. Submission Date for this Tender is 06-07-2021. Bridge Work Tenders in North Sikkim Sikkim. Bidders can get complete Tender details and download the document.




Tender Notice

27822880
Corrigendum : Pkg Iii Construction Of 30Mtr Span Steel Bridge Over Bee Kyong In North Sikkim
Open Tender
Indian
Sikkim
North Sikkim
06-07-2021

Tender Details

Pkg Iii Construction Of 30Mtr Span Steel Bridge Over Bee Kyong In North Sikkim

Corrigendum Details

Sr No CorrigendumDate Corrignedum CorrigendumType NewSubmissionDate
1 03-Jun-2021 Postponement of E-Tender Date 25-06-2021
2 14-Jun-2021 POSTPONMENT Date 06-07-2021

Key Value

Document Fees
INR 30000 /-
EMD
INR 686708.0 /-
Tender Value
INR 2.74 Crore /-

BOQ Items

Name of Work:L038-NAMPATAM TO PUNJUKYONG, 30mtr span Steel Bridge over Bee Kyong in North Sikkim
Sl. No. Item Description Item Code / Make Quantity Units
1 1.1 30 Mtr Bee Kyong BI01010001010000000000000515BI0100001702
2 1.2 (ii) Excavation in Hilly Areas in Soil by mechanical means. BI01010001010000000000000515BI0100001703
3 1.3 (A) Excavation in soil in Hilly Area by mechanical means including cutting and trimming of side slopes and disposing of excavated earth with a lift upto 1.5 m and a lead upto 20 m as per drawing and Technical Specification Clause 1603.1 BI01010001010000000000000515BI0100001704 2100 Cum
4 1.4 Construction of Embankment with material obtained from Roadway cutting BI01010001010000000000000515BI0100001705
5 1.5 Construction of Embankment with approved material deposite at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical specification Clause 301.5 BI01010001010000000000000515BI0100001706 180 Cum
6 1.6 Compacting Original Ground. BI01010001010000000000000515BI0100001707
7 1.7 (ii) Compacting original ground supporting subgrade. BI01010001010000000000000515BI0100001708
8 1.8 Loosening of the ground upto a level of 300 mm below the subgrade level, watered, graded and compacted in layers for subgrade construction as per Technical Specification Clause 303.5.2. BI01010001010000000000000515BI0100001709 600 Sqm
9 1.9 Granular Sub-Base with well graded material (Table 400.1) BI01010001010000000000000515BI0100001710
10 2 (A) By Mix in Place Method. BI01010001010000000000000515BI0100001711
11 2.1 Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix-in-place method with rotavator at OMC, and compacting with smooth wheeled roller to achieve the desired density, complete as per technical specification clause 401. BI01010001010000000000000515BI0100001712
12 2.2 (i) For Grading I Material. BI01010001010000000000000515BI0100001713 75 Cum
13 2.3 Water Bound Macadam with Crushable Screenings BI01010001010000000000000515BI0100001714
14 2.4 (2) WBM Grading 2 BI01010001010000000000000515BI0100001715
15 2.5 Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405. BI01010001010000000000000515BI0100001716
16 2.6 (A) By manual means. BI01010001010000000000000515BI0100001717 45 Cum
17 2.7 (3) WBM Grading 3 BI01010001010000000000000515BI0100001718
18 2.8 Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. BI01010001010000000000000515BI0100001719
19 2.9 (A) By manual means. BI01010001010000000000000515BI0100001720 45 Cum
20 3 Prime Coat BI01010001010000000000000515BI0100001721
21 3.1 (i) Low porosity BI01010001010000000000000515BI0100001722
22 3.2 Providing and applying primer coat with Bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 1.2-1.5 kg/sqm using mechanical means as per Technical Specification Clause 502. BI01010001010000000000000515BI0100001723 462.5 Sqm
23 3.3 Tack Coat BI01010001010000000000000515BI0100001724
24 3.4 (iii) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surface treated with primer and cleaned with Hydraulic broom as per Technical Specification Clause 503. BI01010001010000000000000515BI0100001725 462.5 Sqm
25 3.5 20mm thick Open-Graded Premix Carpet BI01010001010000000000000515BI0100001726
26 3.6 20 mm thick Open Graded Premix Carpet using Bitumen Emulsion as per Technical Specification Clause 508.2 BI01010001010000000000000515BI0100001727
27 3.7 By Manual Means BI01010001010000000000000515BI0100001728 462.5 Sqm
28 3.8 Seal Coat BI01010001010000000000000515BI0100001729
