| 1 | 1 | Providing services inside M.D. office campus for cleaning & sweeping of rooms, removal of cobwebs from rooms and corridors, dusting of furnitures in entire campus, brooming of road, parking & canteen area including bathroom cleaning with phynile etc. The rate shall exclude cost of phynile, bleaching powder, T&P etc. required for proper completion of work or as directed by E/I. | NSI 1 | 12 | Month |
|---|
| 2 | 2 | Providing services in hydel colony for cleaning & brooming of roads, side pattries etc. & collecting the Rubbish/Disposable material from different residences and its disposal at nearest dumping station etc. including all labour and T&P required for proper completion of work or as directed by E/I. | NSI 2 | 12 | Month |
|---|
| 3 | 3 | Clearing jungle including uprooting of rank vegetations,grass, bush, wood, trees and saplings of girth upto 30cm measured at a height of 1.0m above ground level and removal of rubbish upto a distance of 50m outside the periphery of UPPCL area cleared or as directed by E/I. | CSI No. 4.08 | 19920.4 | m2 |
|---|
| 4 | 4 | Cleaning of main drain or width more than 300 mm.including disposal of waste refuses sludge out side the board's area including washing and cleaning by clean water completely as per direction of the Engineer-in-charge including cost of all labour,T&P etc.required for proper completion of the work. | CSI No. 20.14 | 10957.2 | m2 |
|---|
| 5 | 5 | Same as above in item No. 20.14 but for drain of width less than 300 mm. | CSI No. 20.15 | 19814.4 | m2 |
|---|
| 6 | 6 | Disposal of rubbish/debris/garbage etc. including collection and loading at different collection point in Hydel colony/M.D. office/CZE office etc. and there after disposing it at Karsana power plant/ any other suitable places upto a distance of 20km including all labours and T&P etc. required for proper completion of work as directed by E/I. | NSI 3 | 1041.66 | cum |
|---|
| 7 | 7 | Supply of cleaning materials, tools & T&P etc. such as Phenyl, Acid, Washing powder, Dusing broom, Stick broom, Harpic, Cleaning cloth, Wiper, Toilet brush, Phenyl tablet, Odonil, Jhaliya etc. required for proper completion of work as directed by E/I. (For MD Office etc.) | NSI 4 | 12 | Month |
|---|
| 8 | 8 | Supply of cleaning materials, tools & T&P etc. such as Phenyl, Acid, Washing powder, Dusing broom, Stick broom, Harpic, Cleaning cloth, Wiper, Toilet brush, Phenyl tablet, Odonil, Jhaliya etc required for proper completion of work as directed by E/I.(For hydel colony, badminton hall, I.T. Training centre B.N.1,2,3,5&11 etc.) | NSI 5 | 12 | Month |
|---|
| 9 | 9 | Special Terms & Conditions:- | | | |
|---|
| 10 | 9.1 | Complete cleaning and sweeping in entire M.D. office shall be carried out daily from 6:00 am to 6:00 pm by engaging at least four number sweepers including toilet, rooms, corridors, campus etc. cleaning of the M.D. office, campus rooms, corridors, toilet etc. shall be completed up to 9.30 A.M. postively in all working day. Each toilet and corridors shall be cleaned minimum four times in a day and other necessary works shall be completed by the contractor as per direction of E/I. | | | |
|---|
| 11 | 9.2 | The contractor must engage daily at least five number of sweeper from 6.00 A.M. to 6.00 P.M. for cleaning/sweeping sevices in colony area which include cleanling of road and road pattries, outer/common area of the residences, M.D. and Director's residences, badminton hall, I.T. Training centre etc. including collection of garbage from houses etc. and other works as directed by E/I. | | | |
|---|
| 12 | 9.3 | Under special circumstances, it will be responsibility of contractor to engage workers till that time, office is in operation beyond 6.00 pm. | | | |
|---|
| 13 | 9.4 | It will be responsibility of contractor to provide uniform to each and every worker and it will be his responsibility to check that his every worker is well dressed.ra. | | | |
|---|
| 14 | 9.5 | The payment of all cleaning work and disposal of garbage, claning of drains, road etc. shall be done in respective items of the B.O.Q | | | |
|---|
| 15 | 9.6 | If any of contractor's worker is found absent from his work area, Rs. 300 per worker per day will be deducted as penality from the bill. | | | |
|---|
| 16 | 9.7 | If the work area or any of specified areas are found untidy by E/I, it would be his decision to penalise the contractor by deducting his bill. | | | |
|---|
| 17 | 10 | Note-The Rate of All Items is Exclusive of GST, So the contractor quoted rate is treated as GST Extra. | | | |
|---|