Various Works Under Business Plan Against Sanctioned Package No . 40 / 2020-21 In The Jurisdiction Of Edd-Iv , Iglas .-1 Cartage Of Following Pcc / St Poles Store Centre Or From Any Other Place To The Respective Site Of Work Through The Kachha Pacca Road Including The Work Of Its Loading & Unloading At The Respective Ends Also Including The Work Of Dragging Etc. And Also Including The Cost Of Labour, T&P Carrier Etc. Required For Proper Completion Of Work. ( Dist. 0 To 50 Kms. ) . 2 Pcc Poles 8.5 Mtr. / 9 Mtr. 3 St Poles 9 / 11 Mtr. 4 Cartage Of Line Material Viz Conductor / Cable, Ab Cable, Transformer, Gi Earth Wire, Cross Arm, Angle, Channel, Insulator, Clamps & Other Line Material From Store Centre Or From Any Other Place To The Respective Site Of Work Through The Kachha Pacca Road Including The Work Of Its Loading & Unloading At The Respective Ends Also Including The Work Of Dragging Etc. And Also Including The Cost Of Labour, T&P Carrier Etc. Required For Proper Completion Of Work. ( Dist. 0 To 50 Kms. ) . 5 Erection Of Single Support Including Complete H.T / L.T Fittings As Per Respo Manual And As Per Direction Of Engineer Incharge Including The Cost Of Labour, T & P And Carrier Etc. Required For Proper Completion Of Work. 6 Pcc Poles 8.5 Mtr. / 9 Mtr. 7 St Poles 9 / 11 Mtr. 8 Laying, Sagging, Stringing, Binding And Jumpering Etc. Of New / Old Line Conductor On The Newly Erected Pole As Per Respo Manual And As Per Direction Of Supervising Engineer, Including The Cost Of Arrangement Of Labour, T&P Carrier Etc. Required For Proper Completion Of Work. 9 Acsr Raccoon Conductor 10 Replacement / Re-Fixing Of Following Damaged / Disturbed / De-Aligned Accessories:- 11 11 Kv Pin Insulator 12 11 Kv V-Type Cross Arm 13 F-Bracket 14 Grouting Of Poles As Per Respo Norms Including Cost Of Grouting Material ( Cement: Sand: Brick Ballast ) Size As Per Respo Norms. This Qty Also Includes The Additional Work Of Old & Existing Lt Line Which Has To Be Converted Into Ht Line. Presently The Supports Of Old Line Do Not Have Grouting. 15 Pcc Poles 8.5 Mtr. 16 St Poles 9 / 11 Mtr. 17 Making The Plinth Of St Pole 9 / 11 Mtr. 18 Chopping Of Tree Branches Which Are Touching To 11 Kv / Lt Lines. 19 Guarding Of 11 Kv Line By Laying Two Nos. Gi Wire Parallel And Fixing Of Lacings ( Tilli ) At A Distance At 2-3 Mtr. As Per Respo Manual And Also Including The Cost Of Arragement Of Labour, T & P Etc. Required For Proper Completion Of Work. 20 Dismantling And Removal Of Existing Conductor / Cable / Gi Wire From The Various Area Preparing Their Coils And Then Stacking In The Respective Je’S ( Store ) As Per Direction Of Supervising Engineer. It Includes The Work Of Cartage, Cost Of Labour, T&P Carrier Etc. Required For Proper Completion Of Work. 21 Acsr Weasal Conductor / Gi Wire 22 Fixing Of Earthing Rod As Per Respo Manual And As Per Direction Of Supervising Engineer Including The Cost Of Labour, T&P Etc. Required For Proper Completion Of Work. 23 Erection And Grouting Of Stay Set Including The Work Of Nozzling Etc. As Per Respo Manual And Also Including The Cost Of Arrangement Of All Grouting Material, Labour, T&P Etc. Required For Proper Completion Of Work. 24 Providing And Fixing Of Stay Insulator. 25 Dismentling Of Old And Damaged Pole After Dismentling Of All Accessories. 26 Pcc Poles 8.5 Mtr. / 9 Mtr. 27 St Poles 9 / 11 Mtr. 28 Safe Carriage Of Old Line Material Viz. Conductor, G.I. Earth Wire, Abc Conductor, Cross Arm, Angle, Channel, Insulators, Clamps & Other Line Material From Any Other Place Or From Site Of Work To Store Centre / J.E. Store Of Its Loading & Unloading At The Respective Ends Including The Cost Of Labour, T&P And Carrier Etc. Required For Proper Completion Of Work. 29 Straightening Of Tilted Pcc / St Poles At Various Places As Per Direction Of Je.