29 3.9 Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510 BI01010001010000000000000515BI0100001730
30 4 Type B(ii) Bitumen (S-65) BI01010001010000000000000515BI0100001731 462.5 Sqm
31 4.1 Construction of earthen shoulder. BI01010001010000000000000515BI0100001732
32 4.2 Construction of subgrade and earthen shoulder with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compavted to meet requirement of table 300.2 with lead upto 1000m as per technical specification clause 303.1. BI01010001010000000000000515BI0100001733 45.375 Cum
33 4.3 Loading and unloading of Lime, Aggregates, Stone boulder,Brick Aggregates etc. by manual means BI01010001010000000000000515BI0100001734
34 4.4 i) Loading of aggregates BI01010001010000000000000515BI0100001735 211.439 Cum
35 4.5 ii) Loading of sand BI01010001010000000000000515BI0100001736 31.525 Cum
36 4.6 Loading and unloading of Lime, Aggregates, Stone boulder,Brick Aggregates etc. by Mechanical means BI01010001010000000000000515BI0100001737
37 4.7 iii) Unloading of aggregates BI01010001010000000000000515BI0100001738 211.439 Cum
38 4.8 iii) Unloading of sand BI01010001010000000000000515BI0100001739 31.525 Cum
39 4.9 Loading and unloading of Bitumen drums by manual means including a lead upto 30m BI01010001010000000000000515BI0100001740
40 5 i) Loading of Bitumen drums by manual means including a lead upto 30m BI01010001010000000000000515BI0100001741 2.074 ton
41 5.1 ii) Unloading of Bitumen drums by manual means including a lead upto 30m BI01010001010000000000000515BI0100001742 2.074 ton
42 5.2 Haulage excluding Loading and Unloading BI01010001010000000000000515BI0100001743
43 5.3 Haulage of materials by tipper excluding cost of loading, unloading and stacking BI01010001010000000000000515BI0100001744
44 5.4 Case-I : Surfaced road BI01010001010000000000000515BI0100001745
45 5.5 a) Sand lead distance 90 Km BI01010001010000000000000515BI0100001746 5220 T/Km
46 5.6 b) Aggregates ad distance 90 Km BI01010001010000000000000515BI0100001747 33120 T/Km
47 5.7 c) Bitumen ad distance 170 Km BI01010001010000000000000515BI0100001748 352.621 T/Km
48 5.8 Case-III : Katcha Track BI01010001010000000000000515BI0100001749
49 5.9 a) Sand lead distance 15 Km BI01010001010000000000000515BI0100001750 870 T/Km
50 6 b) Aggregates lead distance 15 Km BI01010001010000000000000515BI0100001751 5520 T/Km
51 6.1 c) Bitumen lead distance 0.0 Km BI01010001010000000000000515BI0100001752
52 6.2 Earthwork in excavation for structures as per drawing and technical Specification Clause 305.1. including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50m, dressing of sides and bottom and back filling in trenches with excavated suitable material. BI01010001010000000000000515BI0100001753
53 6.3 I. Ordinary soil (upto 3m depth) BI01010001010000000000000515BI0100001754 380.85 Cum
54 6.4 Providing concrete for plain/reinforced concrete in open foundation complete as per drawing and technical specification clause 802, 803, 1202 & 1203. BI01010001010000000000000515BI0100001755
55 6.5 I. Pcc grade M10 Nominal mix 1 : 3 : 6 (hand mixing) BI01010001010000000000000515BI0100001756 38.154 Cum
56 6.6 Stone masonry in cement mortar for substructure complete as per drawing & technical specification Clauses 702, 704, 1202 and 1204 BI01010001010000000000000515BI0100001757
57 6.7 II. Course rubble masonry (2nd sort) BI01010001010000000000000515BI0100001758 691.6 Cum
58 6.8 Providing and laying filter media with granular crush aggregates as per specification to a thickness of not less than 600mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind retaining wall to the full height compacted to firm condition complete as per drawing and technical specification clause 1204.3.8 BI01010001010000000000000515BI0100001759 344.4 Cum
59 6.9 Stone masonry in cement mortar 1:3 for parapet complete as per drawing and technical specifications Clauses 700 and 1208.4 BI01010001010000000000000515BI0100001760
60 7 I. Random rubble masonry BI01010001010000000000000515BI0100001761 10.16 Cum
61 7.1 Plastering with cement mortar ( 1:4) 15mm thick on Brick/Stone works as per drawing and technical specification clauses 613.4 and 1204 BI01010001010000000000000515BI0100001762 100.24 Sqm
