| 1 | 1 | Earth work in embankment for widening/filling & raising of embankment in ordinary soil on road including 1.5m lift and 30 mtr lead and also including ramming dressing required to proper completion of work including all labour T&P etc as per S.I. NO. 253 | | 500 | cum |
|---|
| 2 | 2 | Earth work in pataries as per S.I. No. 253 | | 120 | cum |
|---|
| 3 | 3 | Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per clause 401. (Excluding GST) | | 55 | cum |
|---|
| 4 | 4 | Providing, laying, WBM Grade-2 with 45-63mm size Stone Ballast, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled smooth roller 8-10 tonnes in stages to proper grade and camber, applying and brooming, stone screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per clause 405.2 (Including hire charges of road roller) (Excluding GST) | | 98 | cum |
|---|
| 5 | 5 | Providing, laying, WBM Grade-3 with 22.4-53mm size Stone Ballast, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled static roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density. Grading 3 as per clause 405.3 (Including hire charges of road roller) (Excluding GST) | | 98 | cum |
|---|
| 6 | 6 | Providing and applying primer coat with bitumen emulsion on prepared surface of granular Base including cleaning of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means. As per Techinical specfication Clause 502 (Including hire charges of road roller & including Cost of bitumen ) (Excluding GST) | | 1312.5 | sqm |
|---|
| 7 | 7 | Providing and applying tack coat with bitumen (VG-10) using pressure distributor at the rate of 0.35 kg per sqm on the prepared bituminous/granular surface treated with primer & cleaned with hydraulic broom as per Technical Specification Clause 503 (Including hire charges of road roller & including Cost of bitumen ) (Excluding GST) | | 1312.5 | sqm |
|---|
| 8 | 8 | Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades. (Including hire charges of road roller & including Cost of bitumen ) (Excluding GST) | | 1312.5 | sqm |
|---|
| 9 | 9 | Providing and laying seal coat by manual means with VG-10 Grade Bitumen sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C as per Technical Specification Clause 510 (Including hire charges of road roller & including Cost of bitumen ) (Excluding GST) | | 1312.5 | sqm |
|---|
| 10 | 10 | Brick edging 7 cm wide on both sides of the road by M- 150 bricks complete as per PWD detailed specification no 20.15 | | 0.35 | Km |
|---|