BOQ
| Name of Work: Various works under business plan against sanctioned package No. 40/2020-21 in the jurisdiction of EDD-IV IGLAS. | |||||
|---|---|---|---|---|---|
| Sl.No. | Item Description | Item Code / Make | Quantity | Units | |
| 1 | 1 | Cartage of following PCC/ST poles Store centre or from any other place to the respective site of work through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of dragging etc. and also including the cost of labour, T&P carrier etc. required for proper completion of work. (Dist. 0 to 50 Kms.). | |||
| 2 | 1.01 | PCC poles 8.5 Mtr./ 9 Mtr. | 12 | Nos. | |
| 3 | 1.02 | ST poles 9/11 Mtr. | 2 | Nos. | |
| 4 | 2 | Cartage of line material viz Conductor/Cable, AB Cable, Transformer, GI earth wire, Cross Arm, Angle, Channel, Insulator, Clamps & other line material from Store centre or from any other place to the respective site of work through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of dragging etc. and also including the cost of labour, T&P carrier etc. required for proper completion of work. (Dist. 0 to 50 Kms.). | 14 | Qtl. | |
| 5 | 3 | Erection of single support including complete H.T/L.T fittings as per RESPO manual and as per direction of Engineer incharge including the cost of labour, T & P and carrier etc. required for proper completion of work. | |||
| 6 | 3.01 | PCC poles 8.5 Mtr./ 9 Mtr. | 12 | Nos. | |
| 7 | 3.02 | ST poles 9/11 Mtr. | 2 | Nos. | |
| 8 | 4 | Laying, sagging, stringing, binding and jumpering etc. of new/old line conductor on the newly erected pole as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work. | |||
| 9 | 4.01 | ACSR Raccoon Conductor | 10877 | Mtr. | |
| 10 | 5 | Replacement/Re-fixing of following damaged/ disturbed/de-aligned accessories:- | |||
| 11 | 5.01 | 11 KV Pin Insulator | 27 | Nos. | |
| 12 | 5.02 | 11 KV V-type Cross Arm | 14 | Nos. | |
| 13 | 5.03 | F-Bracket | 14 | Nos. | |
| 14 | 6 | Grouting of poles as per RESPO norms including cost of grouting material (cement: sand: brick ballast) size as per RESPO norms. This qty also includes the additional work of old & existing LT line which has to be converted into HT line. Presently the supports of old line do not have grouting. | |||
| 15 | 6.01 | PCC poles 8.5 Mtr. | 12 | Nos. | |
| 16 | 6.02 | ST poles 9/11 Mtr. | 2 | Nos. | |
| 17 | 7 | Making the plinth of ST pole 9/11 Mtr. | 2 | Nos. | |
| 18 | 8 | Chopping of tree branches which are touching to 11 KV/LT lines. | 10 | Nos. | |
| 19 | 9 | Guarding of 11 KV line by laying two nos. GI wire parallel and fixing of lacings (tilli) at a distance at 2-3 Mtr. as per RESPO manual and also including the cost of arragement of labour, T & P etc. required for proper completion of work. | 480 | Mtr. | |
| 20 | 10 | Dismantling and removal of existing conductor/cable/GI Wire from the various area preparing their coils and then stacking in the respective JE’s (Store) as per direction of Supervising Engineer. It includes the work of cartage, cost of labour, T&P carrier etc. required for proper completion of work. | |||
| 21 | 10.01 | ACSR Weasal Conductor/ GI Wire | 1300 | Mtr. | |
| 22 | 11 | Fixing of earthing rod as per RESPO manual and as per direction of supervising engineer including the cost of labour, T&P etc. Required for proper completion of work. | 14 | Nos. | |
| 23 | 12 | Erection and grouting of stay set including the work of nozzling etc. as per RESPO manual and also including the cost of arrangement of all grouting material, labour, T&P etc. required for proper completion of work. | 12 | Nos. | |
| 24 | 13 | Providing and fixing of stay insulator. | 12 | Nos. | |
| 25 | 14 | Dismentling of old and damaged pole after dismentling of all accessories. | |||
| 26 | 14.01 | PCC poles 8.5 Mtr./ 9 Mtr. | 12 | Nos. | |
| 27 | 14.02 | ST poles 9/11 Mtr. | 2 | Nos. | |
| 28 | 15 | Safe carriage of Old line material viz. Conductor, G.I. Earth wire, ABC conductor, Cross Arm, Angle, Channel, Insulators, Clamps & other line material from any other place or from site of work to store centre/ J.E. Store of its loading & unloading at the respective ends including the cost of labour, T&P and carrier etc. required for proper completion of work. | 1 | Job | |
| 29 | 16 | Straightening of tilted PCC/ST poles at various places as per direction of JE. | 2 | Nos. |
AI Tender Summary
Tender Timeline
Tender Published
Tender notice published.
CompletedBid Submission Deadline
Online submission via eProcurement portal.
CompletedBid Opening Date
Technical bids will be opened and evaluated.
CompletedTender Documents
Download All (ZIP) ↓We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender