| 1 | 1 | Fabrication of Heavy section without length wise welded joints (Sectional weight 14Kg/Mtr and above). | item1 | 12 | MT |
|---|
| 2 | 2 | Fabrication of Heavy section with length wise welded joints (Sectional weight 14Kg/Mtr and above). | item2 | 3 | MT |
|---|
| 3 | 3 | Fabrication of Light section (sectional weight below 14Kg/Mtr) | item3 | 12.6 | MT |
|---|
| 4 | 4 | Labour charges for erection of structure Heavy,section (sectional weight 14Kg/Mtr and above) | item4 | 15 | MT |
|---|
| 5 | 5 | Labour charges for erection of Light section (sectional weight below 14Kg/Mtr) | item5 | 12.6 | MT |
|---|
| 6 | 6 | Labour for rust removing,cleaning painting of first primer coat(Red - Oxide) of all sections including cost of paint , brush & consumables. | item6 | 27.6 | MT |
|---|
| 7 | 7 | Labour for removing,cleaning painting(Aluminium) of first finishing coat of all sections including cost of paint , brush & consumables. | item7 | 27.6 | MT |
|---|
| 8 | 8 | Labour for painting (Aluminium) of second finishing coat of all sections including cost of paint , brush & consumables. | item8 | 27.6 | MT |
|---|
| 9 | 9 | Labour for erection with own crane arrangement, including providing holes wherewere required , fixing junction box, other consumables, as directed by the field Engineer. - 110 KV CT, PT, NCT (One Single phase unit) | item9 | 3 | Nos. |
|---|
| 10 | 10 | Labour for erection of 33/22/11KV CT,PT,NCT. Reactor, auto recloser (one S.Ph or 3Ph. Unit) including providing holes wherevere required , as directed by the field Engineer. Using manual labour or crane own arrangement 11 KV without using Board crane (one single unit) | item10 | 21 | Nos. |
|---|
| 11 | 11 | Labour for loading, transporting, unloading and erection including fitting switch cubicals, air comp. units and providing air and gas pipeline for breaker without using board crane including the cost of gada cloth, taflan tape and other consumables, including support structure poles, cutting, jointing, bending of pipes whereever required and SF6 gas filling as directed by the field engineer SF6 Circuit Breaker 110KV Breakers | item11 | 1 | No. |
|---|
| 12 | 12 | Labour for loading, transporting, unloading and erection including fitting switch cubicals, air comp. units and providing air and gas pipeline for breaker without using board crane including the cost of gada cloth, taflan tape and other consumables, including support structure poles, cutting, jointing, bending of pipes whereever required and SF6 gas filling as directed by the field engineer VCB/SF6 11 KV Breakers | item12 | 6 | Nos. |
|---|
| 13 | 13 | Labour for erection of AB Switches, including cost of lubricant, consumable, and wiring (if necessary) allinment, checking of operation by both manual and electrical (if necessary) and as directed by the field Engineer. 110 KV Hand operated isolator without earth | item13 | 5 | Nos. |
|---|
| 14 | 14 | Labour for erection of AB Switches, including cost of lubricant, consumable, and wiring (if necessary) allinment, checking of operation by both manual and electrical (if necessary) and as directed by the field Engineer. 11 KV Hand operated isolator without earth | item14 | 12 | Nos. |
|---|
| 15 | 15 | Labour for erection of LAS, single stage or multi stage including fabrication of base if required . 110 KV L.A.S. Station type with surge monitor | item15 | 3 | Nos. |
|---|
| 16 | 16 | Labour for erection of LAS, single stage or multi stage including fabrication of base if required .11 KV Station type LAS | item16 | 6 | Nos. |
|---|
| 17 | 17 | Labour for erection of LAS, single stage or multi stage including fabrication of base if required . 11 KV Distribution type LAS | item17 | 12 | Nos. |
|---|
| 18 | 18 | Labour for erection of Insulators single pole stack up right, under hang or suspension. Single pole stack 110 KV | item18 | 24 | Nos. |
|---|
