Civil Engineering Department has published Selection Of Consultant As Ind . Engineer For Operation And Maintenance Period Of Sambalpur-Rourkela Road Section ( 4 Lane With Paved Shoulder ) Of Sh-10 From Km 4 . 900 ( Sambalpur ) To 167 . 900 Km ( Rourkela ) Executed As Bot ( Toll ) Project . Submission Date for this Tender is 15-03-2021. Design Consultancy Tenders in In SBP RKL road Odisha. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 19-Feb-2021 | 1st Corrigendum | Date | 08-03-2021 |
2 | 04-Mar-2021 | 2nd Corrigendum | Date | 15-03-2021 |
Name of Work: Selection of Consultant as Independent Engineer for Operation & Maintenance (O&M) period of Sambalpur-Rourkela Road Section (4-lane with paved shoulder) of SH-10 from Km 4.900 ( Sambalpur) to 167.900 Km (Rourkela) in the State of Odisha executed as BOT (Toll) Project on DBFOT Pattern. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | A. REMUNERATION\na.Key Professionals | |||
2 | 1.01 | Team Leader-Cum-Senior Highway Engineer | 36 | Man-month | |
3 | 1.02 | Highway Maintenance-cum-Resident Engineer - 1 | 36 | Man-month | |
4 | 1.03 | Highway Maintenance-cum-Resident Engineer - 2 | 36 | Man-month | |
5 | 1.04 | Road Safety Expert | 12 | Man-month | |
6 | 1.05 | Bridge/Structural Engineer | 12 | Man-month | |
7 | 2 | b.Sub Professional Staff | |||
8 | 2.01 | Asst. Quality cum Material Expert | 36 | Man-month | |
9 | 2.02 | Assitant Highway Maintenance Engineer - 1 | 36 | Man-month | |
10 | 2.03 | Assitant Highway Maintenance Engineer - 2 | 36 | Man-month | |
11 | 2.04 | CAD Expert | 6 | Man-month | |
12 | 2.05 | Electrical Engineer | 6 | Man-month | |
13 | 2.06 | Horticulture Expert | 18 | Man-month | |
14 | 2.07 | Quantity Surveyor | 6 | Man-month | |
15 | 2.08 | HTMS / Toll Expert | 6 | Man-month | |
16 | 3 | c. Support Staff | |||
17 | 3.01 | Technical Supervisor( Construction/Maintenance)-1 | 36 | Man-month | |
18 | 3.02 | Technical Supervisor( Construction/Maintenance)-2 | 36 | Man-month | |
19 | 3.03 | Technical Supervisor( Construction/Maintenance)-3 | 36 | Man-month | |
20 | 3.04 | Technical Supervisor( Construction/Maintenance)-4 | 36 | Man-month | |
21 | 3.05 | Office Manager | 36 | Man-month | |
22 | 3.06 | Accountant cum Cashier | 36 | Man-month | |
23 | 3.07 | Steno cum Computer Operator-1 | 36 | Man-month | |
24 | 3.08 | Steno cum Computer Operator-2 | 36 | Man-month | |
25 | 3.09 | Office Boy - 1 | 36 | Man-month | |
26 | 3.1 | Office Boy - 2 | 36 | Man-month | |
27 | 4 | B. REIMBURSABLE\na.Transportation (Fixed rate on rental basis) | |||
28 | 4.01 | Innova/ Scorpio or Equivalent (For Team Leader ) | 36 | Month | |
29 | 4.02 | Indica/Mahendra Jeep or Equivalent (for Resident-cum-Highway Maintenance Engineer and other) | 144 | Month | |
30 | 5 | b. Duty Travel to Site ( Fixed Costs)-Professional and Sub-Professional Staff | |||
31 | 5.01 | Site to CE Office and back for key personnel | 36 | Trip | |
32 | 5.02 | Site to CE Office and back for Sub professional staff | 12 | Trip | |
33 | 6 | c. Office Rent ( Fixed Costs)-Minimum 200Sqm. Area of Office shall be rented. | |||
34 | 6.01 | Office Rent | 36 | Monthly Rate | |
35 | 7 | C.Miscellaneous Expenses\na). Miscellaneous | |||
36 | 7.01 | Office Supplies, Utilities and Communication ( Fixed Costs) | 36 | Monthly Rate | |
37 | 7.02 | Office Furniture and Equipment (Rental) | 36 | Monthly Rate | |
38 | 8 | b). Reports and Document Printing | |||
39 | 8.01 | Monthly reports ( Operation & Maintenance) | 144 | Rate per Copy | |
40 | 8.02 | Quarterly Reports | 72 | Rate per Copy | |
41 | 8.03 | Monthly report on safety, accident and their analysis | 144 | Rate per Copy | |
42 | 8.04 | Various other reports as provided in the concession Agreement such as Completion Report | 216 | Rate per Copy | |
43 | 9 | c) Reports and Documents\n(i) Condition Assessment | |||
44 | 9.01 | Surface defects detection and roughness measurement using Network Survey Vehicle (6 times survey to be conducted) | 161.37 | Rate per Km | |
45 | 9.02 | Pavement strength measurement using FWD (3 times survey to be conducted) | 161.37 | Rate per Km | |
46 | 9.03 | Bridge inspection using Mobile Bridge Inspection Unit (6 times survey to be conducted) | 161.37 | Rate per Km | |
47 | 9.04 | Road signs inspection using Retro Reflectometer (6 times survey to be conducted) | 161.37 | Rate per Km | |
48 | 10 | ii) Traffic Sampling \n | |||
49 | 10.01 | Traffic Sampling using ATCC (161.37 Km) (3Nos of Traffic Survey Stations) | 6 | Rate per Survey |