Maintenance And Repair Works At 33 Kv Sub Station Maliyana And Bhola , Rohta , Pooth , Kaithwari , Khiwai And Karnawal For Sdo Iii Bhola Under Edd Iii Meerut
Tender Overview
Project Description
maintenance and repair Works At 33 Kv Sub Station Maliyana And Bhola , Rohta , Pooth , Kaithwari , Khiwai And Karnawal For Sdo Iii Bhola Under Edd Iii Meerut
Corrigendum
| Sr No | Corrigendum Date | Corrigendum | Type | New Submission Date |
|---|---|---|---|---|
| 1 | 22-Feb-2021 | EXTEND DATE 99/2020-21 | Date | 01-Mar-2021 |
| 2 | 01-Mar-2021 | DATE EXTEND TENDER NO 99/2020-21 | Date | 08-Mar-2021 |
| 3 | 08-Mar-2021 | EXTENDED DATE 99/2020-21 | Date | 19-Mar-2021 |
BOQ
| Name of Work: Replacement of Damage Pole, Straightening of Bended Pole, Resagging of Loose Conductor, Replacement of Jumper of Damage Pole, LT Leads and Cutting of Tree Branches of 11 KV & LT Lines (M & R Scheme) at 33/11 KV Sub Station Bhola, Rohta, Pooth, Kaithwari, Khiwai and Karnawal in the area of EDSD-III, Bhola under EDD-III, Meerut | |||||
|---|---|---|---|---|---|
| Sl.No. | Item Description | Item Code / Make | Quantity | Units | |
| 1 | 1 | Cartage of following material from store center Meerut to JE Store including loading & unloading at both ends maximum distance up to 40 Km. :- | BI01010001010000000000000515BI0100001112 | ||
| 2 | 1.01 | PCC Pole 8.5 mtr. Long | BI01010001010000000000000515BI0100001113 | 15 | Nos |
| 3 | 2 | Cartage of following material from JE, Store to site of work including loading & unloading at both ends maximum distance up to 40 Km. :- | |||
| 4 | 2.01 | PCC Pole 8.5 mtr. Long | 15 | Nos | |
| 5 | 3 | Dismentling of damage and broken PCC pole by digging the pit for required depth and length of HT/LT line including removal of all accessories | 13 | Nos | |
| 6 | 4 | Dismentling of damage and broken double pole of PCC pole by digging the pit for required depth and removal of all accessories of double pole including demounting of T/F | 1 | Job | |
| 7 | 5 | Erection of PCC pole 8.5 mtr. Long in long span and from where damage pole has been emoved after digging of pit of size 1.20x0.60x1.5 mtr. In all type of soil including back filling of the pole with proper ramming | 13 | Nos | |
| 8 | 6 | Fixing of HT & LT line accessories on newly erected poles | 13 | Nos | |
| 9 | 7 | Erection of double pole on PCC pole by digging the pit and fixing of all accessories such as top and droper channel and required 11 KV accessories including mounting of T/F with HT side jumper and fixing of LV PVC lead | 1 | Job | |
| 10 | 8 | Lifting of conductors of 3 ph. 11 kv line and 3 ph. LT line including binding and jumpers properly | 20 | Span | |
| 11 | 9 | Providing and fixing bamboo strips in 3 phase 4 wire and 2 phase 3 wire in LT line with proper binding | 75 | Nos | |
| 12 | 10 | Cutting & Chopping tree branches near & over side of line for making the clearance between line and tree | 105 | Nos | |
| 13 | 11 | Resagging of loose sag of 11 KV line and LT line after opening the bindings then stringing the conductor & rebinding jumpering the same properly | 110 | Span | |
| 14 | 12 | Straightening of bended PCC pole by opening the binding and digging the pit for required size and rebinding the same after complition of work | 32 | Nos |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedCorrigendum-1 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-2 Issued
Clarifications on tender conditions and amendments issued.
CompletedCorrigendum-3 Issued
Clarifications on tender conditions and amendments issued.
CompletedBid Submission Deadline
Online submission via eProcurement portal.