| 19 | 19 | Labour for erection of Insulators single pole stack up right, under hang or suspension. Single pole stack 110 KV (LC Work) | item19 | 9 | Nos. |
|---|
| 20 | 20 | Labour for erection of Insulators single pole stack up right, under hang or suspension. Single pole stack 11 KV | item20 | 30 | Nos. |
|---|
| 21 | 21 | Labour for Erection of Simplex Panel/battery charger | item21 | 6 | Nos. |
|---|
| 22 | 22 | Labour charges for removing rust, primer coat, first & second coat painting both sides & in M.S.board RSJoist & yard light pole etc., including cost of enamel paint (Dulex,Asian, Berger preferred) and other consumables directed by the field Engineer. | item22 | 100 | m2 |
|---|
| 23 | 23 | Labour charges for writting details in Finished Surface boards including cost of enamal paint (Dulex,Asian,Berger preferred) and other Condsumables as directed by the field Engineer | item23 | 15 | m2 |
|---|
| 24 | 24 | Manufacturing and supply of bolt of required length of 18 - 20 mm dia GI rod including cost of GI rod and 2Nos GI nuts washer as directed by the field Engineer. Grout bolt Eye bolt. | item24 | 60 | kgs |
|---|
| 25 | 25 | Supply and provision of M8,M9, M10,M12, M16 full thread GI bolt, nuts GI washer of various size for erection of insulator or any other purpose wherever required and as directed by the field Engineer. | item25 | 600 | kgs |
|---|
| 26 | 26 | Supply and fixing of wooden board 25mm/Hylam sheet 10mm thick for fixing fuse units wherever required As directed by the field Engineer. | item26 | 2 | m2 |
|---|
| 27 | 27 | Supply of the R.S. Joist 200 X 100 mm as per relevent IS of various required lengths for Structures and other purposes as directed by the Field Engineer. | item27 | 14.5 | MT |
|---|
| 28 | 28 | Supply of the MS Channel 125 X 65 mm as per relevent IS of various required lengths for Structures and other purposes as directed by the Field Engineer. | item28 | 3.3 | MT |
|---|
| 29 | 29 | Supply of the MS Channel 100 X 50 mm as per relevent IS of various required lengths for Structures and other purposes as directed by the Field Engineer. | item29 | 5 | MT |
|---|
| 30 | 30 | Supply of MS Rod 40 mm as per relevent IS of various required lengths for Structures and other purposes as directed by the Field Engineer. | item30 | 3.9 | MT |
|---|
| 31 | 31 | Supply of the MS Angle 100 X 100 X 8 mm as per relevent IS of various required lengths for Structures and other purposes as directed by the Field Engineer. | item31 | 0.6 | MT |
|---|
| 32 | 32 | Supply of MS Angle 50 X 50 X 6 mm as per relevent IS of various required lengths for Structures and other purposes as directed by the Field Engineer. | item32 | 2.7 | MT |
|---|
| 33 | 33 | Supply of MS/RTS Rod 20 mm as per relevent IS of various required lengths for Structures and other purposes as directed by the Field Engineer. | item33 | 0.55 | MT |
|---|
| 34 | 34 | Supply of the MS Flat 50 X 8 mm as per relevent IS of various required lengths for Structures and other purposes as directed by the Field Engineer. | item34 | 4.3 | MT |
|---|
| 35 | 35 | Supply of the MS Flat 65 X 10 mm as per relevent IS of various required lengths for Structures and other purposes as directed by the Field Engineer. | item35 | 7.5 | MT |
|---|
| 36 | 36 | Supply of MS Chequerred Plate 6 mm as per relevent IS of various required lengths for Structures and other purposes as directed by the Field Engineer. | item36 | 0.5 | MT |
|---|
| 37 | 37 | Transporting of Iron & Steel items from any stock yard to site including loading and un loading charges. | item37 | 42.85 | MT |
|---|
| 38 | 38 | Fabrication and fixing of bell mouth providing jumper connetion in the solid core/PT insulator including the cost of GI pipe 50mm dia 1mtr and other consumables as directedby the field engineer. | item38 | 9 | Nos. |
|---|
| 39 | 39 | Labour for loading,or unloading or shifting of materials without using Boards Crane (one operation) non fragile material | item39 | 15 | MT |
