| 1 | Civil works | - | 47.70 | Cum | 389.97 | 18602.00 |
| Supply and Filling good gravel (excluding rock) in trenches, sides of foundations and basement with initial lead in layers not exceeding 15 cm thick, consolidating each deposited layer by watering and ramming including cost and conveyance of water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. |
| 2 | Civil works | - | 6.00 | Each | 2464.00 | 14784.00 |
| Manufacture as per BIS:12592 ( Part 1 & 2) Supply & delivery of Manhole Covers M20 Heavy duty 20 cm thick 560 mm dia clear opening and frames any where in A.P., F.O.R destimation including loading, un-loading and stacking at site, sales tax, octroi and other Govt levies etc., as applicable. |
| 3 | Civil works | - | 40.00 | Each | 774.34 | 30974.00 |
| Construction of Additional 0.10mt depth to 0.90mt circular dia sewer man hole of 0.90 mts depth with cement bricks of size (flyash cement blocks of size 225X100X60mm with compressive strength of 50kg/ sqm IS:12894- 1990 class -V ) in CM 1:4 and for corbelling portion with internal plastreng 20 mm thick (CM 1:3 prop) and external plasterng 12mm thick ( CM 1:3prop) excluding the cost and fixing charges of CI steps, including the cost and conveyance of all materials at site complete and curing for 21 days complete all taxes seignarage charges as per specification etc complete. |
| 4 | Civil works | - | 99.38 | Cum | 80.35 | 7985.00 |
| Carting of excavated earth with Manually, loading, transportation, unlaoding to an average lead of about 5 KMts, from the circle-18 jurisdition, including the tranport vehicles, cost and conveyance of all materials and all labour charges but excluding contractor profit and over head charges etc., complete for finished item of work as directed by the GHMC officers. |
| 5 | Civil works | - | 2252.50 | Rmt | 50.97 | 114810.00 |
| Saw cut joints for freshly laid concrete pavement including all materials and labour charges. |
| 6 | Civil works | - | 1192.50 | sqm | 64.79 | 77262.00 |
| Providing of Mechanical trawelling, finishing with sound edges and corners, including hire and operational charges of machinery, labour, fuel etc complete for finished item of work |
| 7 | Civil works | - | 178.88 | Cum | 4900.95 | 876682.00 |
| Supply and placing of the Ready Mix Concrete (RMC) M20 grade Standard Design Mix Concretegrade as per IS4926- 2003 with minimum cement content as per IScode456- 2000 using 20mm graded metal, from standard suppliers approved by the department including pumping, laying concrete, vibrating / screed / pan vibrating, curing etc. complete but excluding cost of steel and its fabrication charges, centering, shuttering for finished item of work. |
| 8 | Civil works | - | 93.41 | Cum | 4185.95 | 391010.00 |
| Supply and placing of the Ready Mix Concrete (RMC) M10 grade Standard Design Mix Concretegrade as per IS4926- 2003 with minimum cement content as per IScode456- 2000 using 20mm graded metal, from standard suppliers approved by the department including pumping, laying concrete, vibrating / screed / pan vibrating, curing etc. complete but excluding cost of steel and its fabrication charges, centering, shuttering for finished item of work. |
| 9 | Civil works | - | 93.41 | Cum | 697.21 | 65126.00 |
| Supply and Filling with Stone Crusher dust finer than 3mm with not more than 10% passing 0.075 seive (excluding rock) in trenches, sides of foundations and basement with initial lead in layers not exceeding 15 cm thick, consolidating each deposited layer by watering and ramming including cost and conveyance of water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. |
| 10 | Civil works | - | 198.75 | Cum | 216.58 | 43045.00 |
| Earth work excavation for foundations and depositing on bank for all lifts and with an initial lead of 10m including all operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, etc. complete for finished item of work excluding seigniorage excluding dewatering charges etc as per SS - 20 B (APSS 308). Earth work excavation Ordinary Soil-Manual Means-Upto 3 m depth |