| 1 | 1 | Dismentling of old and damage c.c including supply of all material,labour and T&P etc.required for proper completion of work. | 15.16 | 76.16 | Sqm |
|---|
| 2 | 2 | Disposal of dismentling cc road material with cartage upto distance 3.00 km i/c loading and unloading 80 % of item no-1 including supply of all material,labour and T&P etc.required for proper completion of work | | 6.09 | Cum |
|---|
| 3 | 3 | Dismentling of old and damage drain brick work including supply of all material,labour and T&P etc.required for proper completion of work | | 2.6 | Cum |
|---|
| 4 | 4 | Deduction of old and workable brick 40% of item no-3 | | 478.64 | Nos |
|---|
| 5 | 5 | Breaking of old brick bets for 4cm guage brick ballast 60% 0f item no-3 | | 1.56 | Cum |
|---|
| 6 | 6 | Deduction cost of old brick ballast as per item no-5 | | 1.56 | Cum |
|---|
| 7 | 7 | Concrete in 1:4:8 with cement,fine sand and brick ballast of 4cm guage including supply of all material,labour and T&P etc.required for proper completion of work. | | 3.77 | Cum |
|---|
| 8 | 8 | M-150 brick work in 1:3 with cement,coarse sand mortar including supply of all material,labour and T&P etc.required for proper completion of work. | | 3.29 | Cum |
|---|
| 9 | 9 | 12mm thick Plaster in 1:3 with cement,coarse sand mortar including supply of all material,labour and T&P etc.required for proper completion of work. | | 43.36 | Sqm |
|---|
| 10 | 10 | C.C in 1:2:4 with cement,coarse sand and stone grit of 2cm guage including supply of all material,labour and T&P etc.required for proper completion of work. | | 0.43 | cum |
|---|
| 11 | 11 | Providing,laying and compaction of two layer stone ballast with fine sand including supply of all material,labour and T&P etc.required for proper completion of work. | | 5.71 | Cum |
|---|
| 12 | 12 | Laying of C.C work in 1:1.5:3 with cement,coarse sand and stone ballast of 2cm guage including supply of all material,labour and T&P etc required for proper completion of work. | | 9.14 | Cum |
|---|
| 13 | 13 | Making Expansion/contraction joints in c.c road i/c approved filler materials in joints.depth of joint 10cm/require depth at the joints of panels and giving them a uniform finish including supply of all material,labour and T&P etc required for proper completion of work. | | 18 | Rmt |
|---|
| 14 | 14 | R.C.C work in 1:2:4 with cement,coarse sand and stone ballast of 2cm guage including supply of all material,labour and T&P etc.required for proper completion of work | 2.86 | 0.26 | Cum |
|---|
| 15 | 15 | Supply and fixing of mild steel bars for RCC work and angle for channel including supply of all material,labour and T&P etc.required for proper completion of work. | | 0.26 | Qlt |
|---|
| 16 | 16 | ADD 1% LABOUR CESS | | 1 | job |
|---|