|---|
| 40 | 40 | Labour for loading,or unloading or shifting of materials without using Boards Crane (one operation) fragile material | item40 | 15 | MT |
|---|
| 41 | 41 | Labour for loading , or un loading ,or shifting of 110KV and above breakers ,CT, PT Etc., by own crane arrangement. (One operation) | item41 | 10 | MT |
|---|
| 42 | 42 | Supply of good Quality Aluminium Paint | item42 | 200 | Ltrs. |
|---|
| 43 | 43 | Supply of good Quality red oxide Paint | item43 | 200 | Ltrs. |
|---|
| 44 | 44 | Supply of good Quality A.C.Black Paint | item44 | 50 | Ltrs. |
|---|
| 45 | 45 | Supply and providing of 600mm mean dia,300mm height 36mm thick cement coller for identification of earth electrode location including 1primer and 2 coats of colour wash as directed by field Engineer. | item45 | 36 | Nos. |
|---|
| 46 | 46 | Labour machineries, consumables for erection of earthmat & earth raisers, as directed by the field Engineer at site | item46 | 11.2 | MT |
|---|
| 47 | 47 | Machineries,consumable for fabrication of earth electrode 10Mtr/6Mtr length or as directed by the field Engineer. | item47 | 3.2 | MT |
|---|
| 48 | 48 | Labour machineries, consumables for fabrication & erection of earth spikes. | item48 | 19 | Nos. |
|---|
| 49 | 49 | Providing 140/150mm dia bore including labour,lead,lift etc., including mobilization in all types of soil and erection of earth electrode, supply and providing A4 Grade bentonite powder with 5% common salt mixed with available site clay soil with water 5Kg/meter depth in earth bore and pouring water and tightening of earth bore, upto satisfactory earth | item49 | 360 | RM |
|---|
| 50 | 50 | Earth work excavation in all classes of soil with initial lead of 10 mtrs and lift of 2 mtrs. etc complete In Hard Gravely Soil | item50 | 175 | m3 |
|---|
| 51 | 51 | Labour charges for erection of bus bar including fabrication and any modification of end clamp wherever necessary and as directed by the field Engineer with making required bends- using 75 mm IPS aluminium tube | item51 | 6 | Nos. |
|---|
| 52 | 52 | Labour charges for erection of bus bar including fabrication and any modification of end clamp wherever necessary and as directed by the field Engineer without making required bends- using 75 mm IPS aluminium tube | item52 | 9 | Nos. |
|---|
| 53 | 53 | Labour charges for erection of bus bar including fabrication and any modification of end clamp wherever necessary and as directed by the field Engineer without making required bends- using 50 mm IPS aluminium tube | item53 | 15 | Nos. |
|---|
| 54 | 54 | Labour for erection of droppers and jumpers including fabrication and any modification of end clamps wherever necessary and as directed by the field engineer. | item54 | 150 | Nos. |
|---|
| 55 | 55 | Labour for erection of droppers and jumpers including fabrication and any modification of end clamps wherever necessary and as directed by the field engineer.(LC Work) | item55 | 20 | Nos. |
|---|
| 56 | 56 | Supply and glanding of ISI mark cablegland of 15 mm size of reputed make including removing of insulation of cable and providing suitable holes as required and as directed by the field engineer | item56 | 75 | Nos. |
|---|
| 57 | 57 | Supply and glanding of ISI mark cablegland of 19 mm size of reputed make including removing of insulation of cable and providing suitable holes as required and as directed by the field engineer. | item57 | 75 | Nos. |
|---|
| 58 | 58 | Supply and glanding of ISI mark cablegland of 25 mm size of reputed make including removing of insulation of cable and providing suitable holes as required and as directed by the field engineer | item58 | 50 | Nos. |
|---|
| 59 | 59 | Supply and glanding of ISI mark cablegland of 32 mm size of reputed make including removing of insulation of cable and providing suitable holes as required and as directed by the field engineer | item59 | 10 | Nos. |
