Lighting Arrangement At Different Station Including Restrengthening Of Pcc Poles And Drawing Of Acsr Conductor In Lt Distribution Oh Line At Lot No. 8 In Connection With Ganga Sagar Mela 2021

Tender Notice

25775303
Lighting Arrangement At Different Station Including Restrengthening Of Pcc Poles And Drawing Of Acsr Conductor In Lt Distribution Oh Line At Lot No. 8 In Connection With Ganga Sagar Mela 2021
Indian
West Bengal
20-10-2020
24-11-2020
26-11-2020

Tender Details

Lighting Arrangement At Different Station Including Restrengthening Of Pcc Poles And Drawing Of Acsr Conductor In Lt Distribution Oh Line At Lot No. 8 In Connection With Ganga Sagar Mela 2021

Key Value

Document Fees
Refer document
EMD
INR 59000.00 /-
Tender Value
Refer document

BOQ Items

Name of Work: Lighting arrangement at different station including restrengthening of PCC poles and drawing of ACSR Conductor in LT Distribution OH line at LOT No. 8 in connection with Ganga Sagar Mela – 2021
Sl. No. Item Description Item Code / Make Quantity Units
1 1 Supply of hire basis 4.88 mtr long and 0.10 mtr. dia (Av.) bottom and 50 mm. dia. top salbollah post and erecting the same at Bus Stand and other different places as per direction of E.I.C. (av. distance between the two poles is 20 mtrs.) BI01010001010000000000000515BI0100001113 340 Nos
2 2 Supply on hire basis 4.88 mtr. long and 0.10 mtr. dia (av) bamboo post & erecting the same at bus stand other different places as per direction of the E.I.C. BI01010001010000000000000515BI0100001114 100 Nos
3 3 Supply on hire basis 400 watt sodium vapour fixture, lamp ballast and other materials required to complete the work with effect from 04.01.2021 to 17.01.2021 = 16 points x 14 days. BI01010001010000000000000515BI0100001115 224 Pts
4 4 Drawing of LT feeder and distribution line from medium pressure voltage by 3 Ph. 4 wire system as per IE rules and ISS rules by 50 sq. mm. to 16 sq. mm. PVC single core wire on hire basis on salbollah post & on PCC pole incl. supply of wire installation of binding wire etc. as directed before 04.01.2021 5000 Mtr
5 5 Constructions of tower by steel tubular pole with cross arms for both sides the tower should be 9.14 mtr. long x 1.5 mtr. bottom by supplying reqd. quantity steel pipe cross arms horizontal support etc. to complete the tower on the basis incl. fitting fixing of twin type of 400 watt sodium vapour flood light fixture and lamp (1 set in front and other in the back, if necessary) on hire basis as per direction of EIC incl. drawing off elec. Connection with all protection to avoid all kind of accident and all the tower should be properly earth as per IE rules with effect from 04-01-2021 to17-01-2021 = 14 days 2 Sets
6 6 Making lighting arrangement by one no steel tubular pole 9.14mtr long x 1.5 mtr [5ft] bottom for proper illumination of bus stand including supply of necessary materials required to complete the tower on hire basis including fitting fixing of twin type of 400 watt of sodium vapour flood light fixture and lamp on iron frame and other in the back if necessary as per direction of E.I.C. incl. drawing all elec. Connection an necessary protection complete from 10-01-2021 to 17-01-2021= 8 days 4 Sets
7 7 Drawing tube light points from different distribution and feeder lines on salbollah post and PCC pole at different places with supplying on hire basis 40 watt tube light, choke, starter and all other necessary materials to complete the work from 04.01.2021 to 17.01.2021 = 14 days x 480 pts. 6720 Pts
8 8 Drawing street light points from different distribution and feeder lines salbollah posts to different places directed with supply on hire basis 60 watt. bulb, holder bracket and necessary materials required to complete the work
9 8.01 From 04.01.2021 to 17.01.2021 = 14 days x 150 pts. 2100 Pts
10 8.02 From 18.01.2021 to 22.01.2021 = 5 days x 20 pts. 100 Pts
11 9 Drawing halogen light point on the existing salbollah post from different feeder line as per direction E.I.C. by supplying on hire basis 1000 watt halogen lamp fixture from 04.01.2021 to 17.01.2021 = 14 days x 35 pts. 490 Pts
12 10 Drawing halogen light 1000 watt on PCC pole on hire basis from Kashinagar to Hardwood point from different distribution line to different places as per direction EIC incl. connection of wire and other materials as reqd. to complete the job with effect from 04.01.2021 to 16.01.2021 = 13 days x 20 points. 260 Pts
13 11 Drawing the street light points for bus stand (old & new) from different feeder and distribution line to PCC pole street tubular pole and salballah post to different places as directed with supply on hire basis 250 W sodium fixture lamp ballast and other necessary materials reqd. for the work to complete from 04.01.2021 to 17.01.2021=14days x 100pts 1400 Pts
14 12 Drawing of light point for bridge ghat, jetty ghat and other places as directed with supply on hire basis 400 W sodium vapour fixture lamp ballast and other materials reqd. to complete the work from 04.01.2021 to 17.01.2021 = 14 days x 25 pts. 350 Pts
15 13 Drawing of light point of 400 watt twin type flood light fixture and son lamp with control gear complete on hire basis from 04.01.2021 to 17.01.2021 = 14days x 50pts 700 Pts
16 14 Drawing ceiling lights points from different distribution line to different hogla shed as per direction of EIC with supply on hire basis 40 watt bulb holder and other materials required to complete the work from 04.01.2021 to 17.01.2021 = 14 days x 325 pts. 4550 Pts
17 15 Drawing ceiling light points from different distribution line to different jetty ghat as per direction of EIC with suppy on hire basis 40 watt bulb holder and other materials required to complete the work from 08.01.2021 to 16.01.2021 = 9 days x 60 pts. 540 Pts
18 16 Drawing of metal flood light points on hire basis on jetty ghat, bus stand from different feeder of 400 watt metal flood fixture, lamp, control gear etc. reqd. to complete the job from 08.01.2021 to 16.01.2021 = 9 days x 20 pts. 180 Pts
19 17 Making jetty ghat signal with color 12 nos. 40 watt x 4 ft. long tube as directed including supply on hire basis ( for 5 nos. jetty) tube choke starter wire etc. for the work complete from 04.01.2021 to 17.01.2021 = 14 days x 15 pts. 210 Pts
20 18 Temporary installation of panel board wooden plank including supply on hire basis salbollah wood plank etc. as per direction of E.I.C. 6 Pts
21 19 Drawing flood light point in new bus stand road PCC pole and tower from different feeder line as directed with fitting fixing of 400 watt twin type SON-T flood light fixture and lamp with control gear bulb etc. as required to complete the work on hire basis for the period from 04.01.2021 to 16.01.2021 = 13 days x 20 pts. 260 Pts
22 20 Temporary installation of controlling station with fittings 63 amps TPN 16 amp TPN main switch on wooden plank and salbollah on hire basis incl. elec. Connection complete as per direction of E.I.C. 20 Nos
23 21 Making electrical connection from WBSEDCL supply main switch board by supplying on hire basis 50 sq. mm x 3.5 core PVC Al. cable as per IE rules as per direction of E.I.C. including supply of all necessary materials reqd. before 01.01.2020 (average Distance from WBSEDCL supply main switch to departmental panel board is 50 mtrs) for four nos. station with proper earthing as per IE rules. 10 Set
24 22 Replacement of 120 mm size digit 2020 in place of 2016 replacing only digit. Removal of existing letter with supply of red letters as per sample and other materials as directed. 1 Items
25 23 Fitting fixing of glow sign board /signage board/vernacular board on salballah structures on hire basis at different places as per direction of EIC with all electrical connection including supply of all materials reqd. to Complete the work. 60 Nos
26 24 Maintenance of controlling station by engaging skilled operating staff for operation of controlling switch of different places as per direction of E.I.C. 20 Nos
27 25 Carrying charges of materials such as S.V. fixture, glow sign board, panel board etc. from Akshyanagar store to Kakdwip Lot No. 8 and back to store after completion of mela incl. loading & unloading. 2 Trips
28 26 Painting of control panel board & the electrical accessories by one coat of red oxide paint and two coats of approved & anti corrosive paint as per direction of the E.I.C. 9 Nos
29 27 PROVING BARRIER LIGHTING AT OLD AND NEW BUS STAND Drawing L.T. feeder and distribution line from medium pressure voltage by 3 Ph. 4 wire system as per IE rules and ISS rules by 16 sq mm. PVC single core wires on hire basis on salbollah post including supply of necy. Wire as per direction of E.I.C 1000 Mtr
30 28 Drawing barrier lighting from different distribution lines to different places on salbollah post with supply of 60 W colour lamp holders etc. on hire basis and other necessary materials required to complete the work from 10.01.2021 to 17.01.2021 = 8 days x 100 pts. 800 Pts
31 29 Repairing of L.T. panel board replacement of fuse grip, indicating lamp 63 amps main switch and fixing of the repaired accessories with all inter connection and testing complete as per direction of the E.I.C. 10 Nos
32 30 Petty repairing of glow sign board with supply of suitable size letter and fixing the same as per existing model including supplying 3 mm thick plastic sheet of reqd. to complete the work and painting complete. 20 Nos
33 31 LIGHTING OF NEW BUS STAND AREA THROUGH MS TUBULAR POLES Supply on hire basis of 9 m long pole and erecting by excavation of earth in any kind if soil at different places of new bus stand and jetty ghat area as per direction of E.I.C for the period from 02.01.2021 to 22.01.2021 20 Nos
34 32 Supply on hire basis of 9 mtrs long steel pole and erecting by excavation of earth in any kind of soul at LCT as per direction of EIC from 02.01.2021 to 22.01.2021 10 Nos
