| 1 | 1 | Earthwork excavation in soft rock not requiring blasting and depositing on bank with an initial lead of 10 metres and initial lift of 2 metres in hard stiff clay stiff black cotton soil with small sized boulders as per SS 20 B for foundation and all other incidental charges such as shoring, strutting, walling, bailing out water and forming protective bunds etc., complete as per standard specification. | | 1000.26 | Cubic metre |
|---|
| 2 | 2 | Cement concrete 1:3:6 mix using 40mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement and labour for mixing laying, watering curing and compacting concrete and labour for form work and all other incidental charges, etc., complete for Leveling course of drain. | | 76.32 | Cubic metre |
|---|
| 3 | 3 | Cement Concrete of Grade M 15 using 20mm ISS size HBG ISS hard granite broken Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications FOR BASE COURSE. | | 184.05 | Cubic metre |
|---|
| 4 | 4 | Vibrated Cement Concrete of Grade M 20 using 20mm ISS size HBG ISS hard granite broken Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications FOR BODY WALL. | | 245.4 | Cubic metre |
|---|
| 5 | 5 | Vibrated Reinforcement Concrete of Grade M 25 using graded ISS size HBG ISS hard granite broken Metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications FOR BASE SLAB, VERTICAL WALL & COVER SLAB . | | 145.92 | Cubic metre |
|---|
| 6 | 6 | Providing and fixing class1 PVC seepage pipes of 110 mm dia of required lengths for abutments and return walls including costs and conveyance of all materials to work site and labour charges for fixing , etc., complete to drain the water. | | 10 | Numbers |
|---|
| 7 | 7 | Supply and fabrication of Steel Grade Fe 500 required for all RCC items of works involved in the schedule including cost of steel, cost of fabrication, labour charges for cleaning the bars straightening, cutting, bending, tying grills, hoisting and placing the reinforcement in position as specified in the drawings including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc., complete as per standard specification as per clause 1000, 1500, 1600, 1700, 2100, 2300 & 900 of MORTH Vth Revision | | 8.21 | Metric Tonne |
|---|
| 8 | 8 | Supplying and fixing of Reinforced Cement Concrete Man hole cover 750 mm dia with frames as per IRC 50- 1979 as directed by the Departmental officers including labour charges for fixing at every intervals of 10 m along the drain including all other incidental charges etc., complete | | 40 | Numbers |
|---|
| 9 | 9 | Fabrication, supply and fixing in position of Grating at fixing at Drainage wall using M.S. angle of size 25 x 25 x5 mm for frame and Special type of Hold fast welded to the frame fixed at centre for wall and fixing the 8mm RTS bar including necessary dismantling, making holes in RCC/PCC walls wherever necessary with power drill to the extend required and made good to the original conditions after fixing as directed by the departmental officers. | | 80 | Numbers |
|---|
| 10 | 10 | Supply and Laying of Ornamental Anti Skid Tiles 20 mm thick over a base layer of cement mortor 1:3, including cost of materials in etc., complete.\n\n | | 654.4 | Square Metre |
|---|
| 11 | 11 | Calculation of SubTotal, GST and Total Amount carried out by system automatically | | | |
|---|
| 12 | 12 | Basic cost of value put to tender as per estimate | | 1 | (A) |
|---|
| 13 | 13 | Add GST at 12% | | 1 | (B) |
|---|
| 14 | 14 | Total Value put to Tender | | 1 | (A+B) |
|---|
| 15 | 15 | Differnce Amount (Excess/less) | | 1 | (D) |
|---|
| 16 | 16 | Quoted Amount (Basic Rate Only) | | 1 | (E) |
|---|
| 17 | 17 | Add GST at 12% of Quoted Amount | | 1 | (F) |
|---|
| 18 | 18 | Total Value of Quoted Amount including 12% of GST | | 1 | (E+F) |
|---|