| 1 | 1 | Dismantling existing C.C. Flooring, tiles etc and earth work excavation in and deposting the spoil outside the mill,with all cost and charges | CW1 | | |
|---|
| 2 | 1.01 | In all classes of soft soil | CW1.01 | 1657 | CUM |
|---|
| 3 | 1.02 | In hard rock /Hard laterite (blasting prohibited) | CW1.02 | 50 | CUM |
|---|
| 4 | 2 | Cement concrete 1:3:6 using 40mm hard granite broken stone for foundation laying consolidating curing etc .complete with all cost and charges excluding cost of cement curing etc .complete with all cost and charges | CW2 | 130 | CUM |
|---|
| 5 | 3 | Masonry work in cemnet mortar 1:5 using cement solid block for air trench side wall with all cost and charges excluding cost of cement | CW3 | 372 | CUM |
|---|
| 6 | 4 | Plastering with cement morter 1:4 12mm thickne coat including finishing all crners and jints with neat cement grouting etc cmplete for inside trenches with all cost and charges including curing but excluding the cost of cement. | CW4 | 4719 | Sqm |
|---|
| 7 | 5 | Reinforced Cement Concrete1:2:4 using 20mm hard broken stone with all cost and charges for mixing laying and form work on both sides for trench wall and whereever reuired, slabs,bottom etc complete excluding cost of cement and steel | CW5 | 238 | CUM |
|---|
| 8 | 6 | Reinforcement for RCC work including straightening, cutting, bending, placing in position and binding all complete but excludng the cost of the steel. | CW6 | 17850 | Kgs |
|---|
| 9 | 7 | Reflooring after chipping the exisisting floor and spreading SBR(latex Lotion) at 4m2per litre ,lay Cement concrete 1:2:4 using 20mm metel for 75mm thick and top finished with hard floor materials spread at 3kg per M2 by way of Vacum Dewatering method and power trowled with all cost and hire of vacum dewater pump, power trowel etc complete but excluding cost of cement and hard floor materials etc | CW7 | 5171 | Sqm |
|---|
| 10 | 8 | Fixing Air silts and Manhole etc in concrete over air trenches and finishing openings with cement grout | CW8 | 228 | Nos |
|---|
| 11 | 9 | Cutting expansion groove in concrete floor for specified width and depth and filling solvent free filler with all charges excluding cost of solvent | CW9 | 1607 | Mtr |
|---|
| 12 | 10 | White cement washing two coats with all cost and charges | CW10 | 3714 | Sqm |
|---|
| 13 | 11 | Demolishing Laterite masnry work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.. | CW11 | 40 | CUM |
|---|
| 14 | 12 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) | CW12 | 44 | CUM |
|---|
| 15 | 13 | Random Rubble masonery in CM 1:5 for foundation Basement etc. | CW13 | 30 | CUM |
|---|
| 16 | 14 | Patch plastering with cement mortar :4 | CW14 | 1000 | Sqm |
|---|
| 17 | 15 | Extra for fixing charges of labour of air fan 1200 dia includng fixng in position grouting, supporting wherever required etc,complete excluding the charges of materials. | CW15 | 228 | Nos |
|---|
| 18 | 16 | Extra for fixing charges of labour of Eleminator includng fixng in position grouting, supporting wherever required etc,complete excluding the charges of materials. | CW16 | 228 | Nos |
|---|
| 19 | 17 | Extra for fixing charges of labour of Pump pipe line grotng includng fixng in position grouting, supporting wherever required etc,complete excluding the charges of materials. | CW17 | 228 | Nos |
|---|
| 20 | 18 | Extra for fixing charges of labour of Water Filter frame grouting includng fixng in position grouting, supporting wherever required etc,complete excluding the charges of materials. | CW18 | 228 | Nos |
|---|
| 21 | 19 | Extra for fixing charges of labour of Rotary screen Filter frame grouting includng fixng in position grouting, supporting wherever required etc,complete excluding the charges of materials. | CW19 | 228 | Nos |
|---|
| 22 | 20 | Providing and fixing plastic sheet of approved thickness above slab shuttering work before concreting | CW20 | 100 | Sqm |
|---|
| 23 | 21 | Providing temporary curtain arrngment with suitable materials for protecting dust and arranging smooth working rooms where the between the company wrking area and civil working area.(The actual partition area to be measured for payment) | CW21 | 800 | Sqm |
|---|
| 24 | 22 | Extra for refilling the available earth in side of trenches including charges for refilling transportation,compaction consolidation etc complete | CW22 | 44 | CUM |
|---|