Road Transport and Highways Government Departments Closing in 0 days TDR #25075299

Nhidcl/Meghalaya/Tura Bypass/Nh-51/2020 Consultancy Services For Preparation Of Detailed Project Report For Construction To 2-Lane Tura Bypass Between Existing Km 95 . 00 To Km 101 . 00 Of Nh-51 On Epc Mode In The State Of Meghalaya

Issued by Government Departments · Meghalaya, Meghalaya
Tender Value
Ref. Documents
Estimated cost
Bid Submission
08 Sep 2020
0 days left
EMD
Ref. Documents
Bank guarantee accepted
Document Fee
5900
Non-refundable
Tender Type
Online

Tender Overview

Competition Type
NCB
Bidding Type
Tender
Location / State
Meghalaya → Meghalaya
EMD Exemption
Not Available
Quantity
Not Available

Project Description

Nhidcl/Meghalaya/Tura Bypass/Nh-51/2020 Consultancy Services For Preparation Of Detailed Project Report For Construction To 2-Lane Tura Bypass Between Existing Km 95 . 00 To Km 101 . 00 Of Nh-51 On Epc Mode In The State Of Meghalaya , Remuneration For Local Staff ( Inclusive Of Per Diem Allowance ) , Team Leader Cum Sr . Highway Engineer , Highway Cum Pavement Engineer , Senior Bridge Engineer , Traffic And Safety Expert , Material Cum Geotechnical Engineer Cum Geologist , Senior Survey Engineer , Environment Specialist , Quantity Surveyor/Documentation Expert , Land Acquisition Expert , Utility Expert , Sub Professional Staff ( To Be Assessed By Consultant As Per Requirement Of Assignment ) , Position , Position , Position , Support Staff ( Inclusive Of Per Diem Allowance ) , Office Manager , Typist , Office Boy , Transportation ( Fixed Costs ) , The Vehicles Hired By The Consultant Shall Include The Cost For Rental , Drivers , Operation , Maintenance , Repairs , Insurance , Etc . , Duty Travel To Site ( Fixed Costs ) , Trips , Office Rent ( Fixed Costs ) The Rent Cost Includes Maintenance , Cleaning , Repairs , Etc . , Office Rent , Office Supplies , Utilities And Communication ( Fixed Costs ) , Office Supplies , Drafting Supplies , Computer Running Costs , Domestic And International Communication , Office Furniture And Equipment ( Rental ) , Office Furniture And Equipment , Reports And Document Printing , Monthly Report ( 3 Copies Per Month ) , Inception Report & Qap , Environment And Social Impact Screening Report , Draft Feasibility Report , Final Feasibility Report , Strip Plan With L . A . Reports , Draft La And Clearances I Report , Final La And Clearances I Report , Draft Environmental Assessment Report& Rap , Final Environmental Assessment Report& Rap , Draft Detailed Design Report & Drawings Etc . Draft Emp , Draft Bidding Documents , Final Detailed Project Report With Bill Of Quantities , Cost Estimates , Updated Drawings Etc . Final Emp , Final Bidding Documents , Draft 3 ( A ) , 3 ( A ) And 3 ( D ) & 3G Notification For Land Acquisition ( 3 Copies Each ) , La & Clearances Ii Report , Survey And Investigation A . Topographical Survey ( Fixed Rate ) , Topographic Survey Including Hire Charges For Equipment ( Gps , Total Station , Auto Level Etc . ) And Supply Of Survey Teams Comprising Of Project Survey Filed Staff Etc . Inclusive Of Cost Of Materials , Labourer . , Detailed Topographic Surveys Using Mobile/ Aerial Lidar Or Equivalent Technology , Sub-Surface Utilities Detection Using Ground Penetrating Radar , Induction Locator Or Better Technologies , Survey/Investigation Using Network Survey Vehicle As Per Tor , Investigation ( Fixed Cost ) ( Lumpsum ) , Road And Bridge Inventory , Bbd Test And Pavement Evaluation , Roughness Survey , Axle Load Survey , Material Survey And Investigation , Sub-Grade Investigation , Traffic Survey , Socio-Economic & Census Survey/Studies , Land Acquisition Studies , Any Other Investigations/Surveys , Sub-Soil Investigation ( Boring ) ( Rate/M ) , A ) In Soil Other Than Hard Rock , B ) In Hard Rock , Fixing Boundary Pillars , Procuring And Fixing Boundary Pillars And Its Installation , Complete In All Respect As Per Irc:25 , 1967: Wherever The Proposed Alignment Follows The Existing Alignment , The Boundary Pillars Shall Be Fixed At An Interval Of 200M On Either Side Of Proposed Right Of Way . Wherever There Is A Proposal Of Realignment Of The Existing Highway And/Or Construction Of New Bypasses , Consultant Shall Fix Boundary Pillars Along The Proposed Alignment On The Extreme Boundary On Either Side Of The Project Highway At 50 M Interval , Other Miscellaneous Expenses ( Like Da , Internal Travel Expenses Other Incidentals ) ( Fixed Cost )

BOQ

Consultancy Services for Preparation of Detailed Project Report for “construction to 2-Lane Tura Bypass between existing km 95+00 to km 101+00 of NH-51 on EPC mode in the State of Meghalaya
Sl.No.Item DescriptionItem Code / MakeQuantityUnits
11Remuneration for Local Staff (inclusive of per diem allowance)BI01010001010000000000000515BI0100001112
21.01Team Leader cum Sr. Highway EngineerBI01010001010000000000000515BI01000011139Month
31.02Highway cum Pavement EngineerBI01010001010000000000000515BI01000011145Month
41.03Senior Bridge EngineerBI01010001010000000000000515BI01000011155Month
51.04Traffic and Safety ExpertBI01010001010000000000000515BI01000011164Month
61.05Material cum GeoTechnical Engineer cum Geologist6Month
71.06Senior Survey Engineer7Month
81.07Environment Specialist3Month
91.08Quantity Surveyor/Documentation Expert6Month
101.09Land Acquisition Expert10Month
111.1Utility Expert4Month
122Sub Professional Staff (To be assessed by consultant as per requirement of assignment)
132.01Position1Month
142.02Position1Month
152.03Position1Month
163Support Staff (inclusive of per diem allowance)
173.01Office Manager300Days
183.02Typist300Days
193.03Office Boy300Days
204Transportation (Fixed Costs)
214.01The vehicles hired by the Consultant shall include the cost For rental, drivers, operation, maintenance, repairs, insurance, etc.300Days
225Duty Travel to Site (Fixed Costs)
235.01Trips10Trips
246Office Rent (Fixed Costs) \nThe rent cost includes maintenance, cleaning, repairs, etc.
256.01Office Rent300Days
267Office Supplies, Utilities and Communication (Fixed Costs)
277.01Office Supplies300Days
287.02Drafting Supplies300Days
297.03Computer Running Costs300Days
307.04Domestic and International Communication300Days
318Office Furniture and Equipment (Rental)
328.01Office Furniture and Equipment300Days
339Reports and Document Printing
349.01Monthly Report (3 copies per month)30Nos
359.02Inception Report & QAP3Nos
369.03Environment and Social Impact Screening Report4Nos
379.04Draft Feasibility Report4Nos
389.05Final Feasibility Report6Nos
399.06Strip Plan with L.A. Reports6Nos
409.07Draft LA and Clearances I Report4Nos
419.08Final LA and Clearances I Report4Nos
429.09Draft Environmental Assessment report& RAP4Nos
439.1Final Environmental Assessment report& RAP6Nos
449.11Draft Detailed Design Report & Drawings etc. Draft EMP4Nos
459.12Draft Bidding Documents4Nos
469.13Final Detailed Project Report with Bill of Quantities, Cost Estimates, Updated Drawings etc. Final EMP6Nos
479.14Final Bidding Documents6Nos
489.15Draft 3(a) ,3(A) and 3(D)& 3G notification for land acquisition (3 copies each)9Nos
499.16LA & Clearances II Report6Nos
5010Survey and Investigation A. Topographical Survey (Fixed Rate)
5110.01Topographic Survey including hire charges for equipment (GPS, Total Station, Auto Level etc.) and supply of survey Teams comprising of project survey filed staff etc. inclusive of cost of materials, labourer.30Km
5210.02Detailed topographic surveys using mobile/ aerial LiDAR or equivalent technology30Km
5310.03Sub-surface utilities detection using Ground Penetrating Radar, Induction Locator or better technologies1Lumpsum
5410.04Survey/Investigation using Network Survey Vehicle as per TOR30Km
5511Investigation (Fixed cost)(lumpsum)
5611.01Road and Bridge Inventory1LumpSum
5711.02BBD Test and Pavement Evaluation1LumpSum
5811.03Roughness Survey1LumpSum
5911.04Axle Load Survey1LumpSum
6011.05Material Survey and Investigation1LumpSum
6111.06Sub-grade Investigation1LumpSum
6211.07Traffic Survey1LumpSum
6311.08Socio-economic & Census Survey/Studies1LumpSum
6411.09Land Acquisition Studies1LumpSum
6511.1Any other investigations/surveys1LumpSum
6611.11Sub-Soil Investigation (Boring) (Rate/m)
6711.12a) In soil other than hard rock2000Meter
6811.13b) In hard rock300Meter
6912Fixing Boundary pillars
7012.01Procuring and fixing boundary pillars and its installation, complete in all respect as per IRC:25,1967: Wherever the proposed alignment follows the existing alignment, the boundary pillars shall be fixed at an interval of 200m on either side of proposed Right of Way. Wherever there is a proposal of realignment of the existing Highway and/or construction of New Bypasses, Consultant shall fix boundary pillars along the proposed alignment on the extreme boundary on either side of the project Highway at 50 m interval1Lumpsum
7113.16Other Miscellaneous expenses (Like DA, internal travel expenses other incidentals)(Fixed Cost)1LumpSum

AI Tender Summary

OUR REF NO 25075299
AUTHORITY Government Departments
TENDER VALUE Ref. Documents
LAST DATE 08-09-2020
Authority
Authority Name National Highways and Infrastructure Development Corporation Limited
Work Description Nhidcl/Meghalaya/Tura Bypass/Nh-51/2020 Consultancy Services For Preparation Of Detailed Project Report For Construction To 2-Lane Tura Bypass Between Existing Km 95 . 00 To Km 101 . 00 Of Nh-51 On Epc Mode In The State Of Meghalaya , Remuneration For Local Staff ( Inclusive Of Per Diem Allowance ) , Team Leader Cum Sr . Highway Engineer , Highway Cum Pavement Engineer , Senior Bridge Engineer , Traffic And Safety Expert , Material Cum Geotechnical Engineer Cum Geologist , Senior Survey Engineer , Environment Specialist , Quantity Surveyor/Documentation Expert , Land Acquisition Expert , Utility Expert , Sub Professional Staff ( To Be Assessed By Consultant As Per Requirement Of Assignment ) , Position , Position , Position , Support Staff ( Inclusive Of Per Diem Allowance ) , Office Manager , Typist , Office Boy , Transportation ( Fixed Costs ) , The Vehicles Hired By The Consultant Shall Include The Cost For Rental , Drivers , Operation , Maintenance , Repairs , Insurance , Etc . , Duty Travel To Site ( Fixed Costs ) , Trips , Office Rent ( Fixed Costs ) The Rent Cost Includes Maintenance , Cleaning , Repairs , Etc . , Office Rent , Office Supplies , Utilities And Communication ( Fixed Costs ) , Office Supplies , Drafting Supplies , Computer Running Costs , Domestic And International Communication , Office Furniture And Equipment ( Rental ) , Office Furniture And Equipment , Reports And Document Printing , Monthly Report ( 3 Copies Per Month ) , Inception Report & Qap , Environment And Social Impact Screening Report , Draft Feasibility Report , Final Feasibility Report , Strip Plan With L . A . Reports , Draft La And Clearances I Report , Final La And Clearances I Report , Draft Environmental Assessment Report& Rap , Final Environmental Assessment Report& Rap , Draft Detailed Design Report & Drawings Etc . Draft Emp , Draft Bidding Documents , Final Detailed Project Report With Bill Of Quantities , Cost Estimates , Updated Drawings Etc . Final Emp , Final Bidding Documents , Draft 3 ( A ) , 3 ( A ) And 3 ( D ) & 3G Notification For Land Acquisition ( 3 Copies Each ) , La & Clearances Ii Report , Survey And Investigation A . Topographical Survey ( Fixed Rate ) , Topographic Survey Including Hire Charges For Equipment ( Gps , Total Station , Auto Level Etc . ) And Supply Of Survey Teams Comprising