Public Works Department-PWD has published D/W- Restoration Works To Veli-Kadinamkulam Road Between Ch 4/500 And 6/000 In Connection With Kwa/Jnnurm- Improvements To Water Supply Scheme To Vpm Muncipal Corporation And Adjoining Panchayaths- Strengthening , Distribution Net Work-Supplying , Layin . Submission Date for this Tender is 20-01-2021. Road Work Tenders in Thiruvananthapuram Kerala. Bidders can get complete Tender details and download the document.
Work Name:D/W- Restoration works to Veli-Kadinamkulam road between CH: 4/500 and 6/000 in connection with KWA/JNNURM- Improvements to water supply scheme to Tvpm Muncipal Corporation and adjoining Panchayaths- strengthening, distribution net work-supplying, laying, testing and commissioning of PVC pipes (WP7). | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Restoration work | BI01010001010000000000000515BI0100001113 | ||
2 | 1.01 | 3.6 : Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000mExcavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m | BI01010001010000000000000515BI0100001114 | 485.38 | cum |
3 | 1.02 | 3.15 : Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres by Mechanical Means <br>Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead upto 1000 metres by Mechanical Means | BI01010001010000000000000515BI0100001115 | 364 | sqm |
4 | 1.03 | 4.2.A.2 : Construction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. <br>\nGrading-IV - For lower sub base - Mix in Place Method <br>Construction of granular sub-base by providing graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. Grading-IV - For lower sub base - Mix in Place Method | BI01010001010000000000000515BI0100001116 | 277.36 | cum |
5 | 1.04 | 4.12 : Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. | BI01010001010000000000000515BI0100001117 | 251.7 | cum |
6 | 1.05 | 5.1.a : Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means.Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means. | BI01010001010000000000000515BI0100001118 | 1750.8 | sqm |
7 | 1.06 | 5.2.a : Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom.Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. | BI01010001010000000000000515BI0100001119 | 6175.8 | sqm |
8 | 1.07 | 5.3.2.a : Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder (VG 30), transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction.<br>\nFor Grading II - (19 mm nominal size)<br>Providing and laying bituminous macadam with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder (VG 30), transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction.For Grading II - (19 mm nominal size) | BI01010001010000000000000515BI0100001120 | 87.54 | cum |
9 | 1.08 | 5.6.2.a : Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder( NRMB) @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects\nGrading - II (13.2 mm Nominal Size)<br>Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder( NRMB) @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respectsGrading - II (13.2 mm Nominal Size) | BI01010001010000000000000515BI0100001121 | 146.802 | cum |
10 | 1.09 | 3.17 : Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2.Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2. | BI01010001010000000000000515BI0100001122 | 384 | cum |