Tamil Nadu Generation And Distribution Corporation Limited-TANGEDCO has published Execution Of Works In Agrl Normal , Agrl Tatkal Schemes , Oht/Street Light , Improvement , Corroded Pole Replacement Works In Kannivadi Section Of Dharapuram Division ( Running Contract ) . Submission Date for this Tender is 31-10-2020. Street Lighting Tenders in Dharapuram Tamil Nadu. Bidders can get complete Tender details and download the document.
Name of Work: Work Contract for Execution of works in Agrl Normal, Agrl Tatkal Schemes, OHT/Street Light, Improvement & Corroded pole replacement works in Kannivadi section of Dharapuram Division (Running Contract). | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Pit excavation for 7.5 mts / 8 mts pole in ordinary soil including cleaning of site (each pit) - 1.25 x 0.6 x 1.5m [ordinary soil] | Item1 | 72 | Pit |
2 | 2 | Pit excavation for 9.0M and 9.14 M PSC/RCC / all metal poles (each pit) 1.25 x 0.6 x 1.83 mtr - Ordinary soil | Item2 | 15 | Pit |
3 | 3 | Excavation of Stay pit in ordinary soil [0.95 x 0.6 x 1.2m] | Item3 | 60 | Pit |
4 | 4 | Erection of 7.5m / 8.0m poles [RCC / PSC] (Including refilling of excavated earth) | Item4 | 72 | E |
5 | 5 | Erection of 9.00m / 9.14m RCC / PSC/Rail pole, Tubular pole and all Metal Poles (Including refilling of excavated earth) | Item5 | 15 | E |
6 | 6 | Erection stay set complete (Including refilling of excavated earth) | Item6 | 60 | Set |
7 | 7 | Transport 7.5 mtrs / 8.00 mtrs of poles including R.S.Joist and Rail Poles Upto 1.0 Km (FROM ROAD SIDE TO WORKSPOT Using Crane/Machine) | Item7 | 72 | Per Pole |
8 | 8 | Transport of 9.0 mtr and above poles including R.S. Joist and Rail poles upto 1.0 Km (FROM ROAD SIDE TO WORKSPOT Using Crane/Machine) | Item8 | 15 | Per Pole |
9 | 9 | Loading of 7.5 Mtr / 8.0 Mtr RCC / PSC/ Metal Pole [ per pole ] | Item9 | 72 | E |
10 | 10 | Loading of [ 9.14 mtr ] 9.0 mtr poles RCC /PSC Pole / Metal Pole [ per pole ] | Item10 | 15 | E |
11 | 11 | Unloading of 7.5 Mtr / 8.0 Mtr RCC / PSC/ Metal Pole [ per pole ] | Item11 | 72 | E |
12 | 12 | Unloading of [ 9.14 mtr ] 9.0 mtr poles RCC /PSC Pole / Metal Pole [ per pole ] | Item12 | 15 | E |
13 | 13 | Retrieving grill from detoriated pole [grill separate from damaged pole] | Item13 | 20 | E |
14 | 14 | Fixing of LT 1 phase cross Arm | Item14 | 50 | E |
15 | 15 | Fixing of LTTI, HT TI Fitting | Item15 | 12 | E |
16 | 16 | Fixing of LT 3 ph Cross Arm | Item16 | 50 | E |
17 | 17 | Fixing of 3 1/2 V Cross arm | Item17 | 4 | E |
18 | 18 | Fixing of 4 1/2 V Cross arm | Item18 | 4 | E |
19 | 19 | Fixing of tapping channel / guarding Cross arm | Item19 | 4 | E |
20 | 20 | Fixing of 11 KV Pin insulator with pin | Item20 | 21 | E |
21 | 21 | Fixing of 22 KV Pin insulator with pin | Item21 | 9 | E |
22 | 22 | Fixing of 11 KV Strain disc / polymer disc with hardware | Item22 | 12 | set |
23 | 23 | Fixing of 22 KV Strain disc / polymer disc with hardware | Item23 | 12 | set |
24 | 24 | Fixing of LT Pin insulator with pin | Item24 | 200 | E |
25 | 25 | Fixing of LT Shackle with hardware | Item25 | 75 | E |
26 | 26 | Fixing of Aluminium knob | Item26 | 100 | E |
27 | 27 | Paving Stringing and sagging of conductor including binding of pin and proper tight [including transport of condutor from Road side to work spot] per run - Upto 7/2.59 mm ACSR, 7/2.50 AAAC including PVC cable upto 25 sqmm | Item27 | 3 | Km |
28 | 28 | Paving Stringing and sagging of conductor including binding of pin and proper tight [including transport of condutor from Road side to work spot] per run - ACSR 7/3.35mm & 7/ 3.15 AAAC including PVC cable above 25 sqmm | Item28 | 15 | Km |
29 | 29 | Earthing of poles (Earthing wiring and connection including transporting of earth pipe and excavation of pit) | Item29 | 80 | E |
30 | 30 | Sleeve concreting for pole 0.6 m x 0.6m x 0.3 m with coping | Item30 | 20 | Loc |
31 | 31 | Labour charges for alteration of back clamp / stay clamp to suitable for works. | Item31 | 40 | E |
32 | 32 | Releasing and erection 1 ph SC wire [during conductor or support change] | Item32 | 60 | SC |
33 | 33 | Releasing and erection 3 ph SC wire [during conductor or support change] | Item33 | 20 | SC |
34 | 34 | Transport of line Materials [ minimum 1 MT ] from sub stores to section pocket store or near to work spot at road side by using private vehicle or vice versa excluding loading and unloading - Upto 8 kms | Item34 | 5 | MT |
35 | 35 | Above 8 Kms and for every addl. 1 KM | Item35 | 15 | MT |
36 | 36 | Dismantling of 7.5m / 8.0m poles [RCC / PSC] | Item36 | 10 | E |
37 | 37 | Dismantling of 9.00m / 9.14m RCC / PSC/Rail pole, Tubular pole and all Metal Poles | Item37 | 10 | E |
38 | 38 | Dismantling stay set complete | Item38 | 30 | Set |
39 | 39 | Dismantling of LT 1 ph Cross Arm | Item39 | 10 | E |
40 | 40 | Dismantling of LT/HT TI Fitting | Item40 | 20 | E |
41 | 41 | Dismantling of LT 3 ph Cross Arm | Item41 | 20 | E |
42 | 42 | Dismantling of 3 1/2 V Cross arm | Item42 | 15 | E |
43 | 43 | Dismantling of tapping channel / guarding "X" arm | Item43 | 5 | E |
44 | 44 | Dismantling of 11 KV Pin insulator with pin | Item44 | 60 | E |
45 | 45 | Dismantlng of 11 KV Strain disc / polymer disc with hardware | Item45 | 24 | set |
46 | 46 | Dismantling of LT Pin insulator with pin | Item46 | 60 | E |
47 | 47 | Dismantling of LT Shackle with hardware | Item47 | 24 | E |
48 | 48 | Dismantling of Aluminium knob | Item48 | 20 | E |
49 | 49 | Dismantling of conductor Upto 7/2.59 mm ACSR, 7/2.50 AAAC including PVC cable upto 25 sqmm | Item49 | 5 | Km |
50 | 50 | Dismantling of conductor ACSR 7/3.35mm & 7/ 3.15 AAAC including PVC cable above 25 sqmm | Item50 | 2 | Km |
51 | 51 | Sub Total | Item51 | 1 | Each |
52 | 52 | EPF @ 13.00% | Item52 | 1 | Each |
53 | 53 | ESI @ 3.25% | Item53 | 1 | Each |
54 | 54 | SGST % | Item54 | 1 | Each |
55 | 55 | CGST % | Item55 | 1 | Each |
56 | 56 | IGST % | Item56 | 1 | Each |