Of Project Survey Filed Staff Etc . Inclusive Of Cost Of Materials , Labourer . , Detailed Topographic Surveys Using Mobile/ Aerial Lidar Or Equivalent Technology , Sub-Surface Utilities Detection Using Ground Penetrating Radar , Induction Locator Or Better Technologies , Survey/Investigation Using Network Survey Vehicle As Per Tor , Investigation ( Fixed Cost ) ( Lumpsum ) , Road And Bridge Inventory , Bbd Test And Pavement Evaluation , Roughness Survey , Axle Load Survey , Material Survey And Investigation , Sub-Grade Investigation , Traffic Survey , Socio-Economic & Census Survey/Studies , Land Acquisition Studies , Any Other Investigations/Surveys , Sub-Soil Investigation ( Boring ) ( Rate/M ) , A ) In Soil Other Than Hard Rock , B ) In Hard Rock , Fixing Boundary Pillars , Procuring And Fixing Boundary Pillars And Its Installation , Complete In All Respect As Per Irc:25 , 1967: Wherever The Proposed Alignment Follows The Existing Alignment , The Boundary Pillars Shall Be Fixed At An Interval Of 200M On Either Side Of Proposed Right Of Way . Wherever There Is A Proposal Of Realignment Of The Existing Highway And/Or Construction Of New Bypasses , Consultant Shall Fix Boundary Pillars Along The Proposed Alignment On The Extreme Boundary On Either Side Of The Project Highway At 50 M Interval , Other Miscellaneous Expenses ( Like Da , Internal Travel Expenses Other Incidentals ) ( Fixed Cost )
Basic Detail
Tender No NHIDCL/Meghalaya/Tura Bypass/NH-51/2020
Bidding Type Tender
Location
City Meghalaya
State Meghalaya
Key Dates
Publish Date 04 Aug 2020
Submission Date 08 Sep 2020
Open Date 11 Sep 2020
Finance
Tender Value Ref. Documents
Tender Fee 5900
EMD Ref. Documents
Exemption Not Available
Document List
RFP.pdf
214175B5-E0D9-4795-A0DC-129B99A2E3E7.html
Tendernotice_1.pdf
BOQ_603511.xls

Unlock Full AI Tender Summary

Get instant access to the complete AI-generated analysis — scope, eligibility, timeline & more.

Instant Access Secure Free
Your details are secure and used only for document delivery.

Tender Timeline

Aug 04, 2020
11:30 IST

Tender Published

Tender notice published.

Completed
Sep 08, 2020
17:00 IST

Bid Submission Deadline

Online submission via eProcurement portal.

Completed
Sep 11, 2020

Bid Opening Date

Technical bids will be opened and evaluated.

Completed

Tender Documents

Download All (ZIP) ↓
pdf

RFP.pdf

html

214175B5-E0D9-4795-A0DC-129B99A2E3E7.html

pdf

Tendernotice_1.pdf

xls

BOQ_603511.xls

Disclaimer

We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender

TenderDetail
Loading tenders