| 1 | 1 | Cleaning the existing black topped surface with removal of foreign materials with brooms or soft brushes and finally dusting with old gunny bags and compressed air to receive bituminous surface Including all cost i.e cost of all materials, all labour, all T&P, etc complete in all respect and as per direction of the Engineer- in- charge. | BI01010001010000000000000515BI0100001118 | 11043.9 | Sqm |
|---|
| 2 | 2 | Providing Wet Mix Macadam using crushed stone aggregates as per approved drawing and technical specification as per clause 406, section 900 and all relevant sections/ clauses of the MoRT&H Speification for road & Bridge works (5th Revision) & including all cost i.e cost,conveyance of all matericals,all labour, all T&P, royalty etc complete in all respect and as per direction of the Engineer- in- charge. | BI01010001010000000000000515BI0100001119 | 29.38 | Cum |
|---|
| 3 | 3 | Providing & applying tack coat with rapid setting (RS-1) Bitumen Emulsion on prepared surface including cleaning of road surface and spraying tack coat @ 0.20 K.g / Sqm using mechanical means as per Cluse No. 501, 503 and Section 900 and all relevant sections/ clauses of the Mort&h specification for road and bridgeworks of Ministry of Road Transfport& Highway (5th Revision) & Including all cost i.e cost ,conveyance of all materials, all labour, all T&P, etc complete in all respect and as per direction of the Engineer- in- charge. | BI01010001010000000000000515BI0100001120 | 11043.9 | Sqm |
|---|
| 4 | 4 | Providing and laying 25mm thick compacted Semi Dense Bituminous Concrete using 60/70 VG-30grade Bitumen and crusher broken hard granite aggregates of specified grading -ii materials premixed with bitumenous binder @ 5 percent of mix and filler transporting the hot mix to work site laying with a hydrostatic paver finisher with sensor control to the required grade and level and alignment rolling with smooth wheeld vibratory and tandom rollers to achieve the desired compaction as per section , 900 and all relevant clauses 501& 508 of the Mort&h specification for road and bridgeworks of Ministry of Road Transfport& Highway (5th Revision) & Including all cost i.e cost ,conveyance ,royality of all materials, all labour, all T&P, etc complete in all respect and as per direction of the Engineer- in- charge. | BI01010001010000000000000515BI0100001121 | 276.1 | Cum |
|---|
| 5 | 5 | Providing road marking with hot applied t hermo plastic compound 2.5mm thick including glass beads @250gms per sqm area,thickness of 2.5mm is exclusive of surface applied glass beads as per IRC:35.The finished surface tobe level,uniform and free from streaks and holes etc. for finished item of work as per approved drawing and technical specification complete in all respect as per Section 900 and clause 803 of MoRT&H specification for road and bridge work (5th Revision) & including cost ,conveyance of all materials, all labour, all T&P, etc complete in all respect and as per direction of the Engineer- in- charge. | BI01010001010000000000000515BI0100001122 | 357 | Sqm |
|---|
| 6 | 6 | Construction of embankment with approved materials obtained from borrow pits with all leads and lifts transporting to site spreading, grading slope and compacting to meet required etc complete as per Clause No 305, section 900 and all relevant sections/ clauses of the Mort&h specification for road and bridgeworks of Ministry of Road Transfport& Highway (5th Revision) & Including all cost i.e cost of all materials, all labour, all T&P, royalty etc complete in all respect and as per direction of the Engineer- in- charge.(Including Royality of Earth) | BI01010001010000000000000515BI0100001123 | 2245.38 | Cum |
|---|