62 7.2 Providing PCC M20 architectural coping on the top of retaining wall complete as per drawing and technical specification clause 615,710 and 1204.3.11 BI01010001010000000000000515BI0100001763 78 Rm
63 7.3 Loading and unloading by manual means BI01010001010000000000000515BI0100001764
64 7.4 i) Loading of masonry stone BI01010001010000000000000515BI0100001765 814.26 m3
65 7.5 i) Loading of aggregates BI01010001010000000000000515BI0100001766 453.74 m3
66 7.6 ii) Loading of sand BI01010001010000000000000515BI0100001767 266.18 m3
67 7.7 Loading and unloading by Mechanical means BI01010001010000000000000515BI0100001768
68 7.8 iii) Unloading of masonry stone BI01010001010000000000000515BI0100001769 814.26 m3
69 7.9 iii) Unloading of aggregates BI01010001010000000000000515BI0100001770 453.74 m3
70 8 iii) Unloading of sand BI01010001010000000000000515BI0100001771 266.18 m3
71 8.1 Loading and unloading of cement by manual means BI01010001010000000000000515BI0100001772
72 8.2 i) Loading of cement BI01010001010000000000000515BI0100001773 130 ton
73 8.3 ii) Unloading of cement BI01010001010000000000000515BI0100001774 130 ton
74 8.4 Haulage of materials by tipper excluding cost of loading, unloading and stacking BI01010001010000000000000515BI0100001775
75 8.5 Case-I : Surfaced road BI01010001010000000000000515BI0100001776
76 8.6 a) Sand lead distance 90 Km BI01010001010000000000000515BI0100001777 46440 T/Km
77 8.7 b) Aggregates lead distance 90 Km BI01010001010000000000000515BI0100001778 71280 T/Km
78 8.8 c) Cement lead distance 30 Km BI01010001010000000000000515BI0100001779 3900 T/Km
79 8.9 d) Masonry stone lead distance 30 Km BI01010001010000000000000515BI0100001780 41640 T/Km
80 9 Case-III : Katcha Track BI01010001010000000000000515BI0100001781
81 9.1 a) Sand lead distance 15 Km BI01010001010000000000000515BI0100001782 7740 T/Km
82 9.2 b) Aggregates lead distance 15 Km BI01010001010000000000000515BI0100001783 11880 T/Km
83 9.3 c) Cement lead distance 0.0 Km BI01010001010000000000000515BI0100001784
84 9.4 d) Masonry stone lead distance 4.0Km BI01010001010000000000000515BI0100001785 5552 T/Km
85 9.5 Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps ,Dewatering,Shoring and shuttering and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material. BI01010001010000000000000515BI0100001786
86 9.6 Ordinary soil BI01010001010000000000000515BI0100001787
87 9.7 Upto 3 m depth BI01010001010000000000000515BI0100001788 932.088 cum
88 9.8 3 m to 6 m depth BI01010001010000000000000515BI0100001789 355.404 cum
89 9.9 Ordinary rock BI01010001010000000000000515BI0100001790 621.392 cum
90 10 Hard rock (requiring blasting) BI01010001010000000000000515BI0100001791 236.936 cum
91 10.1 Hard rock (blasting prohibited) BI01010001010000000000000515BI0100001792
92 10.2 Filling annular space around footing in rock as per technical specification Clause 1203.4.3. BI01010001010000000000000515BI0100001793
93 10.3 P.C.C grade M 15 (Nominal mix 1:2.5:5) BI01010001010000000000000515BI0100001794 29.92 cum
94 10.4 Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 BI01010001010000000000000515BI0100001795
95 10.5 P.C.C grade M 15 BI01010001010000000000000515BI0100001796
96 10.6 Nominal mix (1:2.5:5) BI01010001010000000000000515BI0100001797 16.728 cum
97 10.7 R.C.C. grade M 30 BI01010001010000000000000515BI0100001798 102.7 cum
98 10.8 Supplying, fitting and placingTMT bar reinforcement in foundation complete as per drawings and technical specifications Clauses 1000 and 1202 BI01010001010000000000000515BI0100001799 27.479 MT
99 10.9 Sub Structure BI01010001010000000000000515BI0100001800
100 11 Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204 BI01010001010000000000000515BI0100001801
101 11.1 For height upto 5 m BI01010001010000000000000515BI0100001802
102 11.2 R.C.C. grade M30 BI01010001010000000000000515BI0100001803 87.146 cum
103 11.3 For height 5 to 10 m BI01010001010000000000000515BI0100001804 65.359 cum
104 11.4 For height above 10 m BI01010001010000000000000515BI0100001805 65.359 cum
105 11.5 Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 BI01010001010000000000000515BI0100001806 39.216 MT
106 11.6 Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7 BI01010001010000000000000515BI0100001807 152 Nos.
107 11.7 Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 BI01010001010000000000000515BI0100001808
108 11.8 Granular material BI01010001010000000000000515BI0100001809 598.689 cum
109 11.9 Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8 BI01010001010000000000000515BI0100001810 76.527 cum
110 12 Supplying, fitting and fixing in position true to line and level sliding plate bearing with PTFE surface sliding on stainless steel complete including all accessories as per drawing and Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications. BI01010001010000000000000515BI0100001811 620 tonne capacit
111 12.1 Supplying, fitting and fixing in position true to line and level elastomeric bearing conforming to IRC:83 (Part-II) Section IX complete, including all accessories as per drawings and technical specification Clause 1207.1 BI01010001010000000000000515BI0100001812 20480 cucm
112 12.2 Super Structure BI01010001010000000000000515BI0100001813
113 12.3 Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5 BI01010001010000000000000515BI0100001814
114 12.4 R.C.C. Grade M 30 BI01010001010000000000000515BI0100001815 68.832 Cum
115 12.5 Supplying, fitting, and placing TMT bar reinforcement in superstructure complete as per drawing and technical specifications Clauses 1002, 1010 and 1202 BI01010001010000000000000515BI0100001816 8.604 MT
116 12.6 Providing steel R.S.Js/ built-up steel sections including cutting, welding/rivetting, hoisting, fixing in position for composite girders with shear connectors complete with painting as per drawing and technical specifications clause 1205.6 BI01010001010000000000000515BI0100001817 51.803 MT
117 12.7 Drainage spouts complete as per drawing and technical specifications Clause 1209 BI01010001010000000000000515BI0100001818 12 Nos.
118 12.8 P.C.C. M 15 ordinary grade (1:2.5:5) levelling course below approach slab complete as per drawing and technical specifications Clauses 800 and 1211 BI01010001010000000000000515BI0100001819
119 12.9 Nominal mix (1:2.5:5) BI01010001010000000000000515BI0100001820 3.833 cum
120 13 Reinforced Cement Concrete M 25 grade approach slab including reinforcement and formwork complete as per drawing and technical specifications Clauses 800 and 1211 BI01010001010000000000000515BI0100001821 12.18 cum
121 13.1 Providing and laying of an elastomeric slab seal expansion joint complete as per approved drawing and approved specifications to be installed by manufacturer/supplier or their authorised representative ensuring compliance to the manufacturer’s instructions for installlation and as per technical specifications Clause 1207.2.5 BI01010001010000000000000515BI0100001822 13 Rm
122 13.2 Filler Joint BI01010001010000000000000515BI0100001823
123 13.3 Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans, covered with sealant complete as per drawing and technical specifications BI01010001010000000000000515BI0100001824 11.6 Rm
124 13.4 Providing and laying bituminous macadam with hot mix plant using crushed aggregates of grading as per Table 500.4 premixed with bituminous binder, transported to site upto a lead of 1000 m laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled to achieve the desired compaction as per Technical Specification Clause 504. BI01010001010000000000000515BI0100001825 11.275 cum
125 13.5 Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clause 508. BI01010001010000000000000515BI0100001826
126 13.6 (i) Bitumen (S-90) BI01010001010000000000000515BI0100001827 225.5 Sqm
127 13.7 Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per Technical Specification Clause 510 BI01010001010000000000000515BI0100001828
128 13.8 By Manual Means BI01010001010000000000000515BI0100001829
129 13.9 Case - II : Type B BI01010001010000000000000515BI0100001830
130 14 (I) Bitumen (S-90) BI01010001010000000000000515BI0100001831 225.5 Sqm
131 14.1 River Bank Protection Work BI01010001010000000000000515BI0100001832
132 14.2 Providing and laying of boulder apron laid in wire crates with 4 mm dia GI wire conforming to IS:280 and IS:4826 in 100 mm x 100 mm mesh (woven diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 25 kg each as per drawing and technical specifications Clause 1301 BI01010001010000000000000515BI0100001833
133 14.3 For 2 m height of Gabion toe wall for Length of 20 m on both side of abutment wall BI01010001010000000000000515BI0100001834 180 Cum
134 14.4 Launching & Erection of superstructure as guide line of IRC -87-2018,IRC-22-2015 and IRC-24-2010 and Technical specification MoRT&H BI01010001010000000000000515BI0100001835 1 Nos.