35 33 Drawing of flood light point at LCT jetty ghat with supply of following flood light fixture with lamp on hire basis with all other necessary materials required to complete the work. 42 Pts
36 34 400 watt twin flood light fixture and son lamp with control gear complete from 02.01.2021 to 22.01.2021 = 21 days x 02 pts
37 34.01 400 watt street light fixture on existing pole and son lamp with control gear complete from 02.01.2021 to 22.01.2021 = 21 days x 04 pts 84 Pts
38 34.02 250 watt street light fixture on existing pole and son lamp with control gear complete from 02.01.2021 to 22.01.2021 = 21 days x 24 pts 504 Pts
39 34.03 Drawing barrier signal lighting on LCT jetty ghat with supply of 60 watt color lamp holder etc on hire basis and other necessary materials required to complete the work from 02.01.2021 to 22.01.2021 = 21 days x 180pts 3780 Pts
40 35 Making earthing arrangement by supplying 5/8” dia earth spike of 2 mtr long with galvanized bolts nuts sand washer etc including supplying and fitting fixing 8 nos SWG GI wire and restoration of the surface duly rammed as per direction and inter connection earth spike to continuous running earth on the top of the PCC pole 20 Nos
41 36 LIGHTING ARRANGEMENT IN BETWEEN NUTAN RUSTA TO LCT JETTY GHAT Drawing street light point on existing PCC pole by 250Watt SV lamp, ballast, fixture, wire etc and including all other accessories for complete the work on hire basis from 04-01-2021 to 17-01-2021 = 14days x 98 pts 1372 Pts
42 37 Supply and delivery at site the special type arm bracket made with 40mm dia GI pipe 2 Mtr long for street light fixture 250 watt SV lamp including MS collar weld at neck of the bracket making 600 bend at the top portion including painting by red oxide paints as per direction of EIC. 20 Nos
43 38 Supply, delivery and fixing of suitable size pole clamp as per direction of EIC. 30 Pairs
44 39 Drawing of overhead line in vertical configuration of medium pressure line by ACSR including supplying binding wire for jumper and insulator and safety device etc. in different places as per ISS and IE rules as per direction of EIC (ACSR conductor will be supplied by the Department) 4000 Mtr
45 40 Fixing of special type arm bracket in PCC pole by supplying necessary fittings all complete 98 Pts
46 41 ILLUMINATION OF EXTENDED PORTION OF MAIN CONCRETE JETTY GHAT NO. 1 Drawing of flood light points for permanent jetty ghat and other place as directed on supply on hire basis 400 watt sodium flood light fixture- 1no, control gear box and SV lamp etc and complete the work from 04-01-2021 to 17-01-2021 =14 days x 12 pts 168 Pts
47 42 Drawing of the flood light point for main entrance of the jetty fixing on MS joist as per direction of EIC. Supply on hire basis 400 watt twin type flood light fixture and 2 nos SON lamp with control gear box complete from 04-01-2021 to 17-01-2021 = 14 days x 4pts 56 Pts
48 43 Drawing of 250watt street light fixture in different place of permanent jetty ghat on hire basis of 250watt S.V. fixture ballast, 250watt S.V. lamp from 04-01-2021 to 17-01-2021 = 14 days x 10pts 140 Pts
49 44 Supply on hire basis of 9mtr long MS pole and erection and fitting fixing on the jetty bridge as per direction of EIC for the period from 04-01-2021 to 17-01-2021 10 Nos
50 45 Supply and delivery at site D type iron clamp set galvanized with necessary GI nuts and washer size 3 ½ “ x 5” dia 30 Nos
51 46 Supply and delivery at site of porcelain shackle insulator size 75mm x 88mm 30 Nos
52 47 Fitting fixing of D type iron clamp, Parceling shackles and pole clamp in the MS pole after completion of the erection work 24 Nos
53 48 Drawing LT feeder and distribution line from medium pressure voltage 3 phase 4-wire system by 25sq.mm. PVC single core aluminum wire on hire basis 400 Mtr
54 49 Making earthing arrangement by supplying 5/8” dia earth spike of 2 mtr long with galvanized bolts nuts sand washer etc including supplying and fitting fixing 8 nos SWG GI wire and restoration of the surface duly rammed as per direction and inter connection earth spike to continuous running earth on the top of the PCC pole 10 Nos
55 50 ILLUMINATION OF JETTY GHAT NO 2 Drawing of flood light points for jetty ghat no. 2 and other place as directed on supply on hire basis 400 watt sodium flood light fixture- 1no, control gear box and SV lamp etc to complete the work from 04-01-2021 to 17-01-2021 =14 days x 16 pts 224 Pts
56 51 Drawing of the flood light point for main entrance of the jetty fixing on MS joist as per direction of EIC. Supply on hire basis 400 watt twin type flood light fixture and 2 nos SON lamp with control gear box complete from 04-01-2021 to 17-01-2021 = 14 days x 8pts 112 Pts
57 52 Drawing of 250watt street light fixture in different place of jetty no. 2 on hire basis of 250watt S.V. fixture ballast, 250watt S.V. lamp from 04-01-2021 to 17-01-2021 = 14 days x 30pts 420 Pts
58 53 Supply on hire basis of 9mtr long MS pole and erection and fitting fixing on the jetty bridge as per direction of EIC for the period from 04-01-2021 to 17-01-2021 12 Nos
59 54 Supply and delivery at site D type iron clamp set galvanized with necessary GI nuts and washer size 3 ½ “ x 5” dia 33 Nos
60 55 Supply and delivery at site of porcelain shackle insulator size 75mm x 88mm 33 Nos
61 56 Supply and delivery at site the special type arm bracket made with 40mm dia GI pipe x 2 mtr long for light fixture 250watt SV lamp including MS collar welded at neck of the bracket including painting by red oxide paint as per direction 6 Nos
62 57 Fitting fixing of D type iron clamp, Parceling shackles and pole clamp in the MS pole after completion of the erection work 33 Nos
63 58 Drawing LT feeder and distribution line from medium pressure voltage 3-phase 4-wire system by 25 sq. mm. PVC single core aluminum wire on hire bsis 500 Mtr
64 59 Making earthing arrangement by supplying 5/8” dia earth spike of 2 mtr long with galvanized bolts nuts sand washer etc including supplying and fitting fixing 8 nos SWG GI wire and restoration of the surface duly rammed as per direction and inter connection earth spike to continuous running earth on the top of the PCC pole 8 Nos
65 60 ILLUMINATION OF JETTY NO. 3 Drawing flood light points from different place of new jetty Ghat and other places as per direction on supply on hire basis 400 watt sodium fixture, 1no control gear box and S.V. lamp etc complete the work from 04-01-2021 to 17-01-2021 = 14 days x 14 nos 196 Pts
66 61 Drawing flood light points for main entrance of the jetty and approach road as per direction of EIC. Supply on hire basis 400 watt twin type flood light fixture and 2nos SON lamp with control gear box complete from 04-01-2021 to 17-01-2021 = 14 days x 4 pts 56 Pts
67 62 Drawing tube light point from different distribution and feeder line on suitable place at jetty with supply on hire basis 40 watt tube light, choke complete the work from 04-01-2021 to 17-01-2021 = 14 days x 60pts 840 Pts
68 63 Drawing of 250 watt street light in different places of new jetty ghat river bank road and approach road, hardwood point and other place on hire basis of 250 watt SV fixture, ballast, 250wattt SV lamp from 04-01-2021 to 17-01-2021 = 14 days x 30 pts [for Jetty No.3 – 20 Nos and bypass road-10nos] 420 Pts
69 64 Supply on hire basis of 9 mtr long MS pole and erection on the jetty bridge, river bank to hardwood point , approach road as per direction of EIC for the period from 04-01-2021 to 17-01-2021 20 Nos
70 65 Supply and delivery at site D type iron clamp set galvanized coating with necessary GI nuts and washer size 3 ½ “ x 5” 80 Nos
71 66 Supply and delivery at site of porcelain shackle insulator size 75mm x 88mm 80 Nos
72 67 Supply & delivery at site 25 sq. mm. 660/1200 volt grade singe core PVC insulated aluminum cable 500 Mtr
73 68 Fitting fixing of D type iron clamp, porcelain shackles and MS clamp in the MS pole after complete erecting work 80 Nos
74 69 Drawing and distribution line from medium pressure voltage 3 Ph 4 wire system by 25 sq.mm PVC single core aluminum cable 1000 Mtr
75 70 Making earthing arrangement by supplying ?” dia earth spike of 2 mtr long with galvanized bolts and nits and washer etc including supplying and fitting riding 8 nos SWG GI wire and restoration of the surface duly rammed as per direction and inter connection earth spike to continuous running earth on the top of the PCC pole 15 Nos
76 71 Making jetty light Ghat signal light with color and LED lamp dimmer and fixing on pole and front side of the jetty to complete the job 1 Items
77 72 ILLUMINATION OF APPROACH ROAD BETWEEN HARDWOOD POINT TO RIVER BANK Supply on hire basis of 9 mtr long steel tubular pole and erection complete at approach road for Hardwood Point near bus stand 20 Nos
78 73 Drawing of 250 watt street light fixture in different place of approach road on hire basis of 250 watt SV fixture ballast, 250 watt SON-T lamp from 07-01-2021 to 17-01-2021 = 11 days x 23 pts 253 Pts
79 74 Drawing of 250 watt street light fixture in approach road near hardwood point jetty ghat on hire basis of 250 watt SV fixture ballast, 250 watt SON-T lamp from 07-01-2021 to 17-01-2021 = 11 days x 15 pts 165 Pts
80 75 Drawing flood light point of approach road near hardwood point bus stand on hire basis of 400 watt twin type flood light fixture and SON lamp with control gear complete from 7-01-2021 to 17-01-2021 = 11 days x 7 pts 77 Pts
81 76 Making earthing arrangement by supplying 5/8” dia earth spike of 2 mtr long with galvanized bolts nuts sand washer etc including supplying and fitting fixing 8 nos SWG GI wire and restoration of the surface duly rammed as per direction and inter connection earth spike to continuous running earth on the top of the PCC pole 10 Nos
