| 1 | 1 | Excavation for foundation in earth, soil of all types, sand, gravel and soft murum, including removing the excavated material up to a distance of 50 m. beyond the building area and stacking and spreading as directed, dewatering, preparing the bed for the foundation and necessary back filling, ramming, watering including shoring and strutting etc. complete. (Lift upto 1.5 m.) By Mechanical Means Bd.A.1 Page No. 259 | 1 | 16.848 | PerCu.M. |
|---|
| 2 | 2 | Providing and laying Cast in situ/Ready Mix cement concrete in M-10 of trap/ granite/ quartzite/ gneiss metal for foundation and bedding including bailing out water, Steel centering, formwork, laying/pumping, compacting, roughening them if special finish is to be provided, finishing if required and curing complete, with fully automatic micro processor based PLC with SCADA enabled reversible Drum Type mixer/concrete Batch mix plant (Pan mixer) etc. complete. With fine aggregate (Natural Sand / Crushed sand VSI Grade finely washed etc) Bd. E. 1 Page No. 287 | 2 | 1.872 | PerCu.M. |
|---|
| 3 | 3 | Providing and laying in situ /Ready Mix cement concrete M-20 of trap / granite /quartzite/ gneiss metal for R.C.C. work in foundations like raft, strip foundations, grillage and footings of R.C.C. columns and steel stanchions etc. including bailing out water, Steel centering formwork, laying/pumping cover blocks, compaction and curing roughening the surface if special finish is to be provided (Excluding reinforcement and structural steel) etc. complete, with fully automatic micro processor based PLC with SCADA enabled reversible Drum Type mixer/ concrete Batch mix plant (Pan mixer) etc. complete. With fine aggregate (Natural Sand / Crushed sand VSI Grade finely washed etc) Bd.F.3 Page No. 298 and B.7, Page No.38 | 3 | 3.159 | PerCu.M. |
|---|
| 4 | 4 | Providing and laying Cast in situ/Ready Mix cement concrete M-20 of trap / granite /quartzite/ gneiss metal for R.C.C. columns as per detailed designs and drawing or as directed including steel centering, formwork, cover blocks, laying/pumping, compaction finishing the formed surfaces with cement mortar 1:3 of sufficient minimum thickness to give a smooth and even surface or roughening if special finish is to be provided and curing etc. complete,(Excluding reinforcement and structural steel).with fully automatic micro processor based PLC with SCADA enabled reversible Drum Type mixer/ concrete Batch mix plant (Pan mixer) etc. complete. With fine aggregate (Natural Sand / Crushed sand VSI Grade finely washed etc) Bd.F.5 Page No. 300 and B.7, Page.No. 38 | 4 | 1.884 | PerCu.M. |
|---|
| 5 | 5 | Providing and laying Cast in situ/Ready Mix cement concrete M-20 of trap / granite /quartzite/ gneiss metal for R.C.C. beams and lintels as per detailed designs and drawings or as directed including steel centering, formwork, cover blocks, laying/pumping, compactionand roughening the surface if special finish is to be provided and curing etc. complete. (Excluding reinforcement and structural steel). with fully automatic micro processor based PLC with SCADA enabled reversible Drum Type mixer/ concrete Batch mix plant (Pan mixer) etc. complete. With fine aggregate (Natural Sand / Crushed sand VSI Grade finely washed etc) Bd.F.6 Page No. 300 and B.7, Page No.38 | 5 | 2.732 | PerCu.M. |
|---|
| 6 | 6 | Providing and laying Cast in situ/Ready Mix cement concrete in M-20 of trap/ granite/ quartzite/ gneiss metal for R.C.C. pardi of required thickness including steel centering, formwork, cover blocks, laying/pumping, compacting , curing , finishing and rougheningthem if special finish is to be provided and curing complete.(Excluding reinforcement and structural steel).with fully automatic micro processor based PLC with SCADA enabled reversible Drum Type mixer/ concrete Batch mix plant (Pan mixer) etc. complete. With fine aggregate (Natural Sand / Crushed sand VSI Grade finely washed etc) Bd.F.11 Page No. 304 and B.7, Page No. 38 | 6 | 5.94 | PerCu.M. |
|---|
| 7 | 7 | Providing and fixing in position TMT - FE - 500 bar reinforcement of various diameters for R.C.C. pile caps, footings, foundations, slabs, beams columns, canopies, staircase, newels, chajjas, lintels pardis, copings, fins, arches etc. as per detailed designs, drawings and schedules. including cutting, bending, hooking the bars, binding with wires or tack welding and supporting as required complete. Bd.F.17, Page No. 306 | 7 | 0.808 | M.T. |
|---|
| 8 | 8 | Providing internal cement plaster 20mm thick in two coats in cement mortar 1:5 without neeru finish, to concrete, brick surface, in all positions including scaffolding and curing etc. complete | 8 | 128.13 | PerSq.M. |
|---|
| 9 | 9 | Providing and applying two coats of water proof cement paint of approved manufacture and of approved colour to old plastered surfaces including scaffolding if necessary, cleaning and preparing the surface, watering for two days etc. complete. | 9 | 128.13 | PerSq.M. |
|---|
| 10 | 10 | In SSR for items of supply of Rubble, Murum, Soil, 60mm./40mm. metal (Hand broken), royalty charges are not included in the rates. For the items of sand and crushed metal rates are inclusive of royalty charges.Prevalent Royalty charges shall be separately considered while preparing estimate and shall be part of Schedule-B of tender.Any revision in Royalty charges shall be included in the rate analysis of the respective item. If there is variation in Royalty charges the difference shall be paid extra over the items to the contractor and shall be recovered if the Royalty rates are reduced by Govt.i.e Revenue department [As per Govt. of Maharashtra, Revenue and Forest Departments Gazette No.67 Dt.15 May,2015. States that the royalty charges of Rs.141.34/Cu.M. ) are considered.ROYALTY CHARGES FOR SAND | 10 | 9.912 | PerCu.M. |
|---|
| 11 | 11 | Laboratory testing charges are not considered in the Rate Abstracts. Where ever required separate item shall be taken in the estimate for material testing charges, on the basis of testing frequency and charges fixed by Vigilance & Quality Control Circle, for the current year and shall form part of tender. testing of material by Quality control and certified quality must be use by contractor. CONCRETE Compressive Strength of C. C. Cube (Set of 3 Cubes) | 11 | 1 | No. |
|---|
| 12 | 12 | PART II- ADD 12% GST | 12 | 1 | GST |
|---|
| 13 | 13 | 1% FOR LABOUR INSURANCE | 13 | 1 | LABOUR INSURANCE |
|---|
| 14 | Total in Figures | | | | |
|---|