| 1 | 1 | Survey including preparation of final tower schedule of material ,marking of locations etc. | | 1 | Job |
|---|
| 2 | 2 | Check Survey and final peg marking (Route Length) | | 1 | Job |
|---|
| 3 | 3 | Cost of Excavation of 220 KV D/C KPTL Tower foundation pits including all earth work, back filling and leveling. | | 237.5 | Cum |
|---|
| 4 | 4 | Cost of Concreting for 220 KV D/C Tower foundation including cost of cement, dewatering, shuttering & curing but excluding cost of reinforcement bars. | | 62.5 | Cum |
|---|
| 5 | 5 | Cost of Setting of Stubs including all foundation work but excluding cost of concreting and excavation (Rate per location) for 220 KV KPTL DC Tower. | | 1 | No. |
|---|
| 6 | 6 | Erection of 220KV KPTL D/C Super Structure of towers and their extensions where ever required including all work above ground level excluding hoisting of insulators and hardware. | | 11.3 | MT |
|---|
| 7 | 7 | Tack welding of all the bolts at first section of DC towers. | | 1 | Job |
|---|
| 8 | 8 | Installation of Back stay. | | 6 | Job |
|---|
| 9 | 9 | Safe dismantling of Old 220KV S/C distorted tower by cutting the tower with the help of gas cutter, etc. | | 1 | Job |
|---|
| 10 | 10 | Destringing of 220 KV S/C ACSR Zebra conductor. | | 2 | Span |
|---|
| 11 | 11 | Destringing of earthwire. | | 2 | Span |
|---|
| 12 | 12 | Laying , tensioning, Stringing, clamping, jointing etc complete with ACSR Zebra conductor DC/SC including hoisting of insulators, fitting of all necessary hardware & accessories etc. | | 2 | Span |
|---|
| 13 | 13 | Laying , tensioning, Stringing, clamping, jointing etc complete with ground wire including hoisting of all necessary hardware & accessories for 1 no. 7/3.25 mm G.S. earthwire. | | 2 | Span |
|---|
| 14 | 14 | Grounding Work including earth work for pipe type earthing. | | 2 | No. |
|---|
| 15 | 15 | Installation of Steel Reinforcement bars in RCC foundation including cost of Steel Reinforcement bars with cutting , bending, placing, binding etc. | | 0.2 | MT |
|---|
| 16 | 16 | Excavation of earth 1.0 to 1.5 mtr deep around old tower stub in 2 mtr dia and breaking of old foundation & chimney up to 1.5 mtr to 2.0 mtr, cutting old stub by gas cutter collection of broken concrete in gunny begs and its disposal outside of field and back filling and leveling of earth. | | 1 | Job |
|---|
| 17 | 17 | Transportation of complete tower stucture, template, conductor, Earthwire, etc from UPPTCL Store to Site including loading and unloading. | | 1 | Job |
|---|
| 18 | 18 | Transportation of old Tower parts, conductor, earthwire and all accessories from Site to UPPTCL Storeincluding loading and unloading. | | 1 | Job |
|---|
| 19 | 19 | Construction of Machan / providing Crane / Hydra to lift the conductor during stringing work for smooth running of traffic on roads for all the locations | | 1 | No. |
|---|
| 20 | 20 | Providing barricades for avoiding any accident during the period of excavation to backfilling of soil after foundation work & during erection of Tower/Monopoles. | | 1 | No. |
|---|