82 77 ILLUMINATION OF JETTY NO.4 AND OTHER ALLIED WORKS Drawing Drawing of flood light points from different place of new jetty ghat and other places as per direction on supply on hire basis 400 watt sodium flood fixture 1 no control gear box and SV lamp etc complete the work from 04-01-2021 to 17-01-2021 = 14 days x 20 pts 280 Pts
83 78 Drawing flood light point for main entrance of the jetty and approach roads fixing on MS joint as per direction of EIC. Supply on hire basis 400 watt twin type flood light fixture and 2 nos SON lamp with control gear box complete from 04-01-2021 to 17-01-2021 = 14 days x 16pts 224 Pts
84 79 Drawing of 250 watt street light fixture in different places of new jetty ghat river bank road and approach road, hardwood point and other place on hire basis of 250- watt SV fixture, ballast 250 watt SV lamp from 04-01-2021 to 17-01-2021 = 14 days x55 pts 770 Pts
85 80 Drawing of metal flood light point on different places as per direction of EIC of 400 watt metal fixture, lamp control gear etc to complete the jobs from 04-01-2021 to 17-01-2021 =14 days x 12pts 168 Pts
86 81 Supply on hire basis of 9 mtr long MS pole and erection on the jetty bridge, river bank to hardwood points approach road as per direction of EIC for the period from 04-01-2021 to 17-01-2021 25 Nos
87 82 Supply and delivery at site D type iron clamp set galvanized coating with necessary GI nuts and washer size 3 ½ “ x 5” 50 Nos
88 83 Supply and delivery at site of porcelain shackle insulator size 75mm x 88mm 50 Nos
89 84 Supply and delivery at site 25 sq.mm. 660/1200 volt grade single core PVC insulated aluminum cable 1000 Mtr
90 85 Fitting fixing of D type iron clamp, porcelain shackles and MS clamp in the MS pole after complete of the erection work 50 Nos
91 86 Drawing and distribution line from medium pressure voltage 3 Ph 4 wire system by 25sq.mm. PVC single core aluminum cable on hire basis 1000 Mtr
92 87 Making earthing arrangement by supplying 5/8” dia earth spike of 2 mtr long with galvanized bolts nuts sand washer etc including supplying and fitting fixing 8 nos SWG GI wire and restoration of the surface duly rammed as per direction and inter connection earth spike to continuous running earth on the top of the PCC pole 15 Nos
93 88 JETTY NO. 5 WITH SURROUNDING AREAS Drawing of flood light points for jetty Ghat No.5 and other place as directed on supply on hire basis 400 watt sodium flood light fixture-1 No, control gear box and SV lamp etc and complete the work from 04-01-2021 to 17-01-2021= 14 days x 16pts.. 224 Pts
94 89 Drawing of the flood light point for main entrance of the jetty fixing on MS joint as per direction of EIC. Supply on hire basis 400 watt twin type flood light fixture and 2 nos SON lamp with control gear box complete from 04-01-2021 to 17-01-2021 =14 days x 15 pts. 210 Pts
95 90 Drawing of 250 watt street light fixture in different place of jetty ghat no5 on hire basis of 250 watt S.V fixture ballast,250 watt S.V. lamp from 04-01-2021 to 17-01-2021= 14 days x 45 pts. 630 Pts
96 91 Supply & drawing of distribution line for medium pressure voltage, 3Phase 4 wire system by 25sq.mm single core PVC insulated wire on hire basis including dismantling the same after completion the work. 4000 Mtr
97 92 Supply on hire basis of 9 mtr. Long MS pole and erection and fitting fixing on the jetty bridge as per direction of EIC for the period from 04-01-2021 to 17-01-2021 41 Nos
98 93 Supply and delivery at site D. type iron clamp set galvanized with necessary GI nuts and washer size 31/2'' x 5'' dia. 164 Nos
99 94 Supply and delivery at site of porcelain shackle insulator size 75mm x 88mm. 164 Nos
100 95 Fitting fixing of D type iron clamp, porcelain shackles and pole clamp in the MS pole after completion of the erection work. 164 Nos
101 96 Making earthing arrangement by supplying 5/8'' dia earth spike of 2 mtr long with galvanized bolts nuts sand washer etc including supplying and fitting fixing 8 nos SWG GI wire and restoration of the surface duly rammed as per direction and inter connection earth spike to continuous running earth on the top of the PCC pole. 41 Nos
102 97 Guarding charge of the whole installation. 1 Items
103 98 Installation of the departmentally supplied LED board on the top of the jetty No. 5 with proper positioning including supply of 7/20 PVC insulated single core aluminium cable approx. length 20 mtr. Including connection and clamping arrangement complete. 2 Nos
104 99 Fitting fixing of light boxes with three sides open with red and green light for signaling for vessel availability in jetty ghat No. 5. 1 Nos
105 100 GROUP-A Shifting and carrying charges of the above PCC poles at different places by hire basis van and manual labour including loading and unloading complete 15 Nos
106 101 Erection of the above PCC poles by excavation of earth depth up to 2 mtrs from ground level and filling with jhama bricks and excavated soil s per requirement to compete the job 15 Nos
107 102 Drawing of ACSR conductor with illumination arrangement and drawing of overhead line in vertical configuration of medium pressure line by ACSR including supplying binding wire from jumper and insulator and safety device etc in different places as per ISS & IE rules and also as per direction of EIC [ACSR conductor will be supplied by the Department] 1800 Mtr
108 103 Supply and drawing of continuous wire for earthing from end pole to receive pole by supplying 12 SWG GI wire with all necessary materials and earth clamp complete as per direction of the EIC 450 Mtr
109 104 Supply and delivery at site D type iron clamp set galvanized with necessary GI nuts bolts and washer size 3.5” x 5” dia including loading unloading and carrying charges complete as per direction of the EIC 60 Nos
110 105 Supply and delivery of porcelain shackle insulator size 75mm x 88mm 60 Nos
111 106 Supply fitting fixing of hexagonal type safety device by making 12 SWG GI wire for LTOH line as per direction of the EIC 30 Nos
112 107 Fitting fixing of D type iron clamp and pole clamp in the PCC pole after completion and erection as per IE rules 60 Nos
113 108 Making earthing arrangement by supplying 5/8” dia earth spike of 2 mtr long with galvanized bolts nuts sand washer etc including supplying and fitting fixing 8 nos SWG GI wire and restoration of the surface duly rammed as per direction and inter connection earth spike to continuous running earth on the top of the PCC pole 10 Nos
114 109 Making stay arrangement by 7/18 SWG GI stay wire including supply of necessary materials which will be required stone chips, cement, sand, stay rod anchor plate for stay complete as per IE rules & ISS 10 Nos
115 110 Drawing of 250 watt street light fixture in extension road from Hardwood Point Launch Ghat on hire basis of 250 watt SV fixture ballast, 250 watt SON-T lamp from 07-01-2021 to 17-01-2021 = 11 days x 15 pts 165 Pts
116 111 Painting with decorative cement basis paint of approved quality after scraping the above pole surface thoroughly in different area as per direction of the EIC 15 Nos
117 112 Painting with ready mix black Japan paint up to 0.5mtr from ground level as per direction with proper numbering 15 Nos
118 113 Painting of D type iron clamp, arm bracket, pole clamp by two coats complete. 15 Nos
119 114 Dismantling of ACSR conductor and earth wire from end pole after disconnection of al. jointing materials i.e. jumper insulator, safety device, binding from the PCC pole in different places at new bus stand and old bus stand as per direction of EIC after completion of mela works 1800 Mtr
120 115 Withdrawing the 8 mtrs PCC poles by excavation of the and lifting the poles carefully and stacking the pole at site store 15 Nos
121 116 Supply on hire basis of 15amps plug socket and plug with wooden board and fixing of the different palaces i.e. police line, police barrack, hospital, movement office etc including supply of power cable and connection complete 100 Nos
122 117 GROUP-B RENEWING EARTHING ARRANGEMENT AND MAKING STARY ARRANGEMENT FOR THE EXISTING PCC POLE AT LOT NO.8 NEW BUS STAND Making earthing arrangement by supplying 5/8” dia Earth spike of 2 mtr long with galvanized bolts nuts and washer etc. including supplying and fitting fixing 8 nos SWG GI wire and restoration of the surface duly rammed as per direction and inter connection earth spike to continuous running earth on the top of the PCC pole 15 Nos
123 118 Making the stay arrangement by 7/18 SWG std stay wire including supply of necessary materials which will be required stone chips, cement, sand, stay rod, anchor plate for stay complete as per IE rules 15 Nos
124 119 Carrying charges of fixed type High Mast including control panel, cable, luminaries etc. from Akshaynagar store to site i.e. Harwood point more and near LCT Jetty by hiring of car and all other necessary arrangement as per requirement 2 Items
125 120 Installation the High Mast pole with fitting fixing of the luminaries (9 Nos.) on the lighting tower and laying of the PVC insulated Aluminium Armoured cable with all interconnection complete with testing of the same as per direction of the EIC. 2 Items
126 121 Carrying back the fixed type High Mast including control panel, cable, luminaries etc. to PHE store after dismantling the luminaries, accessories, cable etc. at Akshaynagar Store by hiring of car and all other necessary arrangement after completion of Mela 2 Items
127 122 Guarding arrangement of the whole installation round the clock as per direction of the EIC 2 Items
128 123 GROUP-C\nProviding power supply at Lot No.8 guest house [Mohana Bungalow] 10-01-2021 to 16-01-2021 with supply of fuel, lubricants, sundries and skilled operational staff and including all other materials required to complete the work with all electrical connections complete = 16Kw x 7 days x 2 hr
129 123.01 Guarding of the while installation at LOT No. 8, Kashinagar, Kakdwip Road, Old and new bus stand, Jetty Ghats etc. by engaging labour as per direction from 04-01-2021 to 17-01-2021 1 Items
130 123.02 Restrengthening of existing poles in different places after disconnecting the stay etc. at main bus stand (New) and connecting the stay as directed 170 Nos
131 124 Earth filling to the level of existing pole and packing of brickbats by supplying required quantity of bats after earth cutting of the pole base and the PCC pole in original position complete by providing stay wire & other materials as per direction of the E.I.C. 170 Nos
132 125 Replacement of GI bolts nuts & washers D type iron clamp shackle insulator etc. of the above works as per requirement complete of all works as per direction of the E.I.C. including supply of all materials. 140 Nos
133 126 GROUP-B [Drawing of ACSR in LT distribution line at new & old bus stand] Drawing of overhead line in vertical configuration for medium pressure line A.C.S.R including supplying of wire for jumper & insulator and safety device etc. in different places complete as per I.E. Rules (A.C.S.R. conductor shall by supplied by deptt.) 24000 Mtr
134 127 Supply & drawing of continuous earth wire from end pole to receive pole by supplying 12 S.W.G G.I. wire with all new materials and earth clamp complete as per direction of E.I.C. 5700 Mtr
135 128 Dismantling of A.C.S.R conductor and earth from end pole after disconnection all jointing materials i.e. jumper including safety device binding from P.C.C. pole in different places of the New Bus Stand as per direction of E.I.C. after completion of Mela – 2021 24000 Mtr
136 129 Painting with decorative cement base of approved quality after scrapping the pole surface thoroughly in different areas as per direction of E.I.C. 250 Nos
137 130 Painting with ready mix Black Japan paint up to 0.5 mtr. G.L. as per direction with proper numbering. 250 Nos
138 131 Painting of ‘D’ type iron clamps and pole clamp etc. after scrapping the surface with two coats of red oxide paint. 800 Nos
139 132 CarryinCharges of over head materials i.e. A.C.S.R. clamp from Akshyanagar to Lot No. 8 & back to Akshyanagar store after mela including loading and unloading 2 Trips
140 133 Drawing of 25 sq. mm and 50sq.mm. x 3.5 core PVC Ar. Al cable in different distribution of L.T. panel board from the panel board of WBSEDCL [cable will be supplied by the department] 270 Mtr
141 134 Drawing of the flood light points at New Bus Stand & Old Bus Stand from different distribution line to P.C.C. pole as directed with supply of following flood light fixture with lamp on hire basis with all other necessary materials reqd. to complete the work for the period from 05.01.2021 to 16.01.2021 = 12 days.
142 134.01 400-watt twin type flood light fixture and son lamp with control Gear complete 12 days x 90 pts. 1080 Pts
143 134.02 400-watt street light fixtures and son lamp with control gear Complete 12 days x 50 pts. 600 Pts
144 135 GROUP-B \nERECTION OF PCC POLES AND DRAWING OF ACSR CONDUCTOR WITH ILLUMINATION ARRANGEMENT AT RIVER BANK AND \nAPPROACH ROAD BEHIND BHARAT SEVASRAM SANGHA Drawing of ACSR conductor with illumination arrangement and Drawing of overhead line in vertical configuration of medium pressure line by ACSR incl. supplying binding wire from jumper and insulator and safety device etc in different places as per ISS and IE rules and also as per direction of EIC (ACSR. conductor will be supplied by the Department) 1500 Mtr
145 136 Supply and drawing of continuous wire for earthing from end pole to receive pole by supplying 10 SWG GI wire with all necy. Materials and earth clamp complete as per direction of EIC. 370 Mtr
146 137 Supply and delivery at site of D type iron clamp set galvanized with necessary GI nuts and bolts washer size 3.5” x 5” dia incl. loading unloading and carrying complete as per direction of EIC 100 Nos
147 138 Supply and delivery of porcelain shackle insulator size 75mm x 88mm including loading unloading and carrying complete as per direction of EIC 100 Nos
148 139 Supply and delivery at site of suitable poles clamp for existing PCC pole with iron angle fitting complete for 3 Ph 4 wire overheads lines as per ISS and IE rules incl. loading and unloading and carrying complete as per direction of EIC i) Size of angle=50mmx50mmx6mm thick. ii) Size of shackle strip=61mmx25mm 20 Nos
149 140 Supply and delivery at site the special Type arm bracket made with 40mm dia pipe x 2 mtr long for street light fixture 400watt SV lamp including MS collar weld at the neck of the bracket 60o bend at the top portion incl. painting by red oxide paints as per direction of EIC. 15 Nos
150 141 Supply and delivery at site of special type MS clamp as per sample by MS patty as required length incl. necy. Nuts, bolts and washer with painting red lead paint of approved make. 30 pair
151 142 Supply fitting fixing of hexagonal type safety device by making 10 SWG GI wire for LTOH line as per direction of EIC 30 Nos
152 143 Fitting fixing of D type iron clamp and pole clamp in the PCC pole after completion and erection as per IE rules 100 Nos
153 144 Making earthing arrangement by supplying 5/8” dia earth spike of 2 mtr long with galvanized bolts nuts sand washer etc including supplying and fitting fixing 8 nos SWG GI wire and restoration of the surface duly rammed as per direction and inter connection earth spike to continuous running earth on the top of the PCC pole 4 Nos
154 145 Making the stay arrangement by 7/8SWG GI std stay wire incl. supply of necessary materials which will be required stone chips, cement, sand, stay rod anchor plate for stay complete as per IE rules and ISS 8 Nos
155 146 Drawing the flood light points of new bus stand from different distribution line to PCC pole as directed with supply of 250watt street light fixture with lamp on hire basis with all other necessary materials required to complete the work for the period from 07.01.2021 to 17.1.2021 = 11 days x 15 Nos 165 Pts
156 147 Painting with decorative cement basis paint of approved quality after scraping the above pole surface thoroughly in different area as per direction of EIC. 15 Nos
157 148 Painting with ready mix black Japan paint upto 0.5mtr above GL as per direction with proper numbering 15 Nos
158 149 Painting of D type iron clamp and poles etc after scraping the surface with two coats 15 Nos
159 150 Dismantling of ACSR conductor and earth wire from end pole after disconnection all jointing materials i.e. jumper insulator safety device binding from the PCC pole in different places at new bus stand and old bus stand as per direction of EIC after completion of mela works 1500 Mtr
160 151 Supply on hire basis 4.88 mtr long and 0.10 mtr dia (av.) bottom and 0.50 mtr (av.) top salbollah post and erecting the same as per direction of EIC 6 Nos
161 152 Supply on hire basis of 9 mtr long MS pole and erection and fitting fixing the same as per direction of the EIC for the period from 09-01-2021 to 17-01-2021 = 9 days 5 Nos
162 153 Supply and delivery at site the special type arm bracket made with 40mm dia GI pipe x 2 mtrs long for light fixture 250 watt SV lamp including 600 bend long at the top position including painting by red oxide paint as per direction 5 Nos
163 154 Drawing LT feeder and distribution line from medium pressure voltage 3 Ph 4 wire system by 25 sq.mm PVC single core aluminum wire on hire basis 500 Mtr
164 155 Drawing tube light point on the salbollah post with supply on hire basis 40watt tube light choke starter and all other necessary materials to complete the work from 07.01.2021 to 17.01.2021 = 11 days x 60 pts 660 Pts
165 156 Drawing of flood light points for other places as directed on supply on hire basis 400 watt sodium flood light fixture 1no control gear box and SV lamp etc to complete the work from 07-01-2021 to 17-01-2021 = 11 days x 1pt = 11pt 11 Pts
166 157 Drawing halogen light point on the PCC pole, salbollah from generating station with supply on hire basis 1000watt halogen lamp fixture from 07.01.2021 to 17.01.2021 = 11 days x 4 pts 44 Pts
167 158 Drawing of 400 watt twin type flood light fixture and SON lamp with control gear complete from 07.01.2021 to 17.01.2021 = 11 days x 7 pts 77 Pts
168 159 Drawing of 250watt street light fixture on hire basis of 250 watt SV fixture ballast 250 watt SV lamp from 07-01-2021 to 17-01-2021 = 11 days x 5pts 55 Pts
169 160 Drawing of the flood light point including supply on hire basis 400 watt twin type flood light fixture and 2 nos SON lamp with control gear box complete from 07-01-2021 to 17-01-2021 = 11 days x 1 pt = 11 pts 11 Pts
170 161 Temporary installation of controlling station with 16amps TPN main switch on wooden plank and salbollah on hire basis including electrical connection complete as per direction of EIC. 4 Nos
171 162 Fitting fixing of glow sign board on salballah structure on hire basis at different places as per direction of EIC with all electrical connection including supply of all materials required to complete the work (glow sign board will be supplied by the department) 5 Nos
172 163 Guarding the whole installation by engaging experienced labour as per direction of EIC in three shifts from 07.01.2021 to 17.01.2021 1 Items
173 164 Taking out the whole installation of the above item as per direction of EIC. 1 Items
174 165 Considering present pandemic situation actual quantity of work may differ from BOQ which shall be finalized by the EIC / competent authority in due course..
175 166 ADD GST @ 12% 1 Items
Disclaimer :
We takes all possible care for accurate & authentic tender information, however Users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender.
Tell us about your Product / Services,
We will Find Tenders for you

Copyright © 2020 · All Rights Reserved. Terms of Usage | Privacy Policy

For Tender Information Services Visit : TenderDetail