| 1 | 1 | Supply of AXGA161 - API Horizontal Centrifugal Pumps | | | |
|---|
| 2 | 1.01 | Supply of AXGA161- API Horizontal Centrifugal Pumps- 301-P-303 A/B, as specified in Material Requisition. | item1 | 2 | No. |
|---|
| 3 | 1.02 | Supply of AXGA161- API Horizontal Centrifugal Pumps- 301-P-304, as specified in Material Requisition. | item2 | 1 | No. |
|---|
| 4 | 1.03 | Supply of AXGA161- API Horizontal Centrifugal Pumps - 301-P-305 A/B, as specified in Material Requisition. | item3 | 2 | No. |
|---|
| 5 | 1.04 | Supply of AXGA161- API Horizontal Centrifugal Pumps - 301-P-307 A/B, as specified in Material Requisition. | item4 | 2 | No. |
|---|
| 6 | 1.05 | Supply of AXGA161- API Horizontal Centrifugal Pumps - 301-P-309 A/B/C/D, as specified in Material Requisition. | item5 | 4 | No. |
|---|
| 7 | 1.06 | Supply of AXGA161- API Horizontal Centrifugal Pumps - 301-P-310 A/B/C, as specified in Material Requisition. | item6 | 3 | No. |
|---|
| 8 | 1.07 | Supply of AXGA161- API Horizontal Centrifugal Pumps - 301-P-318, as specified in Material Requisition. | item7 | 1 | No. |
|---|
| 9 | 2 | Charges for Site Supervision of erection, testing and commissioning of AXGA161 - API Horizontal Centrifugal Pumps- 301-P-303 A/B | | | |
|---|
| 10 | 2.01 | Per diem charges for upto 8 hours work on normal working days. | item8 | 2 | Man Day |
|---|
| 11 | 2.02 | Overtime rate / hour beyond normal 8 hours work on normal working days. | item9 | 1 | Per Hour |
|---|
| 12 | 2.03 | Overtime rate / hour for work on weekly off days / holidays (as applicable to Refinery site). | item10 | 1 | Per Hour |
|---|
| 13 | 3 | Charges for Site Supervision of erection, testing and commissioning of AXGA161 - API Horizontal Centrifugal Pumps- 301-P-304 | | | |
|---|
| 14 | 3.01 | Per diem charges for upto 8 hours work on normal working days. | item11 | 2 | Man Day |
|---|
| 15 | 3.02 | Overtime rate / hour beyond normal 8 hours work on normal working days. | item12 | 1 | Per Hour |
|---|
| 16 | 3.03 | Overtime rate / hour for work on weekly off days / holidays (as applicable to Refinery site). | item13 | 1 | Per Hour |
|---|
| 17 | 4 | Charges for Site Supervision of erection, testing and commissioning of AXGA161 - API Horizontal Centrifugal Pumps - 301-P-305 A/B | | | |
|---|
| 18 | 4.01 | Per diem charges for upto 8 hours work on normal working days. | item14 | 2 | Man Day |
|---|
| 19 | 4.02 | Overtime rate / hour beyond normal 8 hours work on normal working days. | item15 | 1 | Per Hour |
|---|
| 20 | 4.03 | Overtime rate / hour for work on weekly off days / holidays (as applicable to Refinery site). | item16 | 1 | Per Hour |
|---|
| 21 | 5 | Charges for Site Supervision of erection, testing and commissioning of AXGA161 - API Horizontal Centrifugal Pumps- 301-P-307 A/B | | | |
|---|
| 22 | 5.01 | Per diem charges for upto 8 hours work on normal working days. | item17 | 2 | Man Day |
|---|
| 23 | 5.02 | Overtime rate / hour beyond normal 8 hours work on normal working days. | item18 | 1 | Per Hour |
|---|
| 24 | 5.03 | Overtime rate / hour for work on weekly off days / holidays (as applicable to Refinery site). | item19 | 1 | Per Hour |
|---|
| 25 | 6 | Charges for Site Supervision of erection, testing and commissioning of AXGA161 - API Horizontal Centrifugal Pumps - 301-P-309 A/B/C/D | | | |
|---|
| 26 | 6.01 | Per diem charges for upto 8 hours work on normal working days. | item20 | 2 | Man Day |
|---|
| 27 | 6.02 | Overtime rate / hour beyond normal 8 hours work on normal working days. | item21 | 1 | Per Hour |
|---|
| 28 | 6.03 | Overtime rate / hour for work on weekly off days / holidays (as applicable to Refinery site). | item22 | 1 | Per Hour |
|---|
| 29 | 7 | Charges for Site Supervision of erection, testing and commissioning of AXGA161 - API Horizontal Centrifugal Pumps- 301-P-310 A/B/C | | | |
|---|
| 30 | 7.01 | Per diem charges for upto 8 hours work on normal working days. | item23 | 2 | Man Day |
|---|
| 31 | 7.02 | Overtime rate / hour beyond normal 8 hours work on normal working days. | item24 | 1 | Per Hour |
|---|
| 32 | 7.03 | Overtime rate / hour for work on weekly off days / holidays (as applicable to Refinery site). | item25 | 1 | Per Hour |
|---|
| 33 | 8 | Charges for Site Supervision of erection, testing and commissioning of AXGA161 - API Horizontal Centrifugal Pumps- 301-P-318 | | | |
|---|
| 34 | 8.01 | Per diem charges for upto 8 hours work on normal working days. | item26 | 2 | Man Day |
|---|
| 35 | 8.02 | Overtime rate / hour beyond normal 8 hours work on normal working days. | item27 | 1 | Per Hour |
|---|
| 36 | 8.03 | Overtime rate / hour for work on weekly off days / holidays (as applicable to Refinery site). | item28 | 1 | Per Hour |
|---|
| 37 | 9 | Charges for 2 years Operation and Maintenance Spares for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-303 A/B; Bidder to provide spares price breakup in 2 years Spares BOQ sheet. | item29 | 1 | Lot |
|---|
| 38 | 10 | Charges for 2 years Operation and Maintenance Spares for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-304; Bidder to provide spares price breakup in 2 years Spares BOQ sheet. | item30 | 1 | Lot |
|---|
| 39 | 11 | Charges for 2 years Operation and Maintenance Spares for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-305 A/B; Bidder to provide spares price breakup in 2 years Spares BOQ sheet. | item31 | 1 | Lot |
|---|
| 40 | 12 | Charges for 2 years Operation and Maintenance Spares for AXGA161 - API Horizontal Centrifugal Pumps301-P-307 A/B; Bidder to provide spares price breakup in 2 years Spares BOQ sheet. | item32 | 1 | Lot |
|---|
| 41 | 13 | Charges for 2 years Operation and Maintenance Spares for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-309 A/B/C/D; Bidder to provide spares price breakup in 2 years Spares BOQ sheet. | item33 | 1 | Lot |
|---|
| 42 | 14 | Charges for 2 years Operation and Maintenance Spares for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-310 A/B/C; Bidder to provide spares price breakup in 2 years Spares BOQ sheet. | item34 | 1 | Lot |
|---|
| 43 | 15 | Charges for 2 years Operation and Maintenance Spares for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-318; Bidder to provide spares price breakup in 2 years Spares BOQ sheet. | item35 | 1 | Lot |
|---|
| 44 | 16.01 | Charges for Training at IOCL BARAUNI REFINERY for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-303 A/B | item36 | 1 | Manday |
|---|
| 45 | 16.02 | Chargesfor Training at IOCL BARAUNI REFINERY for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-304 | item37 | 1 | Manday |
|---|
| 46 | 16.03 | Chargesfor Training at IOCL BARAUNI REFINERY for AXGA161 - API Horizontal Centrifugal Pumps - 301-P-305 A/B | item38 | 1 | Manday |
|---|
| 47 | 16.04 | Charges for Training at IOCL BARAUNI REFINERY for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-307 A/B | item39 | 1 | Manday |
|---|
| 48 | 16.05 | Charges for Training at IOCL BARAUNI REFINERY of AXGA161 - API Horizontal Centrifugal Pumps - 301-P-309 A/B/C/D | item40 | 1 | Manday |
|---|
| 49 | 16.06 | Charges for Training at IOCL BARAUNI REFINERY for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-310 A/B/C | item41 | 1 | Manday |
|---|
| 50 | 16.07 | Charges for Training at IOCL BARAUNI REFINERY for AXGA161 - API Horizontal Centrifugal Pumps- 301-P-318 | item42 | 1 | Manday |
|---|