Tamil Nadu Transmission Corporation Limited-TANTRANSCO has published Nctps I Se Mi Circle Mpm Dn Fabrication Erection And Commissioning Of The Hot Air Gate Assembly Nctps I Se Mi Circle Mpm Dn Fabrication Erection And Commissioning Of The Hot Air Gate Assembly Including Removal And Re Fixing Insulation Work In Unit Ii Duri. Submission Date for this Tender is 24-08-2020. Fabrication Work Tenders in Work Tamil Nadu. Bidders can get complete Tender details and download the document.
Sr No | CorrigendumDate | Corrignedum | CorrigendumType | NewSubmissionDate |
1 | 14-Aug-2020 | Exemption from payment of EMD to Micro Small Industries under MSMED Act 2006 Corrigendum | Technical Bid | 17-08-2020 |
2 | 18-Aug-2020 | EXTENSION OF DUE DATE | Date | 24-08-2020 |
Name of Work: NCTPS – I – SE/MI circle - MPM Dn. – Fabrication, Erection and commissioning of the Hot air gate assembly including removal and re fixing insulation work in Unit II during the Overhaul period for the year 2020-21. | |||||
---|---|---|---|---|---|
Sl. No. | Item Description | Item Code / Make | Quantity | Units | |
1 | 1 | Charges for transportation of Hot air gate assembly’s and required iron & steel from store for fabrication of supports. Provision of temporary supports & frames to facilitate erection as per the site engineer instruction including temporary supports for mounting 5 Ton capacity chain blocks, for lifting and lowering the gate assembly arrangement and temporary platform etc., Charges for providing the temporary supports and platform supports arrangement for fixing 5 Ton capacity chain blocks-4 Nos, for mounting and removing the existing Hot Air gate assembly, including cost of consumables and T&Ps. (Hot Air Gate Assembly and Iron & Steel in TANGEDCO scope). | BI01010001010000000000000515BI0100001113 | 2 | Nos |
2 | 2 | Fabrication of new GI/MS Duct Assembly With MS Angle Duct frames , erection and commissioning of fabricated new duct assembly (scafolding), including cost of consumables and T&P’s. | BI01010001010000000000000515BI0100001114 | 4 | m² |
3 | 3 | Dismantling of insulation. Estimate for 10 sq. mtr, including cost of consumables and T&P’s. | BI01010001010000000000000515BI0100001115 | 30 | m² |
4 | 4 | Reinsulation, including cost of consumables and T&Ps. | BI01010001010000000000000515BI0100001116 | 30 | m² |
5 | 5 | Removal of deteriorated G.I sheets and re fixing the new / same G.I.sheets after fabricating to the required contour shape, making grooves and tightening with lock screws (1/4”), including cost of consumables and T&Ps. | BI01010001010000000000000515BI0100001117 | 30 | m² |
6 | 6 | Removing the GI strips and retainer plates and providing back with new/ same strips and retainer plates, including cost of consumables and T&Ps. | BI01010001010000000000000515BI0100001118 | 30 | m² |