|---|
| 60 | 60 | Labour for erection of cable glands | item60 | 210 | Nos. |
|---|
| 61 | 61 | Supply and termination of cable core end including cost of cable socket ,lug, ferrules,strap etc,as per cable schedule and as directed by the field Engineer . | item61 | 1500 | Nos. |
|---|
| 62 | 62 | Labour for erection in duct/trunch including the cost of Alu.tag for identification Up to 8 Core | item62 | 5 | Kms. |
|---|
| 63 | 63 | Labour for erection in duct/trunch including the cost of Alu.tag for identification Above 8 Core | item63 | 0.4 | Kms. |
|---|
| 64 | 64 | Labour charges for laying of cable & clamping in structure Up to 8 Core | item64 | 0.5 | Kms. |
|---|
| 65 | 65 | Labour charges for laying of cable & clamping in structure Above 8 Core | item65 | 0.1 | Kms. |
|---|
| 66 | 66 | Supply fixing of ISI mark bakelite HRC/ rewireable fuse holder in panels/boxes for AC/DC/PT circuits wherever required as directed by the field Engineer. Supply fixing of ISI mark HRC Fuse without holder of reputed make in panels /boxes for AC/DC/PT Circuits wherever required as directed by the field Engineer. 16 Amps (16 Amps Fuse base +10 Amps Fuse link) | item66 | 20 | Nos. |
|---|
| 67 | 67 | Supply and fixing of disconnected type terminal block suitable for CT Circuits in panels/box as required & as directed by the field Engineer. | item67 | 150 | Nos. |
|---|
| 68 | 68 | Supply of Tubular type yard light Poles as per drawing 8.0 mtr long stepped tubular pole for yard light (each) | item68 | 10 | Nos. |
|---|
| 69 | 69 | Supply of Tubular type yard light Poles as per drawing 5.5 mtr long stepped tubular pole for yard light (each) | item69 | 10 | Nos. |
|---|
| 70 | 70 | Supply and Erection of LED lamp 72W fitting with fixture and fuse box including wiring and testing for burning condition including the cost of 15 amps 2way strip connector and other consumables. | item70 | 20 | Nos. |
|---|
| 71 | 71 | Labour for erection of yard light pole including laying of cable inside pole | item71 | 20 | Nos. |
|---|
| 72 | 72 | Manufacturing & Supply of yard light box of size 200 X 200 X 150D mm out of 18 SWG M.S.Sheet with cable entry holesm, fixing arrangements for fuse units and mounting clamps as directed by the field engineer including cost of all materials. | item72 | 20 | Nos. |
|---|
| 73 | 73 | Supply & fixing of (Godrej) 6lever Navtal lock with triplicate keys for AB Switch and for any other purpose including the cost of hinges and key token as directed by the Dept. Engineer at site. | item73 | 18 | Nos. |
|---|
| 74 | 74 | Supply and fixing of flexible copper tape/rope for interlinking panel earthing and for any other purpose,on any sizes, including the cost of copper lugs at both ends as directed by the field Engineer. | item74 | 10 | Kg. |
|---|
| 75 | 75 | Fabrication, supply and fixing of A.C. Distribution box of size 750 W X 250 D X 750 H made out of 14 SWG (2mm) M.S. Sheet wherever required as directed by the field engineer. The box shall be vermin proof shall have sturdy hinges, provision for mounting MCB and MCCB, detachable gland plate and locking arrangements including cost of all materials. | item75 | 1 | No. |
|---|
| 76 | 76 | Labour for erection of CT/PT junction box including fabrication of clamp | item76 | 8 | Nos. |
|---|
| 77 | 77 | Labour charges for painting earth raisers by green enamel painting and wherever required including cost of paint(Dulex, Asian Berger perferrd) and other consumables as directed by the field Engineer. | item77 | 1000 | RM |
|---|
| 78 | 78 | Supply fixing of ISI mark porcelain rewirable fuse unit of reputed make in panels, boxes for AC Circuits wherever required as directed by the Field Engineer. - 200 Amps. | item78 | 3 | Nos. |
|---|
| 79 | 79 | Supply fixing of ISI mark bakelite HRC/ rewireable fuse holder in panels/boxes for AC/DC/PT circuits wherever required as directed by the field Engineer. - 63 Amps. | item79 | 6 | Nos. |
