| 1 | 1 | Tack coat using VG-10 grade bitumen Over normal bituminous surfaces @0.35kg/sqm, | BI01010001010000000000000515BI0100001112 | | |
|---|
| 2 | 1.01 | Surface improvement by 30 mm BC on Km -15,16 of Gadarpur-Dineshpur-Matkota-Haldwani motor raod SH-05 (Length- 1.20 Km) | BI01010001010000000000000515BI0100001113 | 23403 | Sqm |
|---|
| 3 | 1.02 | Surface improvement by 30 mm BC on Bhurarani-Chatarpur motor road (Length- 7.00 Km) | BI01010001010000000000000515BI0100001114 | 39873 | Sqm |
|---|
| 4 | 1.03 | Surface improvement by 30 mm BC on Km 01, 02 & 06 to 09 of Gadarpur-Milakkhanam motor road | BI01010001010000000000000515BI0100001115 | 26826 | Sqm |
|---|
| 5 | 2 | Bituminous Macadam\n(Providing and laying bituminous macadam with 100-120 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading premixed with bituminous binder, transported to site, laid over a previously prepared surface with paver finisher to the required grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the desired compaction) for GradingII(19 mm nominal size) | BI01010001010000000000000515BI0100001112 | | |
|---|
| 6 | 2.01 | Surface improvement by 30 mm BC on Km -15,16 of Gadarpur-Dineshpur-Matkota-Haldwani motor raod SH-05 (Length- 1.20 Km) | BI01010001010000000000000515BI0100001113 | 110.3 | Cum |
|---|
| 7 | 2.02 | Surface improvement by 30 mm BC on Bhurarani-Chatarpur motor road (Length- 7.00 Km) | BI01010001010000000000000515BI0100001114 | 69 | Cum |
|---|
| 8 | 2.03 | Surface improvement by 30 mm BC on Km 01, 02 & 06 to 09 of Gadarpur-Milakkhanam motor road | BI01010001010000000000000515BI0100001115 | 5.5 | Cum |
|---|
| 9 | 3 | Providing and laying Bituminous Concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects for Grading-II (bituminous binder @ 5.4 % of mix)) | BI01010001010000000000000515BI0100001112 | | |
|---|
| 10 | 3.01 | Surface improvement by 30 mm BC on Km -15,16 of Gadarpur-Dineshpur-Matkota-Haldwani motor raod SH-05 (Length- 1.20 Km) | BI01010001010000000000000515BI0100001113 | 636 | Cum |
|---|
| 11 | 3.02 | Surface improvement by 30 mm BC on Bhurarani-Chatarpur motor road (Length- 7.00 Km) | BI01010001010000000000000515BI0100001114 | 1286.3 | Cum |
|---|
| 12 | 3.03 | Surface improvement by 30 mm BC on Km 01, 02 & 06 to 09 of Gadarpur-Milakkhanam motor road | BI01010001010000000000000515BI0100001115 | 801.5 | Cum |
|---|
| 13 | 4 | Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. | BI01010001010000000000000515BI0100001112 | | |
|---|
| 14 | 4.01 | Surface improvement by 30 mm BC on Bhurarani-Chatarpur motor road (Length- 7.00 Km) | BI01010001010000000000000515BI0100001114 | 190 | Cum |
|---|
| 15 | 4.02 | Surface improvement by 30 mm BC on Km 01, 02 & 06 to 09 of Gadarpur-Milakkhanam motor road | BI01010001010000000000000515BI0100001115 | 960 | Cum |
|---|
| 16 | 5 | Maintenance of Earhen shoulder (stripping of excess soil) Stripping excess soil from the shoulder surface to achieve the approved level and compacting with plate compactor at OMC as per drawings and Technical Specification Clause 1903 | BI01010001010000000000000515BI0100001112 | | |
|---|
| 17 | 5.01 | Surface improvement by 30 mm BC on Km -15,16 of Gadarpur-Dineshpur-Matkota-Haldwani motor raod SH-05 (Length- 1.20 Km) | BI01010001010000000000000515BI0100001113 | 3000 | Sqm |
|---|
| 18 | 5.02 | Surface improvement by 30 mm BC on Bhurarani-Chatarpur motor road (Length- 7.00 Km) | BI01010001010000000000000515BI0100001114 | 3000 | Sqm |
|---|
| 19 | 5.03 | Surface improvement by 30 mm BC on Km 01, 02 & 06 to 09 of Gadarpur-Milakkhanam motor road | BI01010001010000000000000515BI0100001115 | 1680 | Sqm |
|---|