| 1 | 1 | PROJECT INITIATION ACTIVITIES:\nCarrying out all project initiation activities as per below defined scope of work for all 04 POL locations of OSO (i.e Paradip, Jharsuguda, Bhubaneswar & Balasore) as per direction of Engg-In-Charge.\n | 1 | | |
|---|
| 2 | 2 | i.\tSite visit to all POL locations to understand the existing facilities for planning and positioning of STP units due discussion with POL location officials/Engineering officials.\nii.\tUnderstanding the concept of the project from IOCL and reviewing the existing site parameters and IOCL requirements to oversee the entire project’s budget and finalize the location plan including required site survey etc all complete.\niii.\tSubmission of detail report including all statutory requirements (If any) in detail for hassle free completion of the project.\n | 2 | 4 | EA |
|---|
| 3 | 3 | Liasioning work on the basis of man-day visits to statutory offices if required as per statutory requirement and direction of Engg-in-Charge of IOCL | 3 | 12 | Man day |
|---|
| 4 | 4 | i.Complete design of the Sewerage Treatment Plants in line with requirement based on number of users (w.r.t footfall requirement/actual requirement after joint discussion) at administrative office and TT parking area considering nature of sewage quality and all details mentioned in tender/ to be discussed after tender as per IOCL requirements and guidelines.\nii.Submission of detail design report (03 sets) for IOCL approval | 4 | 4 | EA |
|---|
| 5 | 5 | PROJECT PLANNING ACTIVITIES:\nCarrying out all project planning activities as per below defined scope of work for all 04 POL locations of OSO (i.e Paradip,Jharsuguda,Bhubaneswar & Balasore) as per direction of Enng-in-Charge of IOCL. | 5 | | |
|---|
| 6 | 6 | i) \tDefining various scope of work in detail after designing the entire Sewerage Treatment Plant (STP) for all associated items i.e Civil, Mechanical, Electrical, Automation, other works (if any).\nii) \tPreparation of all drawings i.e architectural, tender drawings, construction drawings, statutory application drawings (if any), as built drawings etc..(03 sets) as per IOCL requirement \niii) \tPreparation of detailed Technical estimates for the above works and associated works (If any).\niv) \tPreparation of BOQ, Technical specifications, List approved brands/Makes for materials & equipment’s to incorporate in the tender documents.\nv)\tThe consultant shall forecast and prepare BOQs considering every scope of work and applying their practical experience in such a manner that, generation of extra items in future is eliminated.\nvi)\tConsultant also to prepare location wise realistic completion time for work completion to incorporate in the tender.\n | 6 | | |
|---|
| 7 | 7 | vii. Preparation of the entire tender package (Full/in phases) due discussion with IOCL.\nviii) Under each tender package, the Consultant shall be requed to :\n• Develop detailed technical specifications for the items involved including data sheet of all equipment etc.\n• Calculate quantities for items and submit quantity take off sheets.\n• Submit and obtain approval of IOC for list of approved makes (minimum 03 nos.) for various items to be incorporated in tender documents. Decision of IOCL in this regard shall be final.\n• Prepare rates for each of the items to be included based on rate analysis. May refer rates from DSR, IOCL SOR etc.\n• The rate analysis shall be based on market rates where at least 03 (three) market quotations for all major items need to be obtained and furnished for back up.\nix) To clarify all technical queries during tendering stage if raised in pre bid meetings. | 7 | 4 | EA |
|---|
| 8 | 8 | PROJECT IMPLEMENTATION ACTIVITIES\nCarrying out all project implementation activities as per below defined scope of work for all 04 POL locations of OSO (i.e Paradip,Jharsuguda,Bhubaneswar & Balasore) as per direction of Engg-in-Charge of IOCL. | 8 | | |
|---|
| 9 | 9 | i. Ensurings periodical site visits after intimation of IOCL, minimum 07 days before to overview the construction works as per specifications, drawings etc.\nii.To check the quality and workmanship parameters and suggest corrective action for quality and smooth completion of the work with proper workmanship.\n | 9 | 16 | Man day |
|---|
| 10 | 10 | PROJECT CLOSER ACTIVITIES\nCarrying out all project closer activities as per below defined scope of work for all 04 POL locations of OSO (i.e Paradip,Jharsuguda,Bhubaneswar & Balasore) as direction of officer I/c. | 10 | | |
|---|
| 11 | 11 | a) \tTo provide assistance at vsite for commissioning and handing over of the project.\nb) \tTechnical assistance for answering any audit / Vigilance / CTE which may arise with regard to any aspect of the work. \nc) \tSubmission of (03 sets) as built drawings after completion of work. | 11 | 4 | EA |
|---|