|---|
| 80 | 80 | Supply fixing of ISI mark HRC Fuse without holder of reputed make in panels /boxes for AC/DC/PT Circuits wherever required as directed by the field Engineer. - 63 Amps. | item80 | 6 | Nos. |
|---|
| 81 | 81 | Manufacturing & supply of sand drum made out of oil drum of size 580 mm dia and 420 mm height with conical cover made out of tin sheet provided with handle including cost of barrel,sand and as directed by field Engineer. | item81 | 4 | Nos. |
|---|
| 82 | 82 | Fabrication, supply and fitting of CT / PT Junction box of size 400 W X 150 D X 300 H made out of 14 SWG (2mm) M.S. Sheet with 16 Nos. termination of stand type with two nuts and washers suitable for 4 Sqmm copper cable and 5 Nos. 1\" gland wherever required as directed by the field engineer. The box shall be vermin proof shall have sturdy hinges, provision for mounting terminal blocks and locking arrangements. (size - 400 W X 150 D X 300 H ) | item82 | 7 | Nos. |
|---|
| 83 | 83 | Supply of Rubber Mat of size 2000 X 1000 X 10 mm | item83 | 6 | Nos. |
|---|
| 84 | 84 | Supply of following Fire Fighting Equipments Fire extinguisher foam type trolley mounted 50 Ltr capacity with accessories | item84 | 1 | No. |
|---|
| 85 | 85 | Supply of Fire extinguisher DCP type trolley mounted 25 KG capacity with accessories | item85 | 2 | Nos. |
|---|
| 86 | 86 | Supply of Fire extinguisher foam type trolley mounted 9 Ltr capacity with accessories | item86 | 6 | Nos. |
|---|
| 87 | 87 | Supply of Fire extinguisher DCP type Portable 10 KG capacity | item87 | 3 | Nos. |
|---|
| 88 | 88 | Supply of Fire extinguisher DCP type Portable 5 KG capacity | item88 | 4 | Nos. |
|---|
| 89 | 89 | Manufacturing & supply of fire bucket of 10 lit capacity made out of 26Swg (0.46 mm) M.S.Sheet painted with white & red namal paint in side & out side respectively bottom of bucket shall be ` U ` shapped out side of the bucket shall be written as Fire in English /Tamil in white enamal paint including cost of all materials. | item89 | 10 | Nos. |
|---|
| 90 | 90 | Manufacturing and supply & fixing of LC/Key board out of 75x 25 mm Alu. frame embedded with 12 mm pre laminated wood particle board using screw on rear 2 Nos plain glass of 5 mm thick fixed with metal roller moving on Alu.channel should be provided on front with locking arrangements.LG glass piece should be fastened on the glass shutters for opening and clossing wall clamp made out of 6mm plate should be provided on as per drawing and as directed by the field Engineer including cost of all materials. (Letter size to be specied, company name will not be provided in the LC B oard) | item90 | 2 | m2 |
|---|
| 91 | 91 | Supply and erection of `B` Class GI pipe for extension of tandum /down pipe for AB Switches and for any other work as required by and as directed by field Engineer including cost of GI Pipe.- 40 mm | item91 | 10 | mtrs. |
|---|
| 92 | 92 | Labour charges for drawing layout and writing details in LC/Key board including cost of enamel paint (Dulex,Asian, Berger preferred) and Other consumables as directed by the field Engineer. | item92 | 15 | m2 |
|---|
| 93 | 93 | Fabrication, Supply & fixing of main equipment board of Various size & Fire stand & etc, as per drawing and as directed by the Executive Engineer , including cost of all materials. | item93 | 200 | Kg. |
|---|
| 94 | 94 | Supply fixing of ISI make MCB(AC) in panels/Boxes of reputed make as directed by the field Engineer.- 3Pole 32 Amps | item94 | 5 | Nos. |
|---|
| 95 | 95 | Providing watch ward | item95 | 240 | Nos. |
|---|
| 96 | 96 | GST for bidders within TamilNadu | | | |
|---|
| 97 | 96.01 | SGST | item96 | 1 | percentage |
|---|
| 98 | 96.02 | CGST | item97 | 1 | percentage |
|---|
| 99 | 97 | GST for bidders outside TamilNadu (IGST) | item98 | 1 | percentage |
|---|