| 1 | Construction | APSS NO 1301 & 1318 | 50.00 | Rmt | 630.00 | 31500.00 |
| Supplying and laying, filling, jointing and testing SWG SP-1 pipes of ISI make confirming to IS 1651 & 4127 1st quality with air tight Cement joints in CM (1.5:1)prop. including excavation of trenches and socket pits in any soil (except rock requiring blasting) and refilling with watering and tamping including cost and conveyance of all materials to site and all labour charges for finished item of work (APSS NO 1301 & 1318) 152.40mm dia SWG pipe upto 3\ depth |
| 2 | Construction | As directed by Engineer-in-chief | 5.00 | each | 7321.00 | 36605.00 |
| Constructing 904.0 mm (3?0?) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½? thick both inside and outside fitted with 20? dia RCC manhole covers and frames including excavating pits up to a depth of 904 mm (3\-0\") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification and including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, cost of seigniorage charges on all materials and all incidental and operational, labour charges like mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item of work as per Standard specification. |
| 3 | Construction | As directed by Engineer-in-chief | 10.00 | each | 223.00 | 2230.00 |
| Supplying and fixing of 15 mm brass body CP finish bib tap of not less than 300 grams weight screw type (full turn) with internal /external threaded conenction conforming to IS 8931 including cost and conveyance of all materials, labour charges etc., complete for finished item of work in all floors. |
| 4 | Construction | As directed by Engineer-in-chief | 50.00 | Rmt | 193.00 | 9650.00 |
| Supplying & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with fittings in ground or on wall including cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions etc. with necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling masonry walls and making good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials and labour charges complete for finished item of work. 28.60mm OD pipe - SDR 13.5 |
| 5 | Construction | As directed by Engineer-in-chief | 20.00 | Rmt | 146.00 | 2920.00 |
| Supplying & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with fittings in ground or on wall including cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions etc. with necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling masonry walls and making good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials and labour charges complete for finished item of work. 22.20mm OD pipe - SDR 13.5 |
| 6 | Construction | As directed by Engineer-in-chief | 5.00 | Nos | 159.70 | 799.00 |
| Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm. Prince/sudhakar or any ISI brand and fixing all special such as plain bends, off sets, door bends, single junctions, double junctions as per site requirement, fixing with PVC clamps if necessary with required number of Bombay nails including cost and conveyance of all materials to site, labour charges etc.complete for finished item of work at all floor levels. (APSS No. 1302 1319 & 1326) for 110 mm dia single socket pipe |
| 7 | Construction | As directed by Engineer-in-chief | 1.00 | each | 223.00 | 223.00 |
| Supplying and fixing PPR ball valve of 25 mm dia confirming to DIN standards 8077/8092 , Indian make heavy type including cost and conveyance of all materials , labour charges etc. complete for finished item of work. |
| 8 | Construction | As directed by Engineer-in-chief | 1.00 | each | 233.00 | 233.00 |
| Supplying and fixing PPR ball valve of 32 mm dia confirming to DIN standards 8077/8092 , Indian make heavy type including cost and conveyance of all materials , labour charges etc. complete for finished item of work. |