| 1 | 1 | Note applicable for all Items of BOQ:- (FOR SPECIAL ATTENTION OF BIDDERS)\nIf the lowest quoted amount is less than the estimated cost of the work mentioned in NIT, the lowest bidder will have to submit FDR/BGB in favour of Accepting Officer within 7 (Seven) days of opening of Financial Bid for the difference in estimated cost and quoted amount. In case the said FDR/BGB is not submitted within stipulated period as mentioned above, the contractor shall be banned for 6 months and his bid will be rejected. FDR/BGB will be released only after completion of entire work and production of proof for the payment of wages to all the workers employed under the contract is paid not less than the minimum wages notified by the Central Govt./State Govt. whichever is more | | | |
|---|
| 2 | 2 | Outsourcing of maintenance and operation services to operate swimming pool and diving pool of E/M installation in two shift per day from 1st shift 0600hrs to 1400 hrs and 2nd shift 1400hrs to 2200 hrs including sundays and holidays by deploying One FGM per shift.\n(a) Machinery/equipment in main swimming pool\n(i) Centrifugal mono block pump set 10 HP - 05 Nos\n(ii) Vertical type pressure filter capacity 125 CUM/hr- 04 Nos\n(iii) Wall mounting constant flow dosing pump set manual strok adjustment 10% to 100%- 3 Nos\n(iv) LT panel board -01 No\n(b) Machinery/equipment in Diving pool\n(i) Centrifugal mono block pump set 10 HP - 03 Nos\n(ii) Vertical type pressure filter capacity 101 CUM/hr- 02 Nos\n(iii) Wall mounting constant flow dosing pump set manual strok adjustment 10% to 100%- 2 Nos | | 660 | Per Shift |
|---|
| 3 | 2.01 | (c) Details of routine works\n(i) To operate pump sets installed at Filtration plant of swimming pool and diving pool and carry out checks of pipe line ,pumps and panel boards for trouble free functioning.\n(ii) To operate suction and delivery valves of pump sets and inlets and out lets valves of balancing tanks.\n(iii) To operate inlet valves of swimming pool diving pool and changing room\n(iv) To operate main valves of gravity main of swimming pool and diving pool feeding at S2 Tank\n(v) To operate chlorination and filtration equipment and carry out routine check of chlorination plant and recording the results\n(vi) To carry out periodical back wash of filtration unit and carry out minor repair in control panels dozing pumps and arresting leakage etc. | | | |
|---|
| 4 | 3 | Outsourcing of maintenance and operation services to operate Splash pool of E/M installation in one shift per day from 0800hrs to 1600 hrs including Sunday and holidays by deploying ONE FGM per shift. \n(a) Splash pool Equipments\n (i) Centrifugal mono block pump set 10 HP - 03 Nos\n (ii) Vertical type pressure filter capacity 125 CUM/hr- 02 Nos\n (iii) Wall mounting constant flow dosing pump set manual stroke adjustment 10% to 100%- 2 Nos\n(iv) LT panel board - 01 No\n(b) Details of Routine work\n(i) To operate pump sets installed at Filtration plant of splash pool and carry out checks of pipe line ,pumps and panel boards for trouble free functioning.\n(ii) To operate suction and delivery valves of pump sets and inlets and out lets valves of balancing tanks.\n(iii) To operate inlet valves of Splash pool \n(iv) To operate main valves of gravity feeding from S2 Tank\n(v) To operate chlorination and filtration equipment and carry out routine check of chlorination plant and recording the results\n(vi) To carry out periodical back wash of filtration unit and carry out minor repair in control panels dozing pumps and arresting leakage etc. | | 330 | Per Shift |
|---|
| 5 | 3.01 | NOTES FOR SL ITEM NO 2 & 3 \n The quoted rate shall be deemed to include the following:-\n (i) The operator shall be well qualified in respective trade and wear approved uniform having firms name while on duty as directed by the Engineer- in- charge. \n(ii) Cost of stationary required to maintain daily log sheet ,attendance register ,daily chlorine results register and store accounting register all as directed by the Engineer -in- charge.\n (iii) The contractor shall prepare duty roster well in advance and got it approved by the Engineer-in charge and one copy of the roster shall be displayed in the notice board of complaint cell.\n (iv) The contractor shall display the details viz Name of the Contractor, contact number and wages paid by contrctor on the notice board at the site of installation.\n (v) Material required for replacement will be measured and paid under relevant items of Sch'A' as supply only under item Nos. 6 to 11.\n(vi) If the cotractor fails to provide any of the above requirements, a recovery of Rs 500/- per document per month shall be recovered from the payments due to the contractor | | | |
|---|
| 6 | 4 | Carryout the suction sweeping of swimming pool and diving pool for removing the sediment slits/dirt and cleaning the walls, over flow channel, and channel grills etc all as directed.\nNOTE:-\nSweeping shall be carried out twice in a week. In special case, due to un-hygienic conditions, the frequency of sweeping to be increased as directed by Engineer in charge. | | 88 | Job |
|---|
| 7 | 5 | Carryout the suction sweeping of splash pool for removing the sediment slits/dirt and cleaning the walls, over flow channel, and channel grills etc all as directed. \nNOTE:-\nSweeping shall be carried out once in a week. In special case, due to un-hygienic conditions, the frequency of sweeping to be increased as directed by Engineer in charge. | | 44 | Job |
|---|
| 8 | 6 | Supply only bleaching powder commercial Grade 1 superior quality complete all as specified and directed.\n | | 200 | Kg |
|---|
| 9 | 7 | Supply only Poly aluminium Chloride Alum (Inorganic soluble powder) complete all as specified and directed.\n | | 900 | Kg |
|---|
| 10 | 8 | Supply only calcium hydrochloride based Granular disinfectant for water treatment complete all as specified and directed. Make:- Purichlor/M/S Grasim industries Ltd or any other make approved by the NMPT committee of E-in-C's Branch.\n | | 1000 | Kg |
|---|
| 11 | 9 | Supply only copper sulphate crystal type complete all as specified and directed. | | 50 | Kg |
|---|
| 12 | 10 | Supply only deep leaf net with 5 mtr Extension handle complete all as specified and directed. | | 3 | Each |
|---|
| 13 | 11 | Supply only Algae brush with 3 mtr handle complete all as specified and directed. | | 3 | Each |
|---|
| 14 | 12 | Dismantling the Electrical connection from motor and taking out the burnt 10 HP motor from beds ,transporting to civil work shop, opening the motor and removing the burnt/old defective winding carefully cleaning the inner parts, rewinding the motor with same gauge supper enamelled copper wire of good insulation, varnishing, heating/drying and reassembling the motor and transporting to site , refixing on the existing beds ,connecting the electrical connection ,testing and commissioning all as directed. | | 2 | Job |
|---|
| 15 | 13 | Dismantling the Electrical connection from motor and taking out the burnt 7.5 HP motor from beds ,transporting to civil work shop, opening the motor and removing the burnt/old defective winding carefully cleaning the inner parts, rewinding the motor with same gauge supper enamelled copper wire of good insulation, varnishing, heating/drying and reassembling the motor and transporting to site , refixing on the existing beds ,connecting the electrical connection ,testing and commissioning all as directed. | | 2 | Job |
|---|
| 16 | 14 | Opening and servicing/overhauling the monoblock pump and motor 10 HP and replacing the defective bearing greasing replacing the burnout gland rope, studs, nuts, bolts, washers ,air releasing valve ,rubber gasket ,metal filling, turing/ grinding and balancing the shaft etc. varnishing the winding, drying and refixing the same all as directed at site. | | 2 | Job |
|---|
| 17 | 15 | Opening and servicing/overhauling the monoblock pump and motor 7.5 HP and replacing the defective bearing, greasing replacing the burnout gland rope, studs, nuts, bolts, washers ,air releasing valve ,rubber gasket ,metal filling, turing/ grinding and balancing the shaft etc. varnishing the winding, drying and refixing the same all as directed at site. | | 2 | Job |
|---|
| 18 | 16 | Supply and fix PVC Flexible Vacuum hose pipe of size 50mm dia complete all as specified and directed. | | 100 | RM |
|---|
| 19 | 17 | Material and labour for preparing the surface by scrapping with wire brush and emery paper and painting with one coat of red oxide zinc chromate primer and two coat of synthetic enamel paint of existing shade including writing MES NO of size 2.5cm height and length depend upon number of letters out going and incoming electric supply, marking the water flow direction for the following equipments installed at Swimming pool and Diving pool all as directed at site and as specified.\n(a) Monoblock pump set 10 HP -8 Nos\n(b) Vertical pressure filter of size 2000mm dia x 1500mm height - 6 Nos with butterfly valves \n(c)Water pipe lines and connected valves\n(d) Panel boards of size 2mx1.5mx0.5M - 2 No\n(e)Sluice valve chambers & covers.\n(f) Cu-Ag dual ionisation plant - 02 nos | | 1 | Job |
|---|
| 20 | 18 | Material and labour for preparing the surface by scrapping with wire brush and emery paper and painting with one coat of red oxide zinc chromate primer and two coats of synthetic enamel paint of existing shade including writing MES NO of size 2.5cm height and length depend upon numer of letters, out going and incoming electric supply, marking the water flow direction for the following equipments installed at URU swimming pool all as directed at site and as specified.\n(a) Monoblock pump set 7.5 HP -3 Nos\n(b) Vertical pressure filter of size 2000mm dia x 1500mm height - 2 Nos with butterfly valves \n(c)Water pipe lines and connected valves\n(d)Sluice valve chamber & cover\n(e) panel board of size 2x1.5x0.5 m \n(f) Cu-Ag dual Ionisation equipment - 01no | | 1 | Job |
|---|
| 21 | 19 | Taking down unserviceable MCB, supply and fix MCB,SP 6-32 Ambs 'C' Curve,3 pole ,complete all as specified and directed. Make:- Havells/Legrand/L&T | | 1 | Each |
|---|
| 22 | 20 | Taking down unserviceable MCCB, supply and fix MCCB, 415V,160Amps, type DU-250C, 4 pole,25 KA complete all as specified and directed.\nMake:- Havells/Legrand/L&T. | | 1 | Job |
|---|
| 23 | 21 | Taking down unserviceable MCCB, supply and fix MCCB, 415V, 125Amps, type DU-250C, 4 pole,25 KA complete all as specified and directed. \nMake:- Havells/Legrand/L&T. | | 1 | Job |
|---|
| 24 | 22 | Supply and Laying flat submersible 1100 Volts grade,3 core copper conductor PVC insulated and PVC sheathed cable of 6 Sq mm including taking down old material. \nMake:- Finolex/Havells/Polycap. | | 50 | RM |
|---|
| 25 | 23 | Supply and fix Direct on line starter, 415 Volts 5 HP to 7.5 HP complete all as specified and directed.\nMake:- L&T/Havells/C&G. | | 1 | Each |
|---|
| 26 | 24 | Supply and fix FASD (Fully automatic star delta starter), in sheet metal enclosure type MK 1F (motor rating AC-3 duty , 415 Volts, 50 Hz,3Phase) relay range 13 - 21 Amps. \nMake:- L&T/Havells/C&G. | | 1 | Each |
|---|
| 27 | 25 | Supply and fix FASD (Fully automatic star delta starter), in sheet metal enclosure type ML 1.5F (motor rating AC-3 duty , 415 Volts, 50 Hz,3Phase) relay range 13 - 21 Amps. \nMake:- L&T/Havells/C&G. | | 1 | Each |
|---|
| 28 | 26 | Supply and fixing single phase preventor 415Volts 50Hz including taking down of old material. \nMake:- L&T/C&S/Schncider | | 2 | Each |
|---|
| 29 | 27 | Supply and fix in replacement LED indication lamp of panel mounting type including taking down old material complete all as specified and directed by Engineer-in-Charge. | | 10 | Each |
|---|
| 30 | 28 | Supply and fix in replacement of Digital Ammeter -0-100 Amps Accuracy class 1.1 ,0.5, flush mounting 96x96 mm complete all as specified and directed by Engineer-in-Charge.\nMake:- AE/L&T/Havells | | 1 | Each |
|---|
| 31 | 29 | Supply and fix in replacement of Digital Voltmeter -0-500 Volts Input voltage 50-550 VAC ,Flush mounting 96x96 mm complete all as specified and directed by Engineer-in-Charge.\nMake:- AE/L&T/Havells | | 1 | Each |
|---|
| 32 | 30 | Supply and fix in replacement ON/OFF push button for pump starter any make/type including taking down old material complete all as specified and directed by Engineer-in-Charge.\nMake:- AE/L&T/Havells | | 10 | Each |
|---|
| 33 | 31 | Taking out sluice valves, refacing, regrinding including nut and bolts with washer and refixing of following sizes:- | | | |
|---|
| 34 | 31.01 | (a) 300mm bore | | 1 | Each |
|---|
| 35 | 31.02 | (b) 200 mm bore | | 1 | Each |
|---|
| 36 | 31.03 | (c) 150 mm bore | | 1 | Each |
|---|
| 37 | 31.04 | (d) 100 mm bore | | 1 | Each |
|---|
| 38 | 32 | Supply and fixing in replacement of Centric Butterfly valves wafer type PN1.0 as per BS-5155 &IS-13095 lever operated body grey cast iron disc -SGI Epoxy coated Disc seal-Nitrile/Epdm 250 &300 mm in Gear operated of size 150 mm bore, with all fittings confirming to IS specification all as specified. | | 1 | Each |
|---|
| 39 | 33 | Supply and Fix NRV (Non Return Valve) flanged and drilled type 150mm dia including taking down the existing unserviceable valve.\nMake:- Kirloskar/Kartar | | 1 | Each |
|---|
| 40 | 34 | Material and labour for Cleaning of Swimming pool of size 50mx20mx6m by acid solution complete all as specified and directed. | | 1 | Job |
|---|
| 41 | 35 | Material and labour for Cleaning of Diving pool of size 18mx18mx6m by acid solution complete all as specified and directed. | | 1 | Job |
|---|
| 42 | 36 | Material and labour for Cleaning of URU Swimming pool of size 20mx10mx2m by acid solution complete all as specified and directed.\n | | 1 | Job |
|---|
| 43 | 37 | Supply and fix Digital portable type PH meter range 0-14 PH complete all as specified and directed.\n | | 6 | Each |
|---|
| 44 | 38 | Supply and fix Digital Total Dissolved Solids water purity tester with leather case and temperature display complete all as specified and directed.\n | | 3 | Each |
|---|
| 45 | 39 | Supply and fixing Chlorine test kit with coloured ample complete with all testing fitment and 100 ML othodine solution in rexine finish wooden box/rexin box confirming to IS specification complete all as specified and directed. | | 6 | Each |
|---|