135 14.5 Load Carrying capacity of bridge as guide line of IRC SP 037-2010 BI01010001010000000000000515BI0100001836 1 Nos.
136 14.6 Loading of stone aggregates BI01010001010000000000000515BI0100001837
137 14.7 M15 grade concrete BI01010001010000000000000515BI0100001838 40.384 Cum
138 14.8 M25 grade concrete BI01010001010000000000000515BI0100001839 10.962 Cum
139 14.9 M30 grade concrete BI01010001010000000000000515BI0100001840 350.456 Cum
140 15 Bituminous Macadam BI01010001010000000000000515BI0100001841 12.763 Cum
141 15.1 Premix carpet BI01010001010000000000000515BI0100001842 6.089 Cum
142 15.2 Seal coat BI01010001010000000000000515BI0100001843 1.353 Cum
143 15.3 Unloading of stone aggregates BI01010001010000000000000515BI0100001844
144 15.4 M15 grade concrete BI01010001010000000000000515BI0100001845 40.384 Cum
145 15.5 M25 grade concrete BI01010001010000000000000515BI0100001846 10.962 Cum
146 15.6 M30 grade concrete BI01010001010000000000000515BI0100001847 350.456 Cum
147 15.7 Bituminous Macadam BI01010001010000000000000515BI0100001848 12.763 Cum
148 15.8 Premix carpet BI01010001010000000000000515BI0100001849 6.089 Cum
149 15.9 Seal coat BI01010001010000000000000515BI0100001850
150 16 Loading of sand BI01010001010000000000000515BI0100001851
151 16.1 M15 grade concrete BI01010001010000000000000515BI0100001852 24.231 Cum
152 16.2 M25 grade concrete BI01010001010000000000000515BI0100001853 5.481 Cum
153 16.3 M30 grade concrete BI01010001010000000000000515BI0100001854 175.228 Cum
154 16.4 Bituminous Macadam BI01010001010000000000000515BI0100001855 3.191 Cum
155 16.5 Seal coat BI01010001010000000000000515BI0100001856 1.353 Cum
156 16.6 Unloading of sand BI01010001010000000000000515BI0100001857
157 16.7 M15 grade concrete BI01010001010000000000000515BI0100001858 24.231 Cum
158 16.8 M25 grade concrete BI01010001010000000000000515BI0100001859 5.481 Cum
159 16.9 M30 grade concrete BI01010001010000000000000515BI0100001860 175.228 Cum
160 17 Bituminous Macadam BI01010001010000000000000515BI0100001861 3.191 Cum
161 17.1 Seal coat BI01010001010000000000000515BI0100001862
162 17.2 Loading of cement and stacking BI01010001010000000000000515BI0100001863
163 17.3 M15 grade concrete BI01010001010000000000000515BI0100001864 13.882 MT
164 17.4 M25 grade concrete BI01010001010000000000000515BI0100001865 4.921 MT
165 17.5 M30 grade concrete BI01010001010000000000000515BI0100001866 167.44 MT
166 17.6 Unloading of cement and stacking BI01010001010000000000000515BI0100001867
167 17.7 M15 grade concrete BI01010001010000000000000515BI0100001868 16.154 MT
168 17.8 M25 grade concrete BI01010001010000000000000515BI0100001869 7.43 MT
169 17.9 M30 grade concrete BI01010001010000000000000515BI0100001870 276.471 MT
170 18 Loading steel and stacking BI01010001010000000000000515BI0100001871 79.064 MT
171 18.1 Unloading steel and stacking BI01010001010000000000000515BI0100001872 79.064 MT
172 18.2 Loading Bitumen Drums and stacking BI01010001010000000000000515BI0100001873
173 18.3 Bituminous Macadam BI01010001010000000000000515BI0100001874 0.812 MT
174 18.4 Premix carpet BI01010001010000000000000515BI0100001875 0.329 MT
175 18.5 Seal coat BI01010001010000000000000515BI0100001876 0.153 MT
176 18.6 Unloading Bitumen Drums and stacking BI01010001010000000000000515BI0100001877
177 18.7 Bituminous Macadam BI01010001010000000000000515BI0100001878 0.812 MT
178 18.8 Premix carpet BI01010001010000000000000515BI0100001879 0.329 MT
179 18.9 Seal coat BI01010001010000000000000515BI0100001880 0.153 MT
180 19 Cost of Haulage Excluding Loading and Unloading BI01010001010000000000000515BI0100001881
181 19.1 Surfaced Road BI01010001010000000000000515BI0100001882
182 19.2 a) Cement lead distance 30 Km BI01010001010000000000000515BI0100001883 5587.3 T.km
183 19.3 b) Stone Aggregates lead distance 90 Km BI01010001010000000000000515BI0100001884 37980.7 T.km
184 19.4 c) Sand lead distance 90 Km BI01010001010000000000000515BI0100001885 18853.5 T.km
185 19.5 d) Steel lead distance 30 Km BI01010001010000000000000515BI0100001886 2371.91 T.km
186 19.6 e) Bitumen lead distance 170 Km BI01010001010000000000000515BI0100001887 220.043 T.km
187 19.7 Unsurface road BI01010001010000000000000515BI0100001888
188 19.8 a) Cement lead distance 0.0 Km BI01010001010000000000000515BI0100001889
189 19.9 b) Stone Aggregates lead distance 15 Km BI01010001010000000000000515BI0100001890 1311.82 T.km
190 20 c) Sand lead distance 15 Km BI01010001010000000000000515BI0100001891 820.041 T.km
191 20.1 d) Steel lead distance 0.0 Km BI01010001010000000000000515BI0100001892
192 20.2 e) Bitumen lead distance 0.0 Km BI01010001010000000000000515BI0100001893
193 20.3 12 % GST on Civil works BI01010001010000000000000515BI0100001894 1 Percentage
194 20.4 1 % labour Cess BI01010001010000000000000515BI0100001895 1 Percentage
195 20.5 18 % GST on Steel parts BI01010001010000000000000515BI0100001896 1 Percentage
196 20.6 1 % labour Cess BI01010001010000000000000515BI0100001897 1 Percentage
197 20.7 Brick work in C.M 1:5 mix including all labour charges etc complete BI01010001010000000000000515BI0100001113 1 Nos
198 20.8 Brick work in C.M 1:5 mix using 2nd class ground moulded chamber burnt bricks with including cost and conveyance of all materials and including all labour charges etc complete BI01010001010000000000000515BI0100001114 25 Nos
199 20.9 Plastering in C.M 1:5-12 mm thick with including cost and conveyance of all materials and including all labour charges etc complete BI01010001010000000000000515BI0100001115 20 Nos
200 21 Plastering in C.M 1:5-12 mm thick with including cost and conveyance of all materials and in BI01010001010000000000000515BI0100001116 1 Nos
201 21.1 b) CI bend 22.5° (250mm dia) BI01010001010000000000000515BI0100001117 1.565 Nos
202 21.2 Construction of chamber for 100mm sluice plates BI01010001010000000000000515BI0100001118 1 Nos
203 21.3 Construction of chamber for 100mm sluices valve BI01010001010000000000000515BI0100001119 1 Nos
204 21.4 Supplying, Conveying and fixing spls. Including ea BI01010001010000000000000515BI0100001120 1 Nos
205 21.5 Supplying, Conveying and fixing spls. Including eart BI01010001010000000000000515BI0100001121 1 Nos
206 21.6 Construction of chamber for 100mm sluice plates BI01010001010000000000000515BI0100001122 1 Nos
207 21.7 Construction of chamber for 100mm sluices valve BI01010001010000000000000515BI0100001123 1 Nos
208 21.8 Laying and Jointing PVC Pipe. Heading BI01010001010000000000000515BI0100001124
209 21.9 Plain Cement Concrete 1:4:8 (one cement four fine aggregates and eight coarse aggregates) using BI01010001010000000000000515BI0100001125 1 Nos
210 22 Brick work in C.M 1:5 mix using 2nd class ground moulded chamber burnt bricks with including cost BI01010001010000000000000515BI0100001126 1 Nos
211 22.1 Construction of chamber for 100mm sluices valve BI01010001010000000000000515BI0100001127 1 Nos
212 22.2 The Total value of Schedule1 BI01010001010000000000000515BI0100001128 1 Nos
213 22.3 The Total value of Schedule4 BI01010001010000000000000515BI0100001129 1 Nos
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail