| 1 | Civil and Electrical Works | As directed by Engineer incharge | 2.00 | Each | 7000.00 | 14000.00 |
| Complete Dismantling & Repair to the 250mm Non Return Valve with new SS metal Bushes complete all welding cutting ,Grinding & fitting etc complete. |
| 2 | Civil and Electrical Works | As directed by Engineer incharge | 2.00 | Each | 7000.00 | 14000.00 |
| Complete Dismantling & Repair to the 250mm Dia Sluice Valve with new checks,packng Rope, Gun metal Bushes complete all cutting ,Grinding & fitting etc complete. |
| 3 | Civil and Electrical Works | As directed by Engineer incharge | 1.00 | Each | 12000.00 | 12000.00 |
| Complete Dismantling & Repair to the 450mm Dia Sluice Valve with new checks,packng Rope, Gun metal Bushes complete all cutting ,Grinding & fitting etc complete. |
| 4 | Civil and Electrical Works | As per IS Codes | 3.00 | Each | 57500.00 | 172500.00 |
| Supply and delivery of single chamber DI Air Valve 100mm dia PN16 with body and cover in Ductile Iron of grade SG 400/12 or equivalent grade as per IS 2896-part 2 - 1985 and subsequent revisions including cost and conveyance of all materials, labour charges, etc. complete for pressure main. |
| 5 | Civil and Electrical Works | As per IS Codes | 1.00 | Each | 70150.00 | 70150.00 |
| Supply and delivery of single chamber DI Air Valve 150mm dia PN16 with body and cover in Ductile Iron of grade SG 400/12 or equivalent grade as per IS 2896-part 2 - 1985 and subsequent revisions including cost and conveyance of all materials, labour charges, etc. complete for pressure main. |
| 6 | Civil and Electrical Works | As per IS Codes | 2.00 | Each | 54326.00 | 108652.00 |
| Supply, erection of PN-16 250 mm dia DI D/F Gate valves (soft seated) Resilient seated Sluice Valve confirming to IS:14846/2000 including cost and conveyance to site etc., including transportation charges, transit conveyance etc., complete. For Sub-gravity main-1 & 2 |
| 7 | Civil and Electrical Works | As per IS Codes | 1.00 | Each | 259668.00 | 259668.00 |
| Supply, erection of PN-16 400 mm dia DI D/F Gate valves (soft seated) Resilient seated Sluice Valve confirming to IS:14846/2000 including cost and conveyance to site etc., including transportation charges, transit conveyance etc., complete. For Sub-gravity main-1 |
| 8 | Civil and Electrical Works | As per relevant standard specifications | 2500.00 | 1 Kg | 100.80 | 252000.00 |
| Hydro-Mechanical Works:Manufacturing, supply, erection and testing of M.S.Pipes and pipe specials as required including cost of M.S.Sheet for pipes, M.S.Plate for flanges as per ISI, cutting bending, rolling, welding fabrication including transportation to site laying in position aligning, jointing, welding if necessary at site including cost of jointing materials like bolts and nuts rubber packing, painting with one coat of red oxide and two coats of anticorrisive bitumen paint including cost and conveyance of all materials, labour charges etc., complete |
| 9 | Civil and Electrical Works | As directed by Engineer incharge | 1.00 | Job | 7500.00 | 7500.00 |
| Repairs for internal wiring in jackwell cum pumphouse |
| 10 | Civil and Electrical Works | As directed by Engineer incharge | 1.00 | Job | 47980.00 | 47980.00 |
| Rectification of Double pole structure |
| 11 | Civil and Electrical Works | As directed by Engineer incharge | 1.00 | Each | 221700.00 | 221700.00 |
| Repairs to Exisiting Transformer Capacity of 200K VA-11KV/430KV. DYN1 / ONAN, Copper wound transformer, out door type, plinth mounted, oil cooled type, 1st filling of oil and manufactured in accordance with IS 2026 with standard fittings such as rated and terminal making plates, Bucholts relay on load tap changer(OLTC) from +5% to -5%, in steps of 1.25%, OLTC panel and giving inter connections, two earthing terminals, two lifting lugs etc., complete |
| 12 | Civil and Electrical Works | As per latest ISI code | 2.00 | Set | 293674.00 | 587348.00 |
| Manufacturing and Supply of Control panel board. The panel board should be metal clad,dust and vermin proof floor mounted industrial type, indore type for controlling 2Nos 90 HP Vertical Turbine pumps. The panel board with accessories should internallu wired neccessary earthing terminal shall internally wired electrical system shall comply as per IE rules and relevant ISS. The thickness of sheets to be used for fabrication of panel board should be 16 guage. The cable boxes wherever necessary with adequate cabling space for termination of cable is to be provided. The details of the panel board are furnished in annexure- I |
| 13 | Civil and Electrical Works | As per IE rules | 50.00 | 1 RMT | 1346.34 | 67317.00 |
| Supply of 3.5 Core 240 sqmm XLPE PVC armoured Aluminium LT Cable from Transformer to Panel Board. |
| 14 | Civil and Electrical Works | As directed by Engineer in charge | 6.00 | Each | 25000.00 | 150000.00 |
| Supply and fixing of Bearings (make:SKF6222/C3) |
| 15 | Civil and Electrical Works | As directed by Engineer in charge | 2.00 | Each | 110000.00 | 220000.00 |
| Dismantling , Repairs and rewinding to existing jyothi make 90 HP/67KW HT motor all required accessories etc complete for fixing of the Motor. |
| 16 | Civil and Electrical Works | As directed by Engineer in charge | 1.00 | Each | 307500.00 | 307500.00 |
| --do-- for Pump - II |
| 17 | Civil and Electrical Works | As directed by Engineer in charge | 1.00 | Each | 291500.00 | 291500.00 |
| Electro-Mechanical works: Dismantling and Repairs to existing Vertical Turbine pumps of capable of discharging 4.41 cusecs/124.87 LPS at a total head of 123.52 ft/37.66 mts Overhauling the all spare parts, replacement bearing box and repairs and replacement of pump bowel, pb neck ring, pb impeller, pb guide bush,oil tube, Oil tube with T.T nut sets,S.S 410head shaft, line shaft thronging, Oil gland, nut bolts refitting pump overhauling Assumbling of pump and all required accessories etc complete for fixing of the pumpset to the existing pipe line are to be provided. excluding valves rates etc.,complete |
| 18 | Civil and Electrical Works | 126.0 | 520.64 | 1 kg | 60.23 | 31358.15 |
| Providing High Yeild Strength Deformed steel bars/ TMT from prime producers (TATA/SAIL/VSP/Jindal) (Fe 500 grade as per IS 1786-2008 of different diameters, including labour charges for cutting, bending to required sizes and shapes, placing in position with cover blocks of approved size and tying with binding wire of 20 SWG, forming grills for reinforcement work as per approved designs and drawings, including cost and conveyance of steel bars and binding wire from approved sources to site of work, cover blocks and all incidental, operational labour charges cutting,bending,placing in position, tying etc., complete for finished item of work for Raft and well steining |
| 19 | Civil and Electrical Works | 402 & 403 | 3.37 | 1 Cu.m | 5746.58 | 19365.97 |
| P.C.C. grade M15(1:2.5:5) corresponding IS 456 using weigh batcher/ mixer with 20mm size graded machine crushed hard granite metal from approved quarry including cost & conveyance of all materials like cement, fine aggregate, coarse aggregate, water etc. to site including all operational incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing etc complete for finished item of work with minimum cement content as per IS code from standard suppliers approved by the department including pumping, centering, shuttering, laying concrete, vibrating, curing etc With Water Lead. |
| 20 | Civil and Electrical Works | 402 & 403 | 3.89 | 1 Cu.m | 6917.25 | 26908.10 |
| R.C.C. grade M20 (Design mix) corresponding IS 456 using weigh batcher/ mixer with 20mm size graded machine crushed hard granite metal from approved quarry including cost & conveyance of all materials like cement, fine aggregate, coarse aggregate, water etc. to site including all operational incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing etc complete but excluding cost of steel and its fabrication charges for finished item of work with minimum cement content as per IS code from standard suppliers approved by the department including pumping, centering, shuttering, laying concrete, vibrating, curing etc for Stiening with water lead. |
| 21 | Civil and Electrical Works | 402 & 403 | 2.40 | 1 Cu.m | 6545.37 | 15708.89 |
| R.C.C. grade M20 (Design mix) corresponding IS 456 using weigh batcher/ mixer with 20mm size graded machine crushed hard granite metal from approved quarry including cost & conveyance of all materials like cement, fine aggregate, coarse aggregate, water etc. to site including all operational incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing etc complete but excluding cost of steel and its fabrication charges for finished item of work with minimum cement content as per IS code from standard suppliers approved by the department including pumping, centering, shuttering, laying concrete, vibrating, curing etc for Raft with water lead. |
| 22 | Civil and Electrical Works | 402.0 | 1.80 | 1 Cu.m | 4610.45 | 8298.81 |
| Cement Concrete in (1:4:8) proportion using 40mm size hard granite machine crushed metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, dewatering , all leads and lifts and labour charges for machine mixing, laying, ramming, curing etc. complete with water lead. |
| 23 | Civil and Electrical Works | 308 & Spl. Specifica-tions | 7.20 | 1 Cu.m | 102.70 | 739.44 |
| Construction of Guide wall around MDC: Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Depth upto 3 m |
| 24 | Civil and Electrical Works | 901 & 904 | 65.94 | 10 Sq.m | 4123.35 | 27189.37 |
| Plastering with 20 mm thick in two coats with base coat in Cement Mortar (1:5)- 16 mm thick and top coat in CM (1:4) - 4mmthick including cost and conveyance of all materials like cement, sand, water etc., to site and operational incidental charges and all labour charges for mixing the mortar, finishing, scaffolding lift, delifts charges, curing including cutting of grooves as directed by the Engineer etc. complete for finished item of work |
| 25 | Civil and Electrical Works | 501 & 504 | 7.17 | 1 Cu.m | 6607.37 | 47374.84 |
| Increasing the Height of Existing DC:Brick masonry for super structure with cement mortar (1:5) prop: using second class bricks 23 x 11 x 7 cms from approved source having minimum crushing strength of 40 Kg/Sq.cm. Including cost and conveyance of all materials like cement, sand, curing etc. to site, including all labour charges like mixing cement mortar, scaffolding charges, lift charges etc., complete for finished item of work |
| 26 | Civil and Electrical Works | 308 & Spl. Specifica-tions | 71.25 | 1 Cu.m | 102.70 | 7317.38 |
| Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Depth upto 3 m for arresting Leakages with MS Pipe in Gravity main (for RCC 450,400 and 300 mm dia |
| 27 | Civil and Electrical Works | As directed by Engineer in charge | 3.00 | Each | 6297.00 | 18891.00 |
| Rectification of leakeges in existing Sub-Gravity main PVC Pipe line of 200mm dia including earth work excavation, PVC pipe of length 1m, MS flanges and tail pieces including refilling, all operational and incidental charges etc., complete for finished item of work. for Sub-Gravity main - 3 |
| 28 | Civil and Electrical Works | As directed by Engineer in charge | 100.00 | Each | 2122.00 | 212200.00 |
| Rectification of leakeges in existing Sub-Gravity main RCC Pipe line of 300 mm dia including earth work excavation in all soils, chieseling the joints and applying CM (1:1) 20MM thick for placing wire mesh 20 gauge, placing wire mesh 20 gauge and applying CM (1:1) 20MM thick over mesh including refilling, all operational and incidental charges etc., complete for finished item of work. for Sub-Gravity main -2 |
| 29 | Civil and Electrical Works | As directed by Engineer in charge | 40.00 | Each | 2455.00 | 98200.00 |
| Rectification of leakeges in existing Sub-Gravity main RCC Pipe line of 400 mm dia including earth work excavation in all soils, chieseling the joints and applying CM (1:1) 20MM thick for placing wire mesh 20 gauge, placing wire mesh 20 gauge and applying CM (1:1) 20MM thick over mesh including refilling, all operational and incidental charges etc., complete for finished item of work. for Sub-Gravity main -1 |
| 30 | Civil and Electrical Works | As directed by Engineer in charge | 120.00 | Each | 2578.00 | 309360.00 |
| Rectification of leakeges in existing Gravity main RCC Pipe line of 450 mm dia including earth work excavation in all soils, chieseling the joints and applying CM (1:1) 20MM thick for placing wire mesh 20 gauge, placing wire mesh 20 gauge and applying CM (1:1) 20MM thick over mesh including refilling, all operational and incidental charges etc., complete for finished item of work. for Gravity main -3 |
| 31 | Civil and Electrical Works | As directed by Engineer in charge | 10.00 | Each | 10728.00 | 107280.00 |
| Arresting Leakages in Gravity Mains: Rectification of leakeges in existing Gravity main PVC Pipe line of 250mm dia including earth work excavation, PVC pipe of length 1m, MS flanges and tail pieces including refilling, all operational and incidental charges etc., complete for finished item of work. for Gravity main - 1&2 |
| 32 | Civil and Electrical Works | 402.0 | 11.97 | 1 Cu.m | 6207.30 | 74301.38 |
| Providing and laying insitu M-15 ( 28 days cube compressive strength not less than 15 N / sqmm ) grade cement concrete using 20 mm down size approved, clean, hard, gradedaggregates for well bottom plug by tremie or skip box method including cost of all materials,machinery, labour, batching, mixing, placing in position as per detailed specifications etc.,complete with initial lead upto 50 m and all lifts for leakages |
| 33 | Civil and Electrical Works | 308 & Spl. Specifica-tions | 41.04 | 1 Cu.m | 102.70 | 4214.81 |
| Arresting Leakages in Pressure Main: Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Depth upto 3 m |
| 34 | Civil and Electrical Works | As diected by Engineer in charge | 400.00 | 1 Sqm | 1.90 | 760.00 |
| Clearing thin jungle growth ( more than 50 percent open space ) including bushes upto 30 cm / parthenium and other weeds including burning or disposing off the same as directed etc., complete. |
| 35 | Civil and Electrical Works | 126.0 | 483.00 | 1 kg | 60.23 | 29091.09 |
| Providing High Yeild Strength Deformed steel bars/ TMT from prime producers (TATA/SAIL/VSP/Jindal) (Fe 500 grade as per IS 1786-2008 of different diameters, including labour charges for cutting, bending to required sizes and shapes, placing in position with cover blocks of approved size and tying with binding wire of 20 SWG, forming grills for reinforcement work as per approved designs and drawings, including cost and conveyance of steel bars and binding wire from approved sources to site of work, cover blocks and all incidental, operational labour charges cutting,bending,placing in position, tying etc., complete for finished item of work for Raft, well steining & Slab |
| 36 | Civil and Electrical Works | 403 & 403 | 0.97 | 1 Cu.m | 9580.04 | 9292.64 |
| --do-- for Beams |
| 37 | Civil and Electrical Works | 402 & 403 | 10.00 | 1 Sqm | 1313.96 | 13139.60 |
| --do-- for 150mm thick slab. |
| 38 | Civil and Electrical Works | 402 & 403 | 0.54 | 1 Cu.m | 6817.72 | 3681.57 |
| R.C.C. grade M20 (Design mix) corresponding IS 456 using weigh batcher/ mixer with 20mm size graded machine crushed hard granite metal from approved quarry including cost & conveyance of all materials like cement, fine aggregate, coarse aggregate, water etc. to site including all operational incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing etc complete but excluding cost of steel and its fabrication charges for finished item of work with minimum cement content as per IS code from standard suppliers approved by the department including pumping, centering, shuttering, laying concrete, vibrating, curing etc for Stiening |
| 39 | Civil and Electrical Works | 402 & 403 | 0.95 | 1 Cu.m | 6445.84 | 6123.55 |
| R.C.C. grade M20 (Design mix) corresponding IS 456 using weigh batcher/ mixer with 20mm size graded machine crushed hard granite metal from approved quarry including cost & conveyance of all materials like cement, fine aggregate, coarse aggregate, water etc. to site including all operational incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing etc complete but excluding cost of steel and its fabrication charges for finished item of work with minimum cement content as per IS code from standard suppliers approved by the department including pumping, centering, shuttering, laying concrete, vibrating, curing etc for Raft |
| 40 | Civil and Electrical Works | 402.0 | 0.63 | 1 Cu.m | 4510.92 | 2841.88 |
| Cement Concrete in (1:4:8) proportion using 40mm size hard granite machine crushed metal from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, dewatering , all leads and lifts and labour charges for machine mixing, laying, ramming, curing etc. complete |
| 41 | Civil and Electrical Works | 308 & Spl. Specifica-tions | 3.47 | 1 Cu.m | 135.60 | 470.53 |
| Construction of RCC Ramp at Jackwell: Excavation for foundation in Ordinary soils including boulders upto 0.30 m diameter for intake structure and other appurtenant works and placing the excavated soil neatly in dump area or disposing off the same as directed etc., complete with initial lead upto 1 km and all lifts. |