Tamil Nadu Generation And Distribution Corporation Limited-TANGEDCO has published Epc Contract Bop Package Including Fgd For 2X800 Mw Ustpp Tender For Design , Manufacture , Supply , Erection , Testing And Commissioning Of Balance Of Plant ( Bop ) Package And Allied Civil Works Related To Bop Including Fgd Package On Epc Basis For E. Submission Date for this Tender is 12-05-2021. Civil Work Tenders in Ramanathapuram District Tamil Nadu. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 10-Mar-2021 | Prebid meeting | Other | 16-04-2021 |
2 | 09-Apr-2021 | Due date extension 1 | Date | 12-05-2021 |
Name of Work:Engineering, Procurement and Construction (EPC) contract for Complete Design, Engineering, Manufacture/procurement, Assembly, Inspection, Testing at Manufacturer’s Works, Packing, Forwarding, Transporting and Insurance, Supply of Complete Machineries (Complete Mechanical, Electrical, Instrumentation & Control Systems and Civil, Structural & Architectural Works and Mandatory Spares at Site), Assembly, Erection, Testing, Commissioning, Trial/ Reliability Run, Conducting Performance Guarantee Tests and Handing over of Balance of Plant and Flue Gas Desulphurisation System and Auxiliaries for 2 x 800MW Uppur Supercritical Thermal Power Project at Uppur, Ramanathapuram Dist., Tamil Nadu. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | SUPPLY OF MAIN EQUIPMENT INCLUDING FACTORY FABRICATED STEEL STRUCTURES FOR BALANCE OF PLANT AND FLUE GAS DESULPHURISATION SYSTEM PACKAGE FOR 2 X 800 MW UPPUR THERMAL POWER PLANT | |||
2 | 1.01 | FGD WITH AUXILARIES | |||
3 | 1.011 | INDIAN COMPONENT | Text1 | 1 | Lot |
4 | 1.012 | FOREIGN COMPONENT | Text2 | 1 | Lot |
5 | 1.02 | COAL HANDLING PLANT | |||
6 | 1.021 | INDIAN COMPONENT | Text3 | 1 | Lot |
7 | 1.022 | FOREIGN COMPONENT | Text4 | 1 | Lot |
8 | 1.03 | ASH HANDLING PLANT | |||
9 | 1.031 | INDIAN COMPONENTS | Text5 | 1 | Lot |
10 | 1.032 | FOREIGN COMPONENTS | Text6 | 1 | Lot |
11 | 1.04 | CW SYSTEM | |||
12 | 1.041 | INDIAN COMPONENTS | Text7 | 1 | Lot |
13 | 1.042 | FOREIGN COMPONENTS | Text8 | 1 | Lot |
14 | 1.05 | NATURAL DRAUGHT COOLING TOWER | |||
15 | 1.051 | INDIAN COMPONENTS | Text9 | 1 | Lot |
16 | 1.052 | FOREIGN COMPONENTS | Text10 | 1 | Lot |
17 | 1.06 | PLANT WATER SYSTEM | |||
18 | 1.061 | INDIAN COMPONENTS | Text11 | 1 | Lot |
19 | 1.062 | FOREIGN COMPONENTS | Text12 | 1 | Lot |
20 | 1.07 | FUEL OIL UNLOADING SYSTEM | |||
21 | 1.071 | INDIAN COMPONENTS | Text13 | 1 | Lot |
22 | 1.072 | FOREIGN COMPONENTS | Text14 | 1 | Lot |
23 | 1.08 | HYDROGEN GENERATION PLANT | |||
24 | 1.081 | INDIAN COMPONENTS | Text15 | 1 | Lot |
25 | 1.082 | FOREIGN COMPONENTS | Text16 | 1 | Lot |
26 | 1.09 | GIS SWITCHYARD 230 kV & 765 kV | |||
27 | 1.091 | INDIAN COMPONENTS | Text17 | 1 | Lot |
28 | 1.092 | FOREIGN COMPONENTS | Text18 | 1 | Lot |
29 | 1.1 | TRANSFORMERS & SWITCHGEAR | |||
30 | 1.101 | INDIAN COMPONENTS | Text19 | 1 | Lot |
31 | 1.102 | FOREIGN COMPONENTS | Text20 | 1 | Lot |
32 | 1.11 | PLC FOR VARIOUS SYSTEMS | |||
33 | 1.111 | INDIAN COMPONENTS | Text21 | 1 | Lot |
34 | 1.112 | FOREIGN COMPONENTS | Text22 | 1 | Lot |
35 | 1.12 | WORKSHOP EQUIPMENT | |||
36 | 1.121 | INDIAN COMPONENTS | Text23 | 1 | Lot |
37 | 1.122 | FOREIGN COMPONENTS | Text24 | 1 | Lot |
38 | 1.13 | PIPE RACK | |||
39 | 1.131 | INDIAN COMPONENTS | Text25 | 1 | Lot |
40 | 1.132 | FOREIGN COMPONENTS | Text26 | 1 | Lot |
41 | 1.14 | MISCELLANEOUS ITEMS (IF ANY) | |||
42 | 1.141 | INDIAN COMPONENTS | Text27 | 1 | Lot |
43 | 1.142 | FOREIGN COMPONENTS | Text28 | 1 | Lot |
44 | 2 | MANDATORY SPARES | |||
45 | 2.01 | INDIAN COMPONENTS | Text29 | 1 | Lot |
46 | 2.02 | FOREIGN COMPONENTS | Text30 | 1 | Lot |
47 | 3 | SUPPLY OF MISCELLANEOUS ITEMS- | |||
48 | 3.01 | INDIAN COMPONENTS | Text31 | 1 | Lot |
49 | 3.02 | FOREIGN COMPONENTS | Text32 | 1 | Lot |
50 | 4 | LOADING, TRANSPORTATION, INSURANCE CHARGES, UNLOADING, ERECTION, TESTING,COMMISSIONING AND PG TEST Etc. | |||
51 | 4.01 | Loading, Inland Transportation including port handling, port clearance, port chargess, Inland Transit Insurance charges, unloading, Storage at site, handling, preservation charges, erection testing and commissiong and performance Guarantee Test | Text33 | 1 | Lot |
52 | 4.02 | FGD FACILITIES | |||
53 | 4.021 | Erection | Text34 | 1 | Lot |
54 | 4.022 | Testing & Commissioning | Text35 | 1 | Lot |
55 | 4.023 | Performance Guarantee Test | Text36 | 1 | Lot |
56 | 4.03 | COAL HANDLING PLANT | |||
57 | 4.031 | Erection | Text37 | 1 | Lot |
58 | 4.032 | Testing & Commissioning | Text38 | 1 | Lot |
59 | 4.033 | Performance Guarantee Test | Text39 | 1 | Lot |
60 | 4.04 | ASH HANDLING PLANT | |||
61 | 4.041 | Erection | Text40 | 1 | Lot |
62 | 4.042 | Testing & Commissioning | Text41 | 1 | Lot |
63 | 4.043 | Performance Guarantee Test | Text42 | 1 | Lot |
64 | 4.05 | CW SYSTEM | |||
65 | 4.051 | Erection | Text43 | 1 | Lot |
66 | 4.052 | Testing & Commissioning | Text44 | 1 | Lot |
67 | 4.053 | Performance Guarantee Test | Text45 | 1 | Lot |
68 | 4.06 | NATURAL DRAUGHT COOLING TOWER | |||
69 | 4.061 | Erection | Text46 | 1 | Lot |
70 | 4.062 | Testing & Commissioning | Text47 | 1 | Lot |
71 | 4.063 | Performance Guarantee Test | Text48 | 1 | Lot |
72 | 4.07 | PLANT WATER SYSTEM | |||
73 | 4.071 | Erection | Text49 | 1 | Lot |
74 | 4.072 | Testing & Commissioning | Text50 | 1 | Lot |
75 | 4.073 | Performance Guarantee Test | Text51 | 1 | Lot |
76 | 4.08 | FUEL OIL UNLOADING SYSTEM | |||
77 | 4.081 | Erection | Text52 | 1 | Lot |
78 | 4.082 | Testing & Commissioning | Text53 | 1 | Lot |
79 | 4.083 | Performance Guarantee Test | Text54 | 1 | Lot |
80 | 4.09 | HYDROGEN GENERATION PLANT | |||
81 | 4.091 | Erection | Text55 | 1 | Lot |
82 | 4.092 | Testing & Commissioning | Text56 | 1 | Lot |
83 | 4.093 | Performance Guarantee Test | Text57 | 1 | Lot |
84 | 4.1 | GIS SWITCHYARD 230 kV & 765 kV | |||
85 | 4.101 | Erection | Text58 | 1 | Lot |
86 | 4.102 | Testing & Commissioning | Text59 | 1 | Lot |
87 | 4.103 | Performance Guarantee Test | Text60 | 1 | Lot |
88 | 4.11 | TRANSFORMERS & SWITCHGEAR | |||
89 | 4.111 | Erection | Text61 | 1 | Lot |
90 | 4.112 | Testing & Commissioning | Text62 | 1 | Lot |
91 | 4.113 | Performance Guarantee Test | Text63 | 1 | Lot |
92 | 4.12 | PLC FOR VARIOUS SYSTEMS | |||
93 | 4.121 | Erection | Text64 | 1 | Lot |
94 | 4.122 | Testing & Commissioning | Text65 | 1 | Lot |
95 | 4.123 | Performance Guarantee Test | Text66 | 1 | Lot |
96 | 4.13 | WORKSHOP EQUIPMENT | |||
97 | 4.131 | Erection | Text67 | 1 | Lot |
98 | 4.132 | Testing & Commissioning | Text68 | 1 | Lot |
99 | 4.133 | Performance Guarantee Test | Text69 | 1 | Lot |
100 | 4.14 | PIPE RACK | |||
101 | 4.141 | Erection | Text70 | 1 | Lot |
102 | 4.142 | Testing & Commissioning | Text71 | 1 | Lot |
103 | 4.143 | Performance Guarantee Test | Text72 | 1 | Lot |
104 | 4.15 | MISCELLANEOUS ITEMS | |||
105 | 4.151 | Erection | Text73 | 1 | Lot |
106 | 4.152 | Testing & Commissioning | Text74 | 1 | Lot |
107 | 4.153 | Performance Guarantee Test | Text75 | 1 | Lot |
108 | 5 | CIVIL WORKS | |||
109 | 5.01 | FGD FACILITIES | |||
110 | 5.011 | CIVIL WORKS | Text76 | 1 | Lot |
111 | 5.012 | STRUCTURAL WORKS | Text77 | 1 | Lot |
112 | 5.02 | COAL HANDLING PLANT | |||
113 | 5.021 | CIVIL WORKS | Text78 | 1 | Lot |
114 | 5.022 | STRUCTURAL WORKS | Text79 | 1 | Lot |
115 | 5.03 | ASH HANDLING PLANT | |||
116 | 5.031 | CIVIL WORKS | Text80 | 1 | Lot |
117 | 5.032 | STRUCTURAL WORKS | Text81 | 1 | Lot |
118 | 5.04 | CW SYSTEM | |||
119 | 5.041 | CIVIL WORKS | Text82 | 1 | Lot |
120 | 5.042 | STRUCTURAL WORKS | Text83 | 1 | Lot |
121 | 5.05 | NATURAL DRAUGHT COOLING TOWER | |||
122 | 5.051 | CIVIL WORKS | Text84 | 1 | Lot |
123 | 5.052 | STRUCTURAL WORKS | Text85 | 1 | Lot |
124 | 5.06 | PLANT WATER SYSTEM | |||
125 | 5.061 | CIVIL WORKS | Text86 | 1 | Lot |
126 | 5.062 | STRUCTURAL WORKS | Text87 | 1 | Lot |
127 | 5.07 | FUEL OIL UNLOADING SYSTEM | |||
128 | 5.071 | CIVIL WORKS | Text88 | 1 | Lot |
129 | 5.072 | STRUCTURAL WORKS | Text89 | 1 | Lot |
130 | 5.08 | HYDROGEN GENERATION PLANT | |||
131 | 5.081 | CIVIL WORKS | Text90 | 1 | Lot |
132 | 5.082 | STRUCTURAL WORKS | Text91 | 1 | Lot |
133 | 5.09 | GIS SWITCHYARD 230 kV & 765 kV | |||
134 | 5.091 | CIVIL WORKS | Text92 | 1 | Lot |
135 | 5.092 | STRUCTURAL WORKS | Text93 | 1 | Lot |
136 | 5.1 | TRANSFORMERS & SWITCHGEAR | |||
137 | 5.101 | CIVIL WORKS | Text94 | 1 | Lot |
138 | 5.102 | STRUCTURAL WORKS | Text95 | 1 | Lot |
139 | 5.11 | VILLAGE ROAD DIVERSION | |||
140 | 5.111 | CIVIL WORKS | Text96 | 1 | Lot |
141 | 5.112 | STRUCTURAL WORKS | Text97 | 1 | Lot |
142 | 5.12 | WORKSHOP | |||
143 | 5.121 | CIVIL WORKS | Text98 | 1 | Lot |
144 | 5.122 | STRUCTURAL WORKS | Text99 | 1 | Lot |
145 | 5.13 | PIPE RACK | |||
146 | 5.131 | CIVIL WORKS | Text100 | 1 | Lot |
147 | 5.132 | STRUCTURAL WORKS | Text101 | 1 | Lot |
148 | 5.14 | LEVELLING AND GRADING | |||
149 | 5.141 | CIVIL WORKS | Text102 | 1 | Lot |
150 | 5.142 | STRUCTURAL WORKS | Text103 | 1 | Lot |
151 | 5.15 | BOUNDARY WALL | |||
152 | 5.151 | CIVIL WORKS | Text104 | 1 | Lot |
153 | 5.152 | STRUCTURAL WORKS | Text105 | 1 | Lot |
154 | 5.16 | ROADS AND DRAINS | |||
155 | 5.161 | CIVIL WORKS | Text106 | 1 | Lot |
156 | 5.162 | STRUCTURAL WORKS | Text107 | 1 | Lot |
157 | 5.17 | RCC CHIMNEY | |||
158 | 5.171 | CIVIL WORKS | Text108 | 1 | Lot |
159 | 5.172 | STRUCTURAL WORKS | Text109 | 1 | Lot |
160 | 5.18 | NON PLANT BUILDING | |||
161 | 5.181 | CIVIL WORKS | Text110 | 1 | Lot |
162 | 5.182 | STRUCTURAL WORKS | Text111 | 1 | Lot |
163 | 5.19 | MISSCELLANEOUS CIVIL WORKS | |||
164 | 5.191 | CIVIL WORKS | Text112 | 1 | Lot |
165 | 5.192 | STRUCTURAL WORKS | Text113 | 1 | Lot |
166 | 6 | TYPE TEST CHARGES | |||
167 | 6.01 | Type Test charges for all Electro-Mechanical equipments | Text114 | 1 | Lot |
168 | 7 | OTHER CHARGES | |||
169 | 7.01 | Imparting Training to Owner's personnel | Text115 | 1 | Lot |
170 | 7.02 | Any other charges - 1 | Text116 | 1 | Lot |
171 | 7.03 | Any other charges - 2 | Text117 | 1 | Lot |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail