Ministry Of Road Transport And Highways has published Consultancy Services For Feasibility Study And Detailed Engineering For Construction Of 4 Lane Flyover On Nh-503 Extn . Between Km . 31/0 To 35/0 In The State Of Himachal Pradesh . . Submission Date for this Tender is 01-03-2021. Feasibility Studies Tenders in Hamirpur Himachal Pradesh. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 03-Feb-2021 | Addendum No. 3 | Other | 17-02-2021 |
2 | 15-Feb-2021 | Corrigendum4 | Date | 01-03-2021 |
Consultancy services for feasibility study and detailed Engineering for Construction of 4 lane flyover on NH-503 extn. between km. 31/0 to 35/0 in the state of Himachal Pradesh. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Remuneration for Local Staff (inclusive of per diem allowance) | BI01010001010000000000000515BI0100001112 | ||
2 | 1.01 | Team Leader cum Senior Bridge Engineer | BI01010001010000000000000515BI0100001113 | 10 | Month |
3 | 1.02 | Bridge Structural Engineer | BI01010001010000000000000515BI0100001114 | 6 | Month |
4 | 1.03 | Highway cum Pavement Engineer | BI01010001010000000000000515BI0100001115 | 10 | Month |
5 | 1.04 | Material-cum-Geotechnical Engineer- Geologist | BI01010001010000000000000515BI0100001116 | 10 | Month |
6 | 1.05 | Senior Survey Engineer | 6 | Month | |
7 | 1.06 | Senior Geologist | 6 | Month | |
8 | 1.07 | Environmental Specialist | 6 | Month | |
9 | 1.08 | Quantity Surveyor/ Documentation Expert | 4 | Month | |
10 | 2 | Sub Professional Staff (To be assessed by Consultant as per requirement of assignment and one sub-professional be a fresh graduate) | |||
11 | 2.01 | Position | 1 | Lumpsum | |
12 | 2.02 | Position | 1 | Lumpsum | |
13 | 2.03 | Position | 1 | Lumpsum | |
14 | 2.04 | Position | 1 | Lumpsum | |
15 | 2.05 | Position | 1 | Lumpsum | |
16 | 2.06 | Position | 1 | Lumpsum | |
17 | 2.07 | Position | 1 | Lumpsum | |
18 | 3 | Support Staff (inclusive of per diem allowance)\nNote: To be assessed by consultant as per requirement of assignment | |||
19 | 3.01 | Office Manager | 1 | Lumpsum | |
20 | 3.02 | Typist | 1 | Lumpsum | |
21 | 3.03 | Office Boy | 1 | Lumpsum | |
22 | 3.04 | Night Watchman | 1 | Lumpsum | |
23 | 4 | Transportation (Fixed Costs) | |||
24 | 4.01 | The vehicles hired by the Consultant shall include the cost For rental, drivers, operation, maintenance, repairs, insurance, etc. | 1 | Lumpsum | |
25 | 5 | Duty Travel to Site (Fixed Costs) | |||
26 | 5.01 | Trips | 1 | Lumpsum | |
27 | 6 | Office Rent (Fixed Costs) \nThe rent cost includes maintenance, cleaning, repairs, etc. | |||
28 | 6.01 | Office Rent | 1 | Lumpsum | |
29 | 7 | Office Supplies, Utilities and Communication (Fixed Costs) | |||
30 | 7.01 | Office Supplies Drafting | 1 | Lumpsum | |
31 | 7.02 | Supplies Computer | 1 | Lumpsum | |
32 | 7.03 | Running Costs | 1 | Lumpsum | |
33 | 7.04 | Domestic and International Communication | 1 | Lumpsum | |
34 | 8 | Office Furniture and Equipment (Rental) | |||
35 | 8.01 | Office Furniture and Equipment | 1 | Lumpsum | |
36 | 9 | Reports and Document Printing | |||
37 | 9.01 | Monthly Report (3 copies per month) | 30 | Nos. | |
38 | 9.02 | Inception Report & QAP | 3 | Nos. | |
39 | 9.03 | Environment and Social Impact Screening Report | 4 | Nos. | |
40 | 9.04 | Draft Feasibility Report | 4 | Nos. | |
41 | 9.05 | Final Feasibility Report | 6 | Nos. | |
42 | 9.06 | Strip Plan with L.A. Reports | 6 | Nos. | |
43 | 9.07 | Draft LA and Clearances I Report | 4 | Nos. | |
44 | 9.08 | Final LA and Clearances I Report | 4 | Nos. | |
45 | 9.09 | Draft Environmental Assessment report& RAP | 4 | Nos. | |
46 | 9.1 | Final Environmental Assessment report& RAP | 6 | Nos. | |
47 | 9.11 | Draft Detailed Design Report & Drawings etc. | 4 | Nos. | |
48 | 9.12 | Draft EMP | 4 | Nos. | |
49 | 9.13 | Draft Bidding Document | 4 | Nos. | |
50 | 9.14 | Final Detailed Project Report with Bill of Quantities, Cost Estimates, Updated Drawings etc. | 6 | Nos. | |
51 | 9.15 | Final EMP | 6 | Nos. | |
52 | 9.16 | Final Bidding Documents | 6 | Nos. | |
53 | 9.17 | Draft 3(a) ,3(A) and 3(D)& 3G notification for land acquisition (3 copies each) | 9 | Nos. | |
54 | 9.18 | LA & Clearances II Report | 6 | Nos. | |
55 | 10 | Survey and Investigation A. Topographical Survey (Fixed Rate) | |||
56 | 10.01 | Topographic Survey including hire charges for equipment (GPS, Total Station, Auto Level etc.) and supply of survey Teams comprising of project survey filed staff etc. inclusive of cost of materials, labourer. | 1 | Complete JoB | |
57 | 10.02 | Detailed topographic surveys using mobile/ aerial LiDAR or better technology | 1 | Complete JoB | |
58 | 11 | Investigation (Fixed cost)(lumpsum) | |||
59 | 11.01 | Road and Bridge Inventory | 1 | LumpSum | |
60 | 11.02 | FWD Test And Pavement Evaluation | 1 | LumpSum | |
61 | 11.03 | Roughness Survey | 1 | LumpSum | |
62 | 11.04 | Axle load Survey | 1 | LumpSum | |
63 | 11.05 | Material Survey and Investigation | 1 | LumpSum | |
64 | 11.06 | Sub grade Investuigation | 1 | LumpSum | |
65 | 11.07 | Traffic Survey | 1 | LumpSum | |
66 | 11.08 | Socio economic and Census Survey/Studies | 1 | LumpSum | |
67 | 11.09 | Land Acquisition Studies | 1 | LumpSum | |
68 | 11.1 | Any other investigations/surveys | 1 | LumpSum | |
69 | 11.11 | Sub-Soil Investigation (Boring) (Rate/m) | |||
70 | 11.12 | a) In soil other than hard rock | 1500 | Meter | |
71 | 11.13 | b) In hard rock | 200 | Meter | |
72 | 11.14 | Net Work Survey and GPR | |||
73 | 11.15 | Net work Survey of the existing Highways as a repository for civil work as per directions from Authority. | 1 | Complete JoB | |
74 | 11.16 | GPR Survey for detection of under ground utilities | 1 | Complete JoB | |
75 | 12 | Fixing Boundary pillars | |||
76 | 12.01 | Procuring and fixing boundary pillars and its installation, complete in all respect as per IRC:25,1967: Wherever the proposed alignment follows the existing alignment, the boundary pillars shall be fixed at an interval of 200m on either side of proposed Right of Way. Wherever there is a proposal of realignment of the existing Highway and/or construction of New Bypasses, Consultant shall fix boundary pillars along the proposed alignment on the extreme boundary on either side of the project Highway at 50 m interval | 1 | Lumpsum | |
77 | 13 | Land Acquisition Team including support staff and logistics/transportation | |||
78 | 13.01 | Ex-Land Revenue Inspector/Officer or equivalent\n | 8 | Month | |
79 | 13.02 | Ex-Kanoogo/Girdwar or equivalent | 8 | Month | |
80 | 13.03 | Ex-Patwari or equivalent\n | 8 | Month | |
81 | 13.04 | Typist (2 nos.) | 8 | Month | |
82 | 13.05 | Peon | 8 | Month | |
83 | 14 | Logistics for Land acquisition Team | |||
84 | 14.01 | Computer including necessary\nperipherals (2 nos.)\n | 8 | Month | |
85 | 14.02 | Printers (2 nos.) | 8 | Month | |
86 | 14.03 | Vehicles (Bolero or equivalent)\nwith monthly running limit of 4000 km\n | 8 | Month | |
87 | 15 | Estimate of ExpatriateConsultants (Name and position to be filled in below columns by the bidder) | |||
88 | 15.01 | Position (Value= 0) | |||
89 | 15.02 | Position (Value= 0) | |||
90 | 15.03 | Position (Value= 0) | |||
91 | 15.04 | Position (Value= 0) | |||
92 | 15.05 | Position (Value= 0) | |||
93 | 15.06 | Position (Value= 0) | |||
94 | 15.07 | Position (Value= 0) | |||
95 | 15.08 | Moblization and Demoblization- International Airfares (Fixed Costs) (To be filled by bidders in below columns) | |||
96 | 15.09 | Position (Value= 0) | |||
97 | 15.1 | Position (Value= 0) | |||
98 | 15.11 | Position (Value= 0) | |||
99 | 15.12 | Position (Value= 0) | |||
100 | 15.13 | Position (Value= 0) | |||
101 | 15.14 | Position (Value= 0) | |||
102 | 15.15 | Position (Value= 0) | |||
103 | 16 | Moblization and Demoblization-Inland Travel in Home country (Fixed Costs) | 1 | LumpSum | |
104 | 17 | Other Miscellaneous expenses (Like DA, internal travel expenses other incidentals)(Fixed Cost) | 1 | LumpSum |
Copyright © 2024 · All Rights Reserved. Terms of Usage | Privacy Policy