| 1 | CC Drain and Metal Road | As per SSR | 37.13 | 1 Cum | 287.50 | 10675.00 |
| Supply and spreading of Gravel for Shoulders in uniform layers with consolidating each deposited layer by watering and ramming including cost and conveyance of gravel and water to work site and all operational, incidental charges, hire charges of T & P etc., complete for finished item of work. as per drawing and technical specification Clause 305.3.9 MORD & 304 MORTH |
| 2 | CC Drain and Metal Road | Clause 405 MORD / 404 MORTH | 81.68 | 1 Cum | 1979.60 | 161694.00 |
| WBM Grading 3, laying, spreading and compacting stone aggregates of specific sizes 40mm to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel Roller 80-100 kN in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405 MORD / 404 MORTH. including cost and conveyance of gravel and water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work (Spreading Loos100 mm Thick To Commpacted to 75 mm Thick) |
| 3 | CC Drain and Metal Road | Clause 405 MORD / 404 MORTH | 42.08 | 1 Cum | 1799.17 | 75709.00 |
| WBM Grading 2, laying, spreading and compacting stone aggregates of specific sizes 60mm to 63 mm to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel Roller 80-100 kN in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 2 as per Technical Specification Clause 405 MORD / 404 MORTH.including cost and conveyance of gravel and water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work (Spreading Loos100 mm Thick To Commpacted to 75 mm Thick) |
| 4 | CC Drain and Metal Road | Clause 401.4 as per Technical Specification Clause 408 MORD. | 86.63 | 1 Cum | 526.17 | 45582.00 |
| Construction of granular sub-base by providing local material spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at once and compacting with smooth wheel roller to achieve the desired density complete as per Clause 401.4 as per Technical Specification Clause 408 MORD including cost and conveyance of gravel and water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work (Spreading Loos 225 mm Thick To Commpacted to 150 mm Thick) |
| 5 | CC Drain and Metal Road | 305 MORD / 304 MORTH | 57.75 | 1 Cum | 230.77 | 13327.00 |
| Earthwork in Excavation for Road work as per Drawing and Technical Specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious materials and disposal upto a lead of 50m, dressing of sides and bottom and backfilling in trenches with excavated suitable materials as per Technical Specification 305 MORD / 304 MORTH for ROAD |
| 6 | CC Drain and Metal Road | As per SSR | 238.00 | 1 Kg | 66.43 | 15810.00 |
| Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and technical specifications for Bars below 36 mm dia including over laps and wastage, where they are not welded |
| 7 | CC Drain and Metal Road | Table 9 of IS 456 BLD-CSTN-2-14 | 2.64 | 1 Cum | 5893.26 | 15558.00 |
| Vibrated Reinforced Cement Concrete M- 30 design mix (Cement:fine aggregate: coarse aggregate) corresponding to Table 9 of IS 456 using10mm & 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including Seigniorage charges, sales & other taxes on all materials including all operational, incidental and labour charges such as machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work and including centering, shuttering. for finished item of work For Culvert CoverSlabs BLD-CSTN-2-14 laying I Postion, curing for 21 day etc., complete for side walls of drains upto 600mm depth |
| 8 | CC Drain and Metal Road | Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH | 5.33 | 1 Cum | 5274.78 | 28115.00 |
| Plain Cement concrete (1:2:4) Nominal using 20 mm metal l with concrete mixture including cost and convence of all the material and labor charges (APSS No. 402) with minimum cement content as per IS code from standards uppliers approved by the department including , centering, shuttering, laying concrete, vibrating, curing etc etc.,complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH laying I Postion, curing for 21 day etc., complete for V-NOTCH |
| 9 | CC Drain and Metal Road | Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH | 4.62 | 1 Cum | 5048.29 | 23323.00 |
| Plain cement concrete M15 nominal mix using 20mm 10mm dia graded metal including cost and convence of all the material and labor charges etc.,complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH FOR CULVERT |
| 10 | CC Drain and Metal Road | Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH | 54.00 | 1 Cum | 5048.29 | 272608.00 |
| Plain cement concrete M15 nominal mix using 20mm 10mm dia graded metal including cost and convence of all the material and labor charges etc.,complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200 MORTH FOR DRAIN |
| 11 | CC Drain and Metal Road | BLD-CSTN-2-5 | 21.98 | 1 Cum | 3911.15 | 85967.00 |
| Plain Cement concrete (1:4:8) using 40 mm metal with with concrete mixture including cost and convence of all the material and labor charges etc.,complete as per drawings and technical specification |
| 12 | CC Drain and Metal Road | 305.3.9 MORD & 304 MORTH | 21.98 | 1 Cum | 321.54 | 7067.00 |
| Supply and Filling of Stone dust gravel in uniform layers with consolidating each deposited layer by watering and ramming including cost and conveyance of gravel and water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. as per drawing and technical specification Clause 305.3.9 MORD & 304 MORTH |
| 13 | CC Drain and Metal Road | 305 MORD / 304 MORTH | 188.87 | 1 Cum | 230.77 | 43586.00 |
| Earthwork in excavation for Roads & Drains as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH |