Construction Construction Of Rcc Water Tank Under Coe-Fab , Phase-Ii, College of Fisheries, Lembucherra, West Tripura-Tripura

Central Agricultural University has published Construction Construction Of Rcc Water Tank Under Coe-Fab , Phase-Ii. Submission Date for this Tender is 23-11-2020. Water Tank Tenders in College of Fisheries, Lembucherra, West Tripura Tripura. Bidders can get complete Tender details and download the document.




Tender Notice

26003337
Construction Construction Of Rcc Water Tank Under Coe-Fab , Phase-Ii
Open Tender
Indian
Tripura
College of Fisheries, Lembucherra, West Tripura
23-11-2020

Tender Details

Construction Construction Of Rcc Water Tank Under Coe-Fab , Phase-Ii

Key Value

Document Fees
Refer document
EMD
INR 15973.0 /-
Tender Value
Refer document

BOQ Items

Name of Work: <Construction of RCC water tank under COE-FAB, Phase-II, college of Fisheries>
Sl. No. Item Description Item Code / Make Quantity Units
1 1.01 Earth work in excavation by mechanical means( Hydraulic excavator)/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. all kind of soil. item1 29.31 Cum
2 1.02 Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. All kind of soil item2 19.54 cum
3 1.03 Supplying and filling in plinth, under floor, foundations etc. with sand (fine) from local quarry with all lifts including spreading in horizontal layers, watering, grading to required slope, ramming, consolidating and compacting each layer by using plate compactor or by any suitable method complete. item3 9.03 Cum
4 1.04 Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering -All work uoto plinth level: 1:4:8 ( 1 Cement: 4 fine sand : 8 graded stone aggregate 40 mm nominal size) item4 4.52 Cum
5 1.05 Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto floor five level. Mild steel and Medium\Tensile steel bars. item5 4626.72 Kgs
6 1.06 Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centring, shuttering, finishing and reinforcement--All work upto plinth level: 1:1½:3 ( 1 Cement: 1½ fine sand : 3 graded stone aggregate 20 mm nominal size) item6 20.37 Cum
7 1.07 Centering shuttering including struttings, propping etc. and removal of form work for: Foundations, footings, bases for columns etc. for mass concrete with timber plank item7 125.94 sqm
8 1.08 Secons class brick work in foundation and plinth including cost of all materials as required complete:- In cement mortar 1:4 ( 1 cement : 4 fine sand ). item8 5.95 cum
9 1.09 12 mm cement plaster of mix: In cement mortar 1 : 3 ( 1 cement : 3 fine sand ) item9 216.81 Sqm
10 1.1 Neat cement punning. item10 216.81 Sqm
11 1.11 Providing and fixing G.I. pipes complete with G.I. fittings including trenching and refilling etc. External work (a) 40 mm dia. nominal bore\n item11 49.8 Metres
12 1.12 Making connection of G.I. distribution branch with G.I. main of following sizes by providing and fixing tee, including cutting and threading the pipe etc. complete :(a) 25 to 40 mm nominal bore item12 1 Each
13 1.13 Providing and fixing G.I. Union in G.I. pipe including cutting and threading the pipe and making long screws etc. complete (New work) (a) 40 mm nominal bore item13 6 Each
14 1.14 Providing and fixing gun metal gate valve with C.I. wheel of approved quality (screwed end): 40 mm nominal bore(a) 40 mm nominal bore item14 11 Each
15 1.15 Constructing masonry Chamber 30x30x50 cm, inside, in brick work in cement mortar 1:4 (1 cement :4fine sand) for stop cock, with C. I. surface box100x100 x75 mm (inside) with hinged cover fixedin cement concrete slab 1:2:4 mix (1 cement :2 coarse sand : 4 graded stone aggregate 20 mm nominal size ) necessary excavation foundationconcrete 1:5:10 ( 1 cement :5fine sand:10 gradedstone aggregate 40mm nominal size ) and insideplastering with cement mortar 1:3 (1 cement :3 coarse sand) 12mm thick finished with a floating coat ofneat cement complete as per standard design : With Second Class bricks item15 1 Each
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.