Hindustan Copper Limited-HCL has published Rate Contract For Housekeeping Drains Sewer Lines Horticulture And Miscellaneous Work Etc 2020 21. Submission Date for this Tender is 18-12-2020. Drainage Tenders in HINDUSTAN COPPER LTD TALOJA MIDC AREA TALOJA Maharashtra. Bidders can get complete Tender details and download the document.
Name of Work: HOUSEKEEPING DRAINS SEWER LINES HORTICULTURE AND MISC WORK | |||||
---|---|---|---|---|---|
Sl. No.+11:111:18 | Activity and Item Description | Item Code | Quantity | Frequency | |
1 | 1 | HOUSEKEEPING\nCleaning & Sweeping of the following areas/deptt: Admin building, Plant, Materials & Contract Department, Warehouse, Union Office, Security Office, Canteen, Road connecting to Admn building, Security gate no 1, Plant, Canteen, Natural Gas Stn, Cathode unloading & Cooling tower. Ware house, Store, 2nd gate, etc\na) Entire office floor area, windows, doors, etc.\nb) Toilets. | item-1 | 1 | Daily |
2 | 2 | GARDEN(only inside)\nWater the plants, garden, planting the saplings/trees (As supplied by HCL/TCP), grass mowing, maintain the green areas), removal of weeds, use of fertilizers and pesticides etc both inside and outside of TCP.\nMINIMUM MANPOWER - 2 unskilled labour. | item-2 | 1 | Daily |
3 | 3 | Septic tank\nCleaning of Septic chambers, lines & Septic Tanks by mechanized way: \na) Cathode yard \nb) Canteen \nc) Warehouse | item-3 | 1 | As and when required |
4 | 4 | Drain \nCleaning of existing Drains and Storm Water Collection Tank (approx. 1100 running meter of drains & 2 tanks of 2x3x3 & 5x7x4 meters.) | item-4 | 1 | (One time job) Needs to be completed within 1 week of start date |
5 | 5 | Unwanted Vegetation \nRemoving of unwanted vegetation (from the roots) inside and outside of TCP. Disposal shall be done in house by way of burning in the chimney. | item-5 | 1 | Twice a year (Needs to be completed within 1 week of start date) |
6 | 6 | Cooling tower cleaning\nCleaning of Cooling tower basins Process. | item-6 | 1 | Once in two months |
7 | 7 | Cooling tower cleaning\nCleaning of Cooling tower basins Casting. | item-7 | 1 | Twice in a month |
8 | 8 | Drinking water tank cleaning\nCleaning of 5- Water tanks \na. Admin - 2 tanks \nb. Canteen - 1 tank \nc. Warehouse - 1 tank \nd. Near compressor room - 1 tank | item-8 | 1 | Once very quarter (Needs to be completed within 2 days of start date) |
9 | 9 | Underground MIDC Water tank | item-9 | 1 | Twice in a year (Needs to be completed within 2 days of start date) |
10 | 10 | Over head water tank (Plant)\n 1 No. | item-10 | 1 | Once in a year (Needs to be completed within 2 days of start date) |
11 | 11 | Soluble oil Tank (Plant)\nPlant Soluble Oil tank cleaning and removing mill scale thereof. | item-11 | 1 | Month |