| 1 | Hafeez Baba Nagar | Standard Specification | 76.18 | cum | 132.40 | 10086.23 |
| Carting away the surplus excavated materials such as rock / earth the site to a suitable distance of about 10 Kms including loading, unloading, conveyance charges and dumping the carted material at the contractors cost labour charges all leads and lifts all other incidental and operational charges etc complete as directed by the HMWSSB Engineers |
| 2 | Hafeez Baba Nagar | Standard Specification | 241.94 | cum | 34.90 | 8443.71 |
| Refilling the pipe line trenches with using excavated soils other than sand with standard specification including watering and tamping in layers of 225mm etc., complete to the finished item as directed by the H.M.W.S.&.S. Board Engineers. |
| 3 | Hafeez Baba Nagar | Standard Specification | 150.00 | 10/sqm | 579.00 | 8685.00 |
| Oil painting to the existing grill/cage with enamel iron premier coat and 2 coats of synthetic oil paint inclduing cost of brushes and other materials with all applicable taxes etc., as directed by the HMWSSB Engineers |
| 4 | Hafeez Baba Nagar | Standard Specification | 3.53 | cum | 5948.00 | 20996.44 |
| Laying of CC road restoration (1:2:4) 150mm thick hard broken metal and 12mm hard broken metal dust free dust free metal using screened, sand, cement, including cost and conveyance of all materials eto site all taxes and duties machine mixing, centring leads and lifts, laying in position vibrating, curing and all labour charges, hire charges of mixer and providng expansition joints with bituminous pads including cost of pads etc carging of surplus earth with a lead of 8 Km including cost and conveyance of loading and unloading etc as directed by the HMWSSB Engineers on 300mm dia 10n length pipe on 300mm dia 12m length pipe on 300mm dia 6m length pipe |
| 5 | Hafeez Baba Nagar | Standard Specification | 6.00 | cum | 5948.00 | 35688.00 |
| Laying of CC road restoration (1:2:4) 150mm thick hard broken metal and 12mm hard broken metal dust free dust free metal using screened, sand, cement, including cost and conveyance of all materials eto site all taxes and duties machine mixing, centring leads and lifts, laying in position vibrating, curing and all labour charges, hire charges of mixer and providng expansition joints with bituminous pads including cost of pads etc carging of surplus earth with a lead of 8 Km including cost and conveyance of loading and unloading etc., as directed by the HMWSSB Engineers |
| 6 | Hafeez Baba Nagar | Standard Specification | 6.00 | cum | 923.00 | 5538.00 |
| Supply, delivery and filling quarry dust wherever required as directed by the Deptl officers including cost and conveyance of quarry dust stacking levelling, watering and tamping, rolling all leads labour charges and other incidental and operational charges etc., complete as directed by the H.M.W.S.&.S. Board Engineers. |
| 7 | Hafeez Baba Nagar | Standard Specification | 12.50 | cum | 9400.00 | 117500.00 |
| Repairing of rust formed on the boides of air valve and sluice valve and painting them with anti corrisive epoxy and paint them with oil based paint emulsion air valve and sluice valve are shifted etc., complete as directed by the H.M.W.S.&.S. Board Engineers. |
| 8 | Hafeez Baba Nagar | Standard Specification | 10.00 | Each | 337.98 | 3379.80 |
| Supply and delivery of 200mm dia rubber gasket including cost and conveyance etc., complete as directed by the H.M.W.S.&.S. Board Engineers. |
| 9 | Hafeez Baba Nagar | Standard Specification | 15.00 | Each | 199.23 | 2988.45 |
| Supply and delivery of 300mm dia rubber gasket including cost and conveyance etc., complete as directed by the H.M.W.S.&.S. Board Engineers. |
| 10 | Hafeez Baba Nagar | Standard Specification | 70.00 | One Hp Hr | 1127.90 | 78953.00 |
| Engaging/Hiring truck mounted derric crane 5 ton inclding operator charges, fuel charges crew charges etc., complete as directed by the H.M.W.S.&.S. Board Engineers.( 7Hr for removing + 7 hr of refixing) |
| 11 | Hafeez Baba Nagar | Standard Specification | 240.00 | One Hp Hr | 384.00 | 92160.00 |
| Bailing out of water including hire charges of diesel pump set, fuel and labour charges etc. complete as directed by the H.M.W.S.&.S. Board Engineers. |
| 12 | Hafeez Baba Nagar | Standard Specification | 65.00 | Hrs | 1261.12 | 81972.80 |
| Hire charges for engaging Power Generator 100KVA for site welding including cost of fuel, wages for driver helper including transportation from Hyderabad to work site and back etc., including transportation charges etc., complete as directed by the HMWS&SB Engineers ( 300mmx90degree bend) |
| 13 | Hafeez Baba Nagar | Standard Specification | 20.00 | Each | 29000.00 | 580000.00 |
| Cutting of MS pipe with the help of gas cutter including hire charges of gas cutter and removal of cut pipe from the trench and lowering the MS pipe into the excavated trenches of 3mtr length with the help of crane and jointing with providing with making spor welding of MS pipe with using Electric Welding rectifier gas cyinder, electric welding rectifier gas cylinder, electrodes welders helpers skilled and unskilled labour etc., including transportation charges etc., complete as directed by the HMWS&SB Engineers ( 300mmx90degree bend) |
| 14 | Hafeez Baba Nagar | Standard Specification | 10.00 | Each | 644.00 | 6440.00 |
| Removing and refixing of 300mm dia sluice valve D/F joints using new nut bolts rubber in place of damaged including all materials labour charges etc., complete as directed by the HMWS&SB Engineers |
| 15 | Hafeez Baba Nagar | Standard Specification | 10.00 | Each | 432.00 | 4320.00 |
| Removing and refixing of 200mm dia air valve D/F joints using new nut bolts rubber in place of damaged including all materials labour charges etc., complete as directed by the HMWS&SB Engineers |
| 16 | Hafeez Baba Nagar | Standard Specification | 10.00 | Each | 6462.00 | 64620.00 |
| Manufacturing supply and delivery of 300mm dia 90 degree bend with S/F joint using MS pipe including cost and conveyance etc., complete as directed by the HMWS&SB Engineers |
| 17 | Hafeez Baba Nagar | Standard Specification | 10.00 | Each | 4208.00 | 42080.00 |
| Manufacturing supply and delivery of 0.90mX0.80m cover for the grill using 8mm thick MS sheet including cost and conveyance etc., complete as directed by the HMWS&SB Engineers |
| 18 | Hafeez Baba Nagar | Standard Specification | 40.00 | Rmt | 5692.00 | 227680.00 |
| Manufacturing supply and delivery of 300mm dia with D/F joint using MS pipe including cost and conveyance etc., complete as directed by the HMWS&SB Engineers |
| 19 | Hafeez Baba Nagar | Standard Specification | 491.25 | Rmt | 128.69 | 63218.96 |
| Barricading, hoarding, lighting and Watching etc., for water supply pipe (WS pipe) line trenches etc., complete as directed by the HMWS&SB Engineers. |
| 20 | Hafeez Baba Nagar | Standard Specification | 260.00 | cum | 343.00 | 89180.00 |
| Earth work excavation and depositing on banks for pipe line trenches with an initial lead of 10 m. and lift of 2 m in all available soils including labour charges, all operational and incidental charges etc., complete as directed by the H.M.W.S.& S. Board Engineers. |
| 21 | Hafeez Baba Nagar | Standard Specification | 39.00 | cum | 2793.00 | 108927.00 |
| Cutting open C.C Road surface including labour charges all leads and other incidental and operational charges tool and plants etc. complete to the finished item of work as directed by the HMWS&SB Engineers. |
| 22 | Hafeez Baba Nagar | Standard Specification | 19.13 | cum | 1342.00 | 25672.46 |
| Cutting open B.T Road with 75mm thick including labour charges all leads and other incidental and operational charges tool and plants etc. complete to the finished item of work as directed by the HMWS&SB Engineers. |