Central University Of Kashmir-CUK has published E-Tender For Construction Of Rcc Columns ( 3Nos ) On Isolated Footings For Main Gate At Watlar Township Cuk , Ganderbal. Submission Date for this Tender is 08-03-2021. Civil Work Tenders in CUK Township Watlar Jammu And Kashmir. Bidders can get complete Tender details and download the document.
Name of Work: e-Tender for Construction of RCC columns (3Nos) on isolated footings for main Gate at Watlar township CUK, Ganderbal | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.\nAll kinds of soil | 5.02 | CUM | |
2 | 2 | Supplying & filling of stone soiling hand packed including cost of hand ramming etc & carriage upto the site of work. Complete | 0.52 | CUM | |
3 | 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering & shuttering. All works upto plinth level 1:4:8 ( 1cement: 4Coarse sand zone III: 8 graded stone agg. 40mm nominal size) crusshed incl. of all carriages complete. | 0.34 | CUM | |
4 | 4 | Providing & laying in position specified grade of reinforced cement concrete excluding the cost of centering, shuttering, finishing & reinforcement. All works upto plinth level. 1:1.5:3 mix incl. of all carriages complete. | 1.78 | CUM | |
5 | 5 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :\n1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size)\n | 2.6 | CUM | |
6 | 6 | Steel reinforcement for R.C.C. work including straightening, cutting,bending, placing in position and binding all complete upto plinth/ above plinth level. Thermo-Mechanically Treated bars of grade Fe-500 D or more incl. of all carriages complete. | 569.4 | KGS | |
7 | 7 | Centering and shuttering including strutting, propping etc. and removal of form for :\n | BI01010001010000000000000515BI0100001136 | ||
8 | 7.1 | Foundations, footings, bases of columns, etc. for mass concrete | BI01010001010000000000000515BI0100001137 | 10.03 | SQM |
9 | 7.2 | Columns, Pillars, Piers, Abutments, Posts and Struts | BI01010001010000000000000515BI0100001138 | 19.51 | SQM |
10 | 8 | Structural steel work in single section, fixed with or without connecting plate,including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | 45 | KGS |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy