| 1 | 1 | Making approach path of approximate 1.5m width & cutting of steps in hilly terrain including cost of labour & T&P Complete to drill hole points. | BI01010001010000000000000515BI0100001112 | 1500 | mtr |
|---|
| 2 | 2 | Dismantling, transportation & assembling of Drilling machines, pumps of different capacity complete by head load including cost of labour, T&P etc as per directions of Engineer-in-charge | BI01010001010000000000000515BI0100001113 | 12 | no. |
|---|
| 3 | 3 | Construction of Platform with locally available material of size 6m X 6m X 1m for housing the drilling machine Complete with cost of all labour, material, T&P & Transport as per direction of Engineer-in-charge. | BI01010001010000000000000515BI0100001114 | 10 | no. |
|---|
| 4 | 4 | Construction of Floating Platform of size 9mX9m using heavy duty steel drums of industrial use including cost of allied material, labour,T&P complete as per direction of Engineer-in-charge. | BI01010001010000000000000515BI0100001115 | 2 | no. |
|---|
| 5 | 5 | Laying of Temporary Water Supply Pipelines (25mm diameter & above) of varying lengths from the nearest water source & Construction of Water Retaining Pits of Size 2mX1mX0.5m complete with cost of all labour, material,T&P & transport including cost of GI Pipes as per direction of Engineer-in-Charge.\n(i) up to 750m | BI01010001010000000000000515BI0100001116 | 1 | LS |
|---|
| 6 | 6 | Carrying out of vertical Diamond Core Drilling in NX Size in different formations & locations including supply of core boxes, preservation of cores in core boxes of standard dimenions as per BIS standards, their marking & taking colour Photographs of the preserved cores etc. complete with cost of all labour,T&P & POL as per direction of E.I.C | BI01010001010000000000000515BI0100001117 | | |
|---|
| 7 | 6.01 | (i) In overburden soil and sandy strata mixed with boulders up to 100 m depth | BI01010001010000000000000515BI0100001118 | 243 | mtr |
|---|
| 8 | 6.02 | (ii) In hard Rock foundation up to 100m | BI01010001010000000000000515BI0100001119 | 412 | mtr |
|---|
| 9 | 7 | Carrying out of Angular Diamond Core Drilling in NX Size in different formations & locations including supply of core boxes, preservation of cores in core boxes of standard dimenions as per BIS standards, their marking & taking colour Photographs of the preserved cores etc. complete with cost of all labour,T&P & POL as per direction of E.I.C | BI01010001010000000000000515BI0100001120 | | |
|---|
| 10 | 7.01 | (i) In overburden soil and sandy strata mixed with boulders up to 100 m depth | BI01010001010000000000000515BI0100001121 | 75 | mtr |
|---|
| 11 | 7.02 | (ii) In hard Rock foundation up to 100m | BI01010001010000000000000515BI0100001122 | 30 | mtr |
|---|
| 12 | 8 | Water Permeability Tests at different depths as per direction of Engineer-in- charge | BI01010001010000000000000515BI0100001123 | | |
|---|
| 13 | 8.01 | (i) up to 100m | BI01010001010000000000000515BI0100001124 | 152 | no. |
|---|