South Eastern Coalfields Limited-SECL has published Laying And Jointing , Diversion / Re-Arrangement Of Ms Pipelines For Dewatering Activities At Old Dipka Quarry During Up-Coming Monsoon Including Installation And Shifting Of Pump Sets Etc . At Dipka Expansion Project . . Submission Date for this Tender is 27-04-2021. Submersible Pump Tenders in Dipka Expansion Project, Dipka Area Chhattisgarh. Bidders can get complete Tender details and download the document.
Name of the Work / Contract No: | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Laying /jointing of MS pipeline along Hardi Bazar Road / Mine boundary for dewatering at Old Dipka Quarry or any other suitable location as per requirement of Dipka Expansion Project. | |||
2 | 1.01 | Laying & jointing of MS pipe line etc. complete, Size - 250mm. | BI01010001010000000000000515BI0100001113 | 3000 | Mtr. |
3 | 1.02 | Making of bend for 10" dia MS pipe. | BI01010001010000000000000515BI0100001114 | 6 | No. |
4 | 1.03 | Fixing of 250mm Size Non-Return Valves. | BI01010001010000000000000515BI0100001117 | 4 | No. |
5 | 2 | Extension, re-arrangement / diversion, shifting, laying/ jointing of MS pipeline & installation of pump set for dewatering activities at Old Dipka Sump of Dipka Expansion Project. | |||
6 | 2.01 | Dismantling of MS pipe line size - 200mm dia. | BI01010001010000000000000515BI0100001118 | 1000 | Mtr. |
7 | 2.02 | Dismantling of MS pipe line size - 250mm dia. | 1000 | Mtr. | |
8 | 2.03 | Laying & jointing of MS pipe line etc. complete, Size - 200mm. | 1000 | Mtr. | |
9 | 2.04 | Laying & jointing of MS pipe line etc. complete, Size - 250mm. | BI01010001010000000000000515BI0100001119 | 1000 | Mtr. |
10 | 2.05 | Installation /shifting and re-installation of the pump motor base plate, starter, power cable, section / delivery valves etc. complete set. | BI01010001010000000000000515BI0100001120 | 15 | Set |
11 | 2.06 | P & F of MS nut bolt 5/8" x 3" or 4" as per required size. | BI01010001010000000000000515BI0100001123 | 200 | Kg |
12 | 2.07 | Making of bend for 8" dia MS pipe. | 4 | No. | |
13 | 2.08 | Making of bend for 10" dia MS pipe. | 4 | No. | |
14 | 2.09 | Fixing of 200mm Size Non-Return Valves. | 2 | No. | |
15 | 2.1 | Fixing of 250mm Size Non-Return Valves. | 2 | No. | |
16 | 3 | Note: 1). Welding electrodes, industrial gases, welding m/c and other tools & tackles will be provided by the contractor. 2). Electric power shall be provided by Deptt. at one point only. 3). If required, truck will be provided by department for transporting of pipe from R/Store / Workshop to working site at one point. 4). Rates are inclusive of CMPF, Pension, Contractor's Profit & other overhead expenses etc. excluding GST. | |||
17 | 4 | Total impact of GST for the purpose of CTC | BI01010001010000000000000515BI0100001129 | 1 | Nos |