| 1 | CIVIL ENGINEERING WORKS | 309 & 310 | 495.00 | 1 Cum | 437.40 | 216513.00 |
| Filling with Gravel in trenches, sides of foundations and basement with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming including all operational, incidental, labour charges, seignorage charges, hire charges of T & P etc., complete for finished item of work. APSS No.309 & 310 |
| 2 | CIVIL ENGINEERING WORKS | 901906.0 | 247.50 | 10 Sqmt | 2151.05 | 53238.00 |
| Plastering to even surfaces of wall with CM(1:4) Prop: 12mm thick in single coat including cost and conveyance of all materials like cement, sand, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental charges and labour charges such as mixing mortar, finishing, curing, etc., complete for finished item of work. (APSS 901,906) |
| 3 | CIVIL ENGINEERING WORKS | 501 & 504 | 57.00 | 1 Cum | 7549.60 | 430327.00 |
| Brick Masonry in superstructure with CM (1:8) prop: using second class bricks of size 23 x 11 x 7 Cms from approved source having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, including seigniorage charges, sales & other taxes on all materials, all operational, incidental and labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work for Ground Floor |
| 4 | CIVIL ENGINEERING WORKS | 402.0 | 25.00 | 1 Cum | 5074.45 | 126861.00 |
| Plain Cement Concrete (1:4:8) proportion (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Broken Granite (IS383, 1970) machine crushed metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, mixing concrete in concrete mixer including seigniorage charges, sales & other taxes on all materials, all operational, incidental, and labour charges such as laying and ramming concrete in layers in position not exceeding 15cm, finishing top surface, curing concrete, etc., complete for finished item of work (APSS No. 402) for Levelling Course and Flooring Bed |
| 5 | CIVIL ENGINEERING WORKS | 308.0 | 74.50 | 1 Cum | 413.50 | 30806.00 |
| Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead of 10m including all operational, incidental, seigniorage charges, labour charges such as shoring ,sheeting, planking, strutting, dewatering etc. complete for finished item of work as per SS - 20 B (APSS 308). for Building Foundation |