| 1 | 1 | VCB RENOVATION AND SIDE PROTECTION WORK | BI01010001010000000000000515BI0100001113 | | |
|---|
| 2 | 1.01 | 15.2.2 : Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix) | BI01010001010000000000000515BI0100001114 | 1.376 | cum |
|---|
| 3 | 1.02 | 15.3 : Demolishing R.C.C. work manually / by mechanical means including stacking of steel bars and disposal of unserviceable material with in 50 metres lead as per direction of Engineer -in-Charge. | BI01010001010000000000000515BI0100001115 | 27.558 | cum |
|---|
| 4 | 1.03 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001116 | 104.058 | cum |
|---|
| 5 | 1.04 | 5.1.2 : Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level:1:1:5:3 (1 cement 1.5 coarse sand :3 graded stone aggregate 20 mm nominal size | BI01010001010000000000000515BI0100001117 | 34.517 | cum |
|---|
| 6 | 1.05 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001118 | 3210.08 | kilogram |
|---|
| 7 | 1.06 | 5.9.5 : Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers | BI01010001010000000000000515BI0100001119 | 116.29 | sqm |
|---|
| 8 | 1.07 | 5.23 : Smooth finishing of the exposed surface of RCC work with 6mm thick cement mortar 1:3 ( cement : 3 fine sand). | BI01010001010000000000000515BI0100001120 | 104.232 | sqm |
|---|
| 9 | 1.08 | 60.7.4 : DR PACKING FOR APRONS - Rough stone dry packing for apron with good quality blasted rubble including packing to compactness to lines levels, cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site | BI01010001010000000000000515BI0100001121 | 25.833 | cum |
|---|
| 10 | 1.09 | 60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site | BI01010001010000000000000515BI0100001122 | 64.2 | cum |
|---|
| 11 | 1.1 | 4.1.5 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) | BI01010001010000000000000515BI0100001123 | 0.75 | cum |
|---|
| 12 | 1.11 | 60.8 : Shutter for check dams- Supplying and providing Thambagam wood shutter planks 5cm thick including cost of materials and labour charges etc complete | BI01010001010000000000000515BI0100001124 | 85.951 | 10 cud m |
|---|
| 13 | 1.12 | 10.26.3 : Providing and fixing hand rail of approved size by welding etc. to steel ladder railing, balcony railing, staircase railing and similar works, including applying priming coat of approves steel primer.G.I. pipes | BI01010001010000000000000515BI0100001125 | 413.1 | kg |
|---|
| 14 | 1.13 | 50.2.26.1 : Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge. | BI01010001010000000000000515BI0100001126 | 298.35 | cum |
|---|
| 15 | 2 | CONSTRUCTION OF STORE SHED | BI01010001010000000000000515BI0100001127 | | |
|---|
| 16 | 2.01 | 2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil | BI01010001010000000000000515BI0100001128 | 5.088 | cum |
|---|
| 17 | 2.02 | 50.6.7.1 : Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for foundation and basement including all cost of materials, labour charges etc. | BI01010001010000000000000515BI0100001129 | 8.063 | cum |
|---|
| 18 | 2.03 | 50.6.7.2 : Laterate masonry with neatly dressed laterate stone of size 40x20x15cm or nearest size in cement mortar 1:6 for super structure above plinth level up to floor two level including all cost of materials, labour charges etc. | BI01010001010000000000000515BI0100001130 | 9.326 | cum |
|---|
| 19 | 2.04 | 5.3 : Reinforced cement concrete work in beams, suspended floors, roofs, having slope up to 15<sup>0</sup> landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with1:1.5:3 (1 cement : 1.5 coarse sand (Zone III) : 3 graded stone aggregate 20 mm nominal size). | BI01010001010000000000000515BI0100001131 | 2.468 | cum |
|---|
| 20 | 2.05 | 5.9.3 : Centering and shuttering including strutting, etc. and removal of form for:Suspended floors, roofs, landings, balconies and access platform | BI01010001010000000000000515BI0100001132 | 23.542 | sqm |
|---|
| 21 | 2.06 | 5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more | BI01010001010000000000000515BI0100001133 | 234.46 | kilogram |
|---|
| 22 | 2.07 | 5.23 : Smooth finishing of the exposed surface of RCC work with 6mm thick cement mortar 1:3 ( cement : 3 fine sand). | BI01010001010000000000000515BI0100001134 | 22.842 | sqm |
|---|
| 23 | 2.08 | 10.6.1 : Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength conforming to IS: 4454 - part 1 and M.S. top cover of required thickness for rolling shutters.80x1.25 mm M.S. laths with 1.25 mm thick top cover | BI01010001010000000000000515BI0100001135 | 4.86 | sqm |
|---|
| 24 | 2.09 | 11.5 : 62 mm thick cement concrete flooring with concrete hardener topping, under layer 50 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and top layer 12 mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate, 6 mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufactures specification. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete. | BI01010001010000000000000515BI0100001136 | 8.75 | sqm |
|---|
| 25 | 2.1 | 13.1.1 : 12 mm cement plaster of mix:1:4 ( 1 cement : 4 fine sand) | BI01010001010000000000000515BI0100001137 | 107.432 | sqm |
|---|
| 26 | 2.11 | 13.37.1 : White washing with lime to give an even shade:New work (three or more coats) | BI01010001010000000000000515BI0100001138 | 107.432 | sqm |
|---|
| 27 | 2.12 | 13.62.1 : Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade:Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture . | BI01010001010000000000000515BI0100001139 | 10.935 